HomeMy WebLinkAboutFurniture Systm - North WingCITY OF PALM DESERT
PALM DESERT REDEVELOPMENT AGENCY
STAFF REPORT
REQUEST: APPROVE PURCHASE AND APPROPRIATION OF MONIES FOR A
MODULAR FURNITURE SYSTEM IN THE AMOUNT OF $61,372 FOR
THE OPEN OFFICE AREAS IN THE NORTH WING OF CITY HALL
SUBMITTED BY: MISSY WIGHTMAN, PROJECT COORDINATOR
VENDOR: TOTAL PLAN BUSINESS INTERIORS, INC.
5645 MISSION BLVD.
RIVERSIDE, CA 92509
DATE: AUGUST 24, 2006
CONTENTS: TOTAL PLAN BUSINESS INTERIORS, INC. PROPOSALS
Recommendation:
By Minute Motion, that the City Council:
1) Approve the purchase of a modular furniture system for the open office
area in the North Wing of City Hall by authorizing a purchase order in the
amount of $61,372 to Total Plan Business Interiors, Inc. of Riverside,
California;
2) Authorize the appropriation of $18,411.60 from the City's unobligated funds
to Account No. 110-4159-415-4040;
3) Authorize the appropriation of $21,480.20 from the Agency's unobligated
funds to Account No. 850-4195-466-4040;
4) Authorize the appropriation of $21,480.20 from the Agency's unobligated
Housing Set -Aside funds to Account No. 870-4195-466-4040; and
5) Authorize the Director of Finance to set aside an additional amount of
$6,137.20 as 10% contingency ($1,841.16 from 110-4159-415-4040,
$2,148.02 from 850-4195-466-4040, and $2,148.02 from 870-4195-466-
4040). Use of contingency requires additional council action.
The total appropriation of $61,372 is for the proposed purchase of a modular
furniture system for the open office area in the North Wing of City Hall. The
appropriations above establish the respective budget divisions of 30% from the
City's unobligated funds, 35% from the Agency's unobligated funds, and 35%
from the Agency's unobligated Housing Set -Aside funds; and
Staff Report
Approve Purchase of Privacy Furniture Systems for the Open Office Area in the North Wing of
City Hall
Page 2 of 2
August 24, 2006
Executive Summary:
Approval of the staff recommendation will allow the procurement of a new modular furniture
system for the open office area in the Redevelopment Agency. This furniture will enhance
privacy between work stations, create better sound attenuation, and provide more functional
work stations for each individual's needs.
Discussion:
The 2006-2007 budget approved a project to create a more productive work environment for the
open office area in the North Wing of City Hall, adding privacy with higher walls and enhanced
sound attenuation. Obtaining walls of this increased height will allow increased employee focus
with reduction in noise levels for improved working conditions, and will match the height level of
system furniture throughout the rest of the open office work environments within City Hall.
Implementing these office partition walls requires no demolition, just removal of the old walls. A
used partition wall dealer has shown interest in the purchase of these old partitions. They would
pay approximately $3,600 for this tear down and purchase of the 12 stations. This allows the
recycling of the old partitions rather than throwing them away, reducing the net cost of new
partitions to $57,772. Additionally, this total reflects a U.S. Communities discount of
approximately 60% off of the majority of list prices. The reconfiguring of the new partition walls
can be done over a single weekend.
Staff who will use the new furniture systems are employees of the Redevelopment Agency,
Business Support, Community Services, and Finance Departments. This equipment will provide
adequate privacy and noise control, which the current system does not.
The modular furniture systems are presented here for approval and procurement. Sample color
boards with material choices and a computer rendering will be available for review in the City
Council's conference room during the week of 21 August 2006.
Submitted by:
Missy Wiz:
Project •.rdinator
A • proval:
Department Head:
MI
aye Yrigoyen,
irector of Redevelopment/Housing
Paul S. Gibson
Director of Finance
--Carlos L. Orteg
Executive Direc
G:\RDA\Melissa Wightrnan\New Office Furniture\Staff Report- Approve Purchase.doc
REQUEST FOR APPROPRIATION FROM THE CITY"S AND AGENCY'S UNOBLIGATED FONDS FOR THE
PROPOSED REMODEL OF THE REDEVELOPMENT LOBBY AND THE CONFERENCE ROOMS LOCATED IN
THE PUBLIC WORKS AND PLANNING DEPARTMENTS, THE CITY COUNCIL OFFICE AREA, AND THE
NORTH WING (JOINT CONSIDERATION WITH THE PALM DESERT CITY COUNCIL).
ZITY COUNCI ACTION:
DENIED . approVed1 BY RDA
RECEIVED OTHER
N4EETIN .. a .... ON ?""D (o
DATE " k.,
AYES : VERIFIED BY RJ &1 rG:,
NOES: n , a
ABSENT : Onf Original on file with City Clerk's Office
Original on File
..,._..........._ _
with City Clerk's Offic
%OS
TUTALPLAN
3USIKESS INTERIORS, UJ(
August 8, 2006
Ms. Missy Wightman
Palm Desert Redevelopment Agency
75-510 Fred Waring Drive
Palm Desert, California 92260
Dear Ms. Wightman:
5645 MISSION BLVD.
RIVERSIDE, CA 92509
(951) 767-9000
FAX (951) 369-1932
www.tota1planbusinteriors.com
■
10-100 HIGHWAY 111. SUITE 206
RANCHO MIRAGE, CA 92270
(760) 341-8434
1
ORANGE COUNTY
(949) 888-9050
I am pleased to present the following revised budgetary proposal for your review. All items
are quoted new under the pre -bid US Communities contract # N051017.
General Contract Information
• Purchase orders to be made out as follows: Haworth, Inc.
c/o TOTALPLAN, Inc.
5645 Mission Blvd.
Riverside, CA 92509
• Contract #: N051016 / 066
• Start Date: 08/28/00
• Most recent revision: Current
• Expiration Date: Unlimited
• Pricing Valid: 30 days from date of proposal
• Payment Terms: Direct Bill by Haworth, Inc. NET 30
Open Office Area —12 Work Areas (Option G)
*Special Notes:-PDRA to contract phone/data installation
-PDRA to provide electrician after installation
• New HAWORTH 3" Enhanced Premise industry grade -A modular systems furniture
• Ten 8' x 8' work areas
• One 8' x 8' work area
• One 8' x 12' work area
• 42", 53", 64" & 80" (64" with 16" stack kit) tackable acoustical panels per layout
• Two panel mounted counter tops per layout
• Power and data cabling path provided by three or top feeds
• *Power: TOTALPLAN will interconnect modular systems panels. PDRA is
responsible for contracting electrician to hardwire to building source
• *Data and Phone: PDRA is responsible for contracting phone and
data cabling installation
• Three duplex receptacles (six plug -ins) per powered work area
• Panel raceways support path for phone and data cables
• 24" & 30" work surfaces to include radius corners per layout
• Twelve enclosed locking overhead storage units
• Twelve open overhead storage units
• Twelve fluorescent under shelf task lights
• One attached steel locking B/B/F drawer pedestal
• One steel locking mobile F/F drawer pedestal
• Twelve steel locking mobile drawer pedestals
• Five steel locking 2-drawer x 30" wide lateral files
• Three steel locking 2-drawer x 36" wide lateral files
• Two steel locking 2-drawer x 42" wide lateral files
• Two steel locking 4-drawer x 36" wide lateral file
• One steel 3-high x 36" book case
• One steel 5-high x 36" combo storage/lateral file (2/3)
• Locks are master keyed for Supervisor access to locked items
• Work areas are ADA and Cal -OSHA compliant
• Haworth limited lifetime parts & labor warranty
• Lower panel fabric: Contract Grade A selections
• 16" upper stack panels: Contract Grade D selections
• Laminate: Contract standard selections
• Trim: Contract standard selections
• Wood top caps & end of run rails
Panels
- 49ea 64" high panel
-9ea 53" high panel
- 2ea 42" high panel
- 24ea 16" high stack panel
-llot Panel connector
-3ea Top feed/data module
- clot Electrical
- 1lot Fabric filler post
- llot Fabric trim cover
- llot Wood top cap
- llot Wood end of run rail
Work Surfaces/Counters
- 17ea Rectangular work surface
-lea Radius end work surface
- ilea Wrap around work surface
- 2ea Support panel
- 2ea Counter tops
- llot Mounting hardware
Overhead Shelving
- 12ea ADA enclosed overhead
-12ea Open shelf
- 24ea Shelf dividers
- 12ea Task light
Slat Kits
-12ea Slat kit tile
-24ea Gooseneck kit
-12ea 18" mini shelf
-12ea Tool clip
-12ea Letter tray
Drawers/ Files
-lea Fixed BBF pedestal
-lea Mobile FF Pedestal
- 12ea Mobile BBF Pedestal
- 2ea 2 x 42 lateral file
- 5ea 2 x 30 lateral file
-3ea 3 x 36 lateral file
- 2ea 4 X 36 lateral file
- lea 3 x 36 book case
- lea 5 x 36 Combo lat/storage
llot Product Per above specification $ 51,894.04
lea Labor Freight, Delivery & 1st Floor Installation
-During normal weekday business hours t 4.000.00
Sub -total $ 55,894.04
Tax $ 4,331.79
Option G TOTAL $ 60,225.83
X
Approval to order
Date P.O. #
Pricing: Prices include freight, delivery and installation during normal weekday business
hours. Labor is taxed when new or additional modular furniture product is installed per
current California tax code.
Design Layout: Prior to order entry an approval signature confirming layout design is
required.
' Terms: To place this order a purchase order is required made out to Haworth, Inc, c/o
TOTALPLAN, Inc., 5645 Mission Blvd., Riverside, CA 92509.
TOTALPLAN is not licensed to hardwire to a building — customer must provide an electrician
for this part of the installation. Computer and phone cabling should be coordinated with a
qualified contractor.
Panel Base Power: The electrical components of modular systems furniture are not
designed to support space heaters, large copiers, microwaves, coffee pots and high amperage
equipment. Surges generated by these items can overload the 20amp panel base power
system and short the electrical circuit out.
Note: Please bear in mind that the furnishings will be ordered specifically for this project and
are not subject to return.
Warranty: All new Haworth items come standard with Haworth's limited lifetime parts &
labor warranty. Please contact me for a copy of this warranty if it was not included with this
proposal.
Thank you for the opportunity to work on this project. I hope this proposal meets with
your approval. Please let me know of any way I can be of assistance.
Sincerely,
TOTALPLAN, INC.
i, L- -) 41,4 , , _
Robert J. Pitt
Sr. Project Manager
RJP:
I�j%
TUTALPLAN
BUSINESS INTERIORS, INC
August 8, 2006
Ms. Missy Wightman
Palm Desert Redevelopment Agency
75-510 Fred Waring Drive
Palm Desert, California 92260
Dear Ms. Wightman:
I am pleased to present the following proposal for your review.
Ergonomic Keyboard Pads
• Manufacturer: Grandstands
• Finish: Black
3ea 15885-ST
2ea 15889-5
5ea 23500
lea Labor
X
Approval to order
New 20" x 10" curved platform
- Swivel & tilt mouse
- No palm rest
New 20" x 10" platform
-Swivel & tilt mouse
-Gel palm rest
5645 MISSION BLVD.
RIVERSIDE, CA 92509
(951) 787-9000
FAX (951) 369-1932
www.totalplanbusinteriors.com
■
70-100 HIGHWAY 111. SUITE 206
RANCHO MIRAGE, CA 92270
(760) 341-8434
II
ORANGE COUNTY
(949) 888-9050
$ 81.43 $ 244.29
$ 94.29 $ 188.58
New Click!t Arm $ 115.00 $ 575.00
Freight, Delivery & 1st Floor Installation
-During normal weekday business hours
- Pricing based in conjunction with modular
furniture option G being approved
Sub -total
Tax
TOTAL
Date P.O. #
$ 55.00
$ 1,062.87
$ 82.37
$ 1,145.24
Pricing: Prices include freight, delivery and installation during normal weekday business
hours.
Terms: To place this order a purchase order is required made out to TOTALPLAN, Inc., 5645
Mission Blvd., Riverside, CA 92509.
Note: Please bear in mind that the furnishings will be ordered specifically for this project and
are not subject to return.
Thank you for the opportunity to work on this project. I hope this proposal meets with
your approval. Please let me know of any way I can be of assistance.
Sincerely,
TOTALPLAN, INC.
Robert J. Pitt
Sr. Project Manager
RIP: