HomeMy WebLinkAboutC35520C and D - San Pablo Phase 1 and 2 Streetscape Imprvmtns 691-16CONTRACT NO. C35520C CONTRACT NO. C35520D STAFF REPORT CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT MEETING DATE: April 25, 2019 PREPARED BY: Randy Bowman, Senior Engineer REQUEST: Adopt the California Environmental Quality Act (CEQA) Notice of Exemption for the San Pablo Phase 1 and Phase 2 Streetscape Improvements Projects; Award Contract No. C35520C in the amount of $7,941,158.00 to Granite Construction Company of Indio, California, for the San Pablo Avenue Phase 1 Streetscape Improvements Project; and Award Contract No. C35520D in the amount of $56,446.00 to Leighton Consulting, Inc. of Temecula, California, for Materials Testing and Special Inspection Services (Project No. 691-16). Recommendation By Minute Motion: 1. Adopt the CEQA Notice of Exemption for the San Pablo Phase 1 and Phase 2 Street Improvements Projects; 2. Award Contract No. C35520C in the amount of $7,941,158.00, based upon base bid value, to Granite Construction Company of Indio, California, for the San Pablo Avenue Phase 1 Streetscape Improvements Project; 3. Authorize the Director of Finance to set aside a 20 percent contingency in the amount of $1,588,232.00 from unobligated Measure A funds for Contract No. C35520C; 4. Award Contract No. C35520D in the amount of $56,446.00 to Leighton Consulting, Inc. of Temecula, California, for Materials Testing and Special Inspection Services; 5. Authorize the Director of Finance to set aside a 20 percent contingency in the amount of $11,289.00 from unobligated Measure A funds for Contract No.C35520D; 6. Authorize the City Manager or designee to review and approve written requests for the use of the contingencies for unanticipated conditions, per Section 3.30.170 Section A of Ordinance No., 1335; April 25, 2019 - Staff Report Award Contract No. C35520C to Granite Construction and Contract C35520D to Leighton Page 2 of 4 7. Appropriate $5,300,826.50 from the following accounts: Fund Amount Unobligated Measure A Fund 213 $2,655,966.50 Drainage Facility Fund 232 $1,011,555.00 Park Fund 233 $155,060.00 Recycling Fund 236 $132,000.00 Gas Tax Fund 211 $1,346,245 8. Authorize the Mayor to execute the Agreements. If the above actions are approved, funds will be available in Account No. 4514342- 4400100, Capital Bond Funds; Measure A Special Revenue Fund 213; Drainage Facility Special Revenue Fund 232; Park Fund 233; Recycling Special Revenue Fund 236; and Gas Tax Special Revenue Fund Account No. 211. Strateqic Plan The improvements to the San Pablo Corridor fulfill priorities identified in the City's Strategic Plan, including the following: • Tourism and Marketing — Priority 1: "Improve access to Palm Desert and its attractions to enhance the ease of lifestyle." • Transportation — Priority 1: "Create walkable neighborhoods and areas within Palm Desert that would include residential, retail, services and employment centers, and parks, recreation and open space to reduce the use of low occupancy vehicles." • Transportation — Priority 3: "De-emphasize single/low-occupancy vehicles and optimize modes of travel (bus, carpool, golf -cart, bicycle and pedestrian)." • Land Use - Priority 4: "Create a mixed -use city core integrating shopping, dining, lodging, and housing." Background Analvsis The Director of Community Development has determined that the proposed San Pablo Avenue Improvement project is exempt under CEQA Sections 15301, 15302, 15303, and 15304, as the improvements are within the City's existing right-of-way, the area abutting the corridor is substantially improved, and served by existing utilities. Therefore, staff is recommending that the City Council adopt a Notice of Exemption for the purposes of CEQA. April 25, 2019 - Staff Report Award Contract No. C35520C to Granite Construction and Contract C35520D to Leighton Page 3of4 The first phase of construction of the San Pablo Avenue Corridor Improvements is the roadway section from Highway 111 to Fred Waring Drive. The project incorporates the preliminary engineering approved previously by City Council with highlighted project elements including widened sidewalks, pedestrian crosswalks, pedestrian scale lighting, landscaping, drainage and pavement improvements, minor utility improvements, and a roundabout at the intersection of San Pablo Avenue and San Gorgonio Way. The award of Contract No. C35520C is for the construction of Phase 1 of the San Pablo Streetscape Improvements project. The Project was appropriately advertised for bid, and on April 2, 2019, sealed bids were received and opened by the Office of the City Clerk with the following results: Contractor Granite Construction Company CS Legacy Construction Sully -Miller Contracting Company Riverside Construction Company Location Indio, CA Ontario, CA Brea, CA Riverside, CA Bid Amount $7,941,158.00 $8,060,604.00 $8,832,100.00 $10,861,779.00 A Request for Proposals for materials testing and special inspection services was also appropriately advertised, and on March 15, 2019. Eight proposals were received. The cost of the proposals ranged from $16,000 to $95,000 with the median cost being around $71,000. The internal selection committee recommends awarding the contract to the top consultant, Leighton Consulting, Inc. in the amount of $56,446.00 based on both the quality of their proposal and their cost. Consultant Location Leighton Consulting, Inc. Temecula Geocon West, Inc. La Quinta Koury Engineering & Testing Chino SCST Riverside Inland Foundation Engr. Inc. Palm Desert American Engineering Lab La Habra MTGL, Inc. Riverside United -Heider Inspection Moreno Valley Fiscal Analysis This project, which was included in the CIP Budget for Fiscal Year (FY) 2018/2019, has an estimated total cost of $9,597,125, including contingency. The amount of $4,296,298.50 is currently available from Capital Bond Funds and $5,300,826.50 is available in the accounts previously listed. Phase 2 of the project is expected to be presented to City Council in FY 2020/2021. April 25, 2019 - Staff Report Award Contract No. C35520C to Granite Construction and Contract C35520D to Leighton Page 4 of 4 LEGAL REVIEW Approved as to Form N/A Robert W. Hargreaves City Attorney DEPT. REVIEW Tom Garcia, P.E. Director of Public Works FINANCIAL CITY MANAGER REVIEW Moore Lauri Aylaian Director of Finance City Manager CONTRACTOR: Granite Construction Company 38000 Monroe Street Indio, CA 92203 CONSULTANT: Leighton Consulting, Inc. 41715 Enterprise Circle North, Suite 103 Temecula, CA 92590 ATTACHMENTS: 1) CEQA Notice of Exemption 2) Contractor's Bid 3) Consultant's Proposal 4) Vicinity Map TO: ❑ Office of Planning and Research P. O. Box 3044, Room 113 Sacramento, CA 95812-3044 ® Clerk of the Board of Supervisors or County Clerk County of: Riverside 1. Project Title: 2. Project Applicant: NOTICE OF EXEMPTION FROM: City of Palm Desert 73-510 Fred Waring Drive Palm Desert, CA 92260 2724 Gateway Dr, Riverside, CA 92507 San Pablo Avenue Corridor Improvements City of Palm Desert 3. Project Location — Identify street address and San Pablo Avenue is a 1.5-mile, five lane, "Enhanced cross streets or attach a map showing project site Secondary Roadway" in the City of Palm Desert the heads (preferably a USGS 15' or 7 1/2' topographical north from Shadow Mountain Drive and terminates at map identified by quadrangle name): Magnesia Falls Drive; traversing El Pasco, Highway 111 and Fred Waring Drive. 4. (a) Project Location — City: Palm Desert 5. Description of nature, purpose, and beneficiaries of Project: 6. Name of Public Agency approving project: 7. Name of Person or Agency undertaking the project, including any person undertaking an activity that receives financial assistance from the Public Agency as part of the activity or the person receiving a lease, permit, license, certificate, or other entitlement of use from the Public Agency as part of the activity: 8. Exempt status: (check one) (a) ❑ Ministerial project. (b) ❑ Not a project. (c) ❑ Emergency Project. (d) ® Categorical Exemption. Notice of Exemption (b) Project Location — County: Riverside The project consists of street improvements to a 1-mile long section of San Pablo Avenue between Highway 111 and Magnesia Falls Drive, including: 1) making pedestrian, bicycle, and vehicular improvements within the existing right-of-way, 2) the addition of vehicular traffic calming measures such as a road -diet; removing a vehicle travel lane in each direction; a pedestrian mid -block crossing between Catalina Way and San Nicolas Avenue, and round -a -bouts at San Gorgonio Way, the eastern entrance to College of the Desert, and Magnesia Falls Drive, and 3) making landscape improvements to existing City -owned properties to enhance the pedestrian experience along the corridor, 4 demonstration of these improvements was piloted successfully duringtirhe Z016 Vision Sarr-Pablb Go Human campaign. This project is also contemplated in the City's 2017 General Plan Environmental Impact Report, City of Palm Desert Tom Garcia, Director of Public Works (Pub. Res. Code § 21080(b)(1); State CEQA Guidelines § 15268) (Pub. Res. Code § 21080(b)(4); State CEQA Guidelines § 15269(b),(c)) Class 1 "Existing Facility", Class 2 "Replacement and FORM "B" State type and section number: (e) ❑ Declared Emergency. Reconstruction", Class 3 "New Construction or Conversion of Small Structures", Class 4 "Minor Alterations to Land" 15301(b)(c)(c) 15302(c) 15303(d) 15301(h) (Pub. Res. Code § 21080(b)(3); State CEQA Guidelines § 15269(a)) (f) ❑ Statutory Exemption. State Code section number: (g) ❑ Other. Explanation: 9. Reason why project was exempt: i Project is consistent with the City's general plan and applicable zoning regulations. This project was identified in the City's General Plan (Chapter 10) for improvements to ienhance the corridor. The areas surrounding the corridor are significantly development with existing utilities, housing, businesses, and public improvements. The site has no value as habitat, is served by existing utilities, and does not result i in significant effects on traffic, noise, air quality, or water quality. 10. Lead Agency Contact Person: Tom Garcia, Director of Public Works Telephone: (760)346-0611 11. If filed by applicant: Attach Preliminary Exemption Assessment (Form "A") before filing. 12. Has a Notice of Exemption been filed by the public agency approving the project? Yes ® No ❑ 13. Was a public hearing held by the lead agency to consider the exemption? Yes ® No ❑ If yes, the date of the public hearing was: April 25, 2019 ZSignature: r Date:3/Z.•� Title:,(///�b1OtjlZ!/GL�!' ® Signed by Lead Agency ❑ Signed by Applicant Date Received for Filing: (Clerk Stamp Here) Authority cited: Sections 21083 and 21100, Public Resources Code. Reference: Sections 21109, 21152, and 21152.1, Public Resources Code. Notice of Exemption FORM "B" C -- CONTRACTOR'S BID SAN PABLO AVENUE PHASE 1 STREETSCAPE IMPROVEMENTS PROJECT NO.691-16 CONTRACT NO. C35520C TO: CITY OF PALM DESERT, "CITY" DATE: 04/02/2019 BIDDER: Granite Construction Comoanv "CONTRACTOR" The UNDERSIGNED, "CONTRACTOR", having carefully examined the site and the Contract Documents for the construction of San Pablo Avenue Phase 1 Streetscape Improvements, PROJECT NO.691-16, CONTRACT NO. C35520C, hereby proposes to construct the work in accordance with the Contract Documents, including Addenda No(s). 1, 2, 3, 4 for the amount stated in this Bid. By submitting this Bid, the Contractor agrees with the City: 1. That unless withdrawn in person by CONTRACTOR or some person authorized in writing by CONTRACTOR before the time specified in the Notice Inviting Bids for the public opening of bids, this Bid constitutes an irrevocable offer for n i n e t y ( 90) calendar days after that date. 2 The CITY has the right to reject any or all Bids and to waive any irregularities or informalities contained in a Bid. 3. That the contract shall be awarded only by the governing body of CITY. Said contract shall only be deemed awarded after the CONTRACTOR'S complete submission of all contract documents, bonds, insurance documentation, and the CITY shall obtain all necessary signatures of the governing body, at which time the contract shall be deemed awarded. 4. To submit to CITY such information as CITY may require to determine the Bidders financial standing experience and to perform thework. 5. That the accompanying cash, certified or cashiers check or Bid Bond constitutes a guarantee that if awarded the contract, CONTRACTOR will execute the Agreement and deliver the required bonds and certificates of insurance within 10 days after notice of award. If CONTRACTOR fails to execute and deliver said documents, the cash, check or B i d B o n d is to be charged with the costs of the resultant damages to CITY, including but not limited to publication costs, the difference in money between the amount bid and the amount in excess of the bid which costs CITY to do or cause to be done the work involved, lease and rental costs, additional salaries and overhead, increased interest and costs of funding the project, attorney expense, additional engineering and architectural expense C-1 and cost of maintaining or construction alternate facilities occasioned by the failure to execute and deliver said documents. It is understood that the quantities shown hereon, except for those quantities marked "Lump Sum", are estimates and the final payment will be based upon the actual work performed, subject to such adjustment and alterations as elsewhere provided herein. Pursuant to and in compliance with the Notice Inviting Bids and other Contract Documents relating to the proposal for the construction of STREET IMPROVEMENTS as specifically set forth in documents entitled SAN PABLO AVENUE PHASE 1 STREETSCAPE IMPROVEMENTS (PROJECT NO. 691-16 and CONTRACT NO. C35520C) all in accordance with the Plans and Project Specifications on file at the City of Palm Desert Engineering Department, the undersigned bidder, having familiarized himself with the terms of the Contract, the local conditions affecting the performance of the Contract and the cost of the Work at the place the Work is to be done; and with the Plans, Project Specifications and other Contract Documents, hereby stipulated; the Contractor agrees to complete the Contract, including all of its component parts and everything required to be performed, and to provide and furnish any and all labor, materials, tools, equipment, expendable supplies and all utility and transportation services necessary to perform the Contract, and complete in a workmanlike manner all of the Work required in connection with the Contract, all in strict conformance with the Plans and Project Specifications on file at the City of Palm Desert Engineering Department. All items shall be fumished and functional per Plans and the Contract Documents. Notes: 1. Please type or print legibly in spaces provided in the BID SCHEDULE 2. Please do not use pencil. 3. Unit Prices shall be entered to two (2) decimal places only. C-2 BID SCHEDULE PROJECT NAME: SAN PABLO AVENUE PHASE 1 STREETSCAPE IMPROVEMENTS PROJECT NUMBER: 691-16 CONTRACT NO.: C3 oc NAME OF BIDDER: Granite Construction Company Base Bid Items MOBILIZATION & DEMOBILIZATION 1 ,5% MAXIMUM OF TOTAL) 2 PROJECT INFORMATION SIGN 3 PUBLIC NOTIFICATION PER SPECIAL PROVISIONS, SECTION 1,29 DEVELOP AND IMPLEMENT RISK 4 LEVEL 1 STORM WATER POLLUTION PREVENTION PLAN (SWPPP) IMPLEMENTATION OF EROSION 5 2ONTROL UPON MOBILIZATION 6 TEMPORARY WATER QUALITY MANAGEMENT BMPS ZHANGEABLE MESSAGE BOARDS 7 =OR TRAVEL CONDITIONS AND ADVANCED PROJECT WARNING 8 TRAFFIC CONTROL AND CONSTRUCTION STAGING POTHOLING - LOCATE, PROTECT & 9 RESTORE EXISTING UTILITIES & IMPROVEMENTS 10 SURVEY MONUMENT PRESERVATION 11 RECORD DRAWING ('AS -BUILT") PLANS (STIPULATED AMOUNT) 12 CLASS'K FIELD OFFICE 13 CLEAR & GRUB WITH CLEAN- JP/MAINTENANCE REMOVE AND DISPOSE OF EXISTING 14 TREE AND ROOT SYSTEM, GRIND STUMP 15 REMOVE EXISTING AC PAVEMENT SAWCUT AND REMOVE EXISTING 16 PCC SIDEWALK (4' THICK TYPICAL) AND DRNEWAYS (6- THICK TYPICAL) LS 1 EA 4 LS 1 LS 1 LS 1 LS 1 EA 4 LS 1 LS 1 LS 1 LS 1 MCI 15 LS 1 EA 50 SF 139,320 SF 64,540 C-3-R-3 ., $ !P 5'd)0 $Do ,p0o�o $M'mov" �D 00 0o do $►�5,000* $AS.bDO $ A ODDS $ ae "Obo's° a $Uou �bO$AA,00 $ 30,000ro $3o, o.o'-= $10,000ut $1a, MD" $2, 500 $2, 500 $ 4, 5 60 °" - $ &7, 500= $ao,000 $- aD.wo010 $ 1�-7o0p $$S,000'" $ D 65 $ l l e, 422 e= go $ 1 o� $ 12Z16210 magm O. M ESC O TITY CO 17 ONE FOOT (1') AC SLOT CUT FOR SF 5,870 $ 90 $ sji REMOVAL OF CURB & GUTTER "' REMOVE EXISTING PCC CURB & LF 5,870 $ 6 $ 35, �p4= 18 3UTTER (6' C.F. TYPICAL) REMOVE EXISTING PCC CURB (6' o0 00 19 C.F. TYPICAL) LF 75 $ (, — $ 115a — 20 31 INDEXISTING AC 2' (0.1T) MIN SF 75,650 $ 21 RELOCATE EXISTING PRIVATE SIGN EA 1 $ ' kbb°= $ .Nm PQ NEW GRADE 23 ADJUST EXISTING STORM DRAIN EA 12 $ Z, °+ $ Zy, pp0�' MANHOLES TO GRADE 000 24 ADJUST EXISTING STORM DRAIN EA 1 $ 2, &dDe $ 2 60042 CATCH BASIN TO GRADE 1 REMOVE EXISTING STORM DRAIN o0 25 ;,ATCH BASIN EA 5 $ 4r ZO0 $ Z I, 00d�' 26 REMOVE EXISTING STORM DRAIN LFPIPE 133 $ ZS Q' $ Itoto , 625 COORDINATE WITH CVWD TO 28 RECONNECTLATEWATER METER & EA 5 $ IDOL"' $ 500�' ;WORK TO BE DONE BY CVWD) 29 REMOVE AND RELOCATE EXISTING EA 6 $ G 00 °-" $ 3, boo PRIVATE MAILBOX COORDINATE WITH CVWD TO 30 RELOCATE EXISTING FIRE HYDRANT EA 4 $ f 2 S « $ soot- ,WORK TO BE DONE BY CVWD) 31 18' RCP STORM DRAIN LF 591 $ 3302 $195,030 32 MODIFY CATCH BASIN EA 3 $ �00�= $ b, 300- 33 CATCH BASIN NO.1 (<10' LONG) EA 12 $ lz � 000 eo $ 1411, 000 34 CATCH BASIN NO.1 (10'-20' LONG) EA 3 $ I(P.000Lp $ 48,0d0ap 35 JUNCTION C C&WCD DETAIL U22E N0. 2 PER EA 3 $ 3, 5oc= $ ! o, 5G0`= 36 MANHOLE NO. 1 EA 1 $ q, S06 '! $ 4, 500 r 37 OFFSITE RUNOFF BMPS LS 1 $3\S,bbD� $3�5.Ob�m SILVA CELL SYSTEM AND oo O0 38 APPURTENANCES PER DETAILS ON EA 12 $1�,boc BMP PLANS C-4-R-3 O, DE PJ ST.O N Q CO RUBBERIZED AC PAVEMENT (TOP 2" 39 R-HH Ns 7 SURFACE COURSE PER TON 1,850 $ 15 0_ $ 323� 7.50% 40 CLASS 2 AGGREGATE BASE CY 1,950 $ 50 $ 9%500" 41 PCC CURB ONLY 8" CF LF 390 $ 35 �- $ r3,6SCE - 42 'CC CURB & GUTTER 8" CF LF 3,870 $ qo °-� $154480dy 43 PCC CURB ONLY 6' CF LF 3,520 $ 33 $ It (,160 qs 44 PCC CURS & GUTTER 6' CF LF 125 $ (o0 e $ -7, S60o` 45 5" PCC ROLLED CURB & GUTTER LF 266 $ 8 5 °- $ 27, & 10 - SPECIALTY, ARTIST -DESIGNED 46(S) CROSSWALK MARKINGS PER PLANS SF 1,078 $ (p0 " $ (phi (080 'POLKA DOTS CROSSWALK" DETAIL 47 3' CONCRETE LANDSCAPE PLANS ER PER LF 255 $ Z °� $ 6, 37S« 48 CONCRETE HEADER WITH DEEPEND LF 90 $ 35 EDGE 49 PCC CURB RAMP TYPE A PER EA 24 $ I o ODOe $ 291 600 SDRSD NO. G-27 50 PEDESTRIAN CONCRETE PAVING SF 30,125 $ oo $ Zto, c47S"�° ,BROOM FINISH) (PEDESTRIAN PEDESTRIAN CONCRETE PAVING: 51 STREETFRONT(TOP-CAST, ETCH SF 22,825 $ FINISH) (PEDESTRIAN PAVING 'B" iPER PLANS) 'VEHICULAR CONCRETE PAVING: 52 STREETFRONT (TOP -CAST, ETCH SF 3,210 $ oo $ 48, 156 FINISH) (VEHICULAR PAVING "B" PER S PLANS) VEHICULAR CONCRETE PAVING 53 "BROOM FINISH) (VEHICULAR SF 2,350 $ + Z o2 $ 28, Zdp PAVING "C" PER PLANS) PEDESTRIAN CONCRETE PAVING: 54 STOREFRONT (COLORED SF 11,135 $ CIO* $ +00,21 S°•� CONCRETE, EXPOSED AGGREGATE) VEHICULAR CONCRETE PAVING: STREETFRONT (COLORED o0 00 55 CONCRETE, EXPOSED AGGREGATE) SF 2,020 $ L f $ 3Zs 326 " (VEHICULAR PAVING "A' PER PLANS) 56 PCC TRUCK APRON PAVERS (TYPE SF 1,340 $ 7,b�`� TBD) AND SUBSECTION PER PLAN 57 PCC MEDIAN ISLAND PAVERS & SF 6,630 $a\00 $� aao� SUBSECTION PER PLAN t 58 PAVERS - GIANT CHESS BOARD LS 1 $ 5-aOe90 $cspto°= 59 THEME WALL CF 845 $ $-gyp° $ ut1;3►ao- C-5-R-3 NO.WIZEWDESCRIX• MR 91111 T1 COST 60 THEME PAVING BAND LF 660 $ $ap�= 61 CONCRETE RETAINING WALL LF 175 $ gpb� $ $t0 62 CONCRETE SEAT WALL LF 425 $ a50r' $ �Dba�� 63 SOUR -IN -PLACE CONCRETE STEPS LS 1 $p $ 1 j W'sop o° WITURS 65 BIKE BOLLARD EA 17 $ 1,Z00W $2O,Lfte 66 BOLLARD (FIXED) EA 35 $ "100'- $ ZN,Sooe 67 BOLLARD (REMOVEABLE) EA 13 $1, Soot $ Z3" 4002' 68 CHILDREN'S PLAY FEATURES EA 7 $ 2, SA0 s' $17, -500 e 69 FREENOTES HARMONY PARK LS 1 $ l(o ODDS $ 1(, MUSICAL FEATURE 4 70 PAR COURSE EQUIPMENT LS 1 $ 36,Owe $ 36, 00ov- 71 TRASH RECEPTACLE EA 22 $ 3, OOO°O $ t b, OOD 4L* 72 RECYCLING RECEPTACLE EA 22 $ 3, 000 = $ G6,, Ooo4" 73 PLAY SURFACE LS 1 $ X, Opp * $ Z6, o00" 74 PUTTING GREEN LS 1 $ I 0 ` 100 00 $1 O, too!-' 75 BENCH "A" (QCP BENCH -KERNEL EA 3 $ 1,30021 $ 3,9000--1 SMALL") 76 BENCH -B' (QCP BENCH "KERNEL EA 5 $ 2,500 - $ 12, Soo LARGE") 77 BENCH "C' (QCP BENCH -BOG-) EA 3 $ 4,060e $1 Z, O*Q'-� 78 BENCH "D" (80' BENCH) EA 8 $ 2.606 t! $ 20, 800°+ 79 GAME TABLE (S X 5') EA 3 $ 4. 300p $ IZ, 906 t� 80 TABLE (5' X 5') EA 4 $ 46 300 i $ 17, zoo'-* 81 TABLE (6' X 8') EA 1 $ 4, 300 0 $ 41300" 82 TREE GRATE (3' XV) EA 16 $ 3,100$ 59, Zoo°= 83 TREE GRATE (4' ROUND) EA 8 $ 3, ?00 t* $ 2cl, 600°" 84 SKATEBORD DETERRENT EA 340 $ Sy °-� $ 18, 3Lo00 ;STAINLESS STEEL & BRASS FINISH) 85 "HALK BOARD &CUSTOM BUILD LS 1 $ $ 5, owSTEEL FRAME S ►� 86 HANDRAILS LS 1 $ I, 900$ 1, 900tr- 87- L-6 4 $ $ 88(S) SPECIALTY, ARTIST -DESIGNED BIKE EA 2 $'�S,Olaj00 $51D.W09 RACKS PER PLANS 89 ROUNDABOUT INFIELD FOUNDATION 1 $4.aflpo0 $�,appOe DETAILS PER LANDSCAPE PLANS EA C-6-R-3 90 TRAFFIC STRIPING, PAVEMENT MARKINGS AND SIGNAGE PER LS 1 $ +03 pdp'� $ 103, 000 PLANS ' 91 MAINTAIN EXISTING SIGNAL & LIGHTING SYSTEMS THROUGHOUT LS 1 CONSTRUCTION 92 TEMPORARY TRAFFIC SIGNAL (SAN LS 1 $ 5 001' $ a`j•bo4� PABLO AVE AT HIGHWAY 111) MODIFY TRAFFIC SIGNAL (SAN 93 °ABLO AVE AT HIGHWAY 111) PER LS 1 $,ate+bb0 $ \:-to,DbV PLANS MODIFY TRAFFIC SIGNAL (SAN ob 94 PABLO AVE AT FRED WARING LS 1 $k5.btb $ \S•��r' DRIVE) PER PLANS ELECTRICAL TRENCHING / tt � 95 CONDUITS / CONDUCTORS FOR LS 1 $110b Op0 $ ��+ STREET LIGHTING AND POWER RECEPTACLES PER PLANS 96 STREET LIGHT, TYPE A (SINGLE HEAD STANDARD TYPE AND EA 12 to $-1 .bt too $%N+ObO LOCATION TBD) STREET LIGHT, TYPE B (DOUBLE cp c� 97 MEAD STANDARD TYPE AND EA 5 $ _OCATION TBD) 98 PALM TREE UP LIGHT, TYPE C PER EA 145 cc $ 4w0 $ Cb1�`- \\b DETAILS ON ELECTRICAL PLANS IN -ROADWAY PAVEMENT LIGHT, to 00 99 TYPE D PER DETAIL ON ELECTRICAL EA 20 $y.5b0' vao.tm — :'LANS 100 _IGHTED BOLLARD, TYPE E PER 55 $ ` xm— $ c�3W_ DETAILS ON ELECTRICAL PLANS 101 TREE GRATE UP LIGHT PER DETAILS EA 24 $ O4 $ ON ELECTRICAL PLANS +bb , bbo 102 TYPE 15 STREET LIGHT PER DETAILS ON ELECTRICAL PLANS EA 8 $S+bOD ~ $ ticpMI TYPE 15TS STREET LIGHT WITH m po 103 PEDESTRIAN PUSH-BUTTON PER EA 6 $ S.bAb $ to.Mb DETAILS ON ELECTRICAL PLANS 104 PEDESTRIAN PUSH-BUTTON POLE EA 8 °o $ �J,LpDO^ PER DETAIL ON ELECTRICAL PLANS 105 TREE BARRIER MOUNTED JUNCTION BOX PER DETAILS ON ELECTRICAL EA 32 $0 ay $ PLANS 106 150-AMP METER PEDESTALS (A, B, 4ND C) PER DETAILS ON EA 3 » $ \.)%mb o� $ �o�ObD ELECTRICAL PLANS C-7-R-3 MIDSG IPTtON I Q �Y COS O SAL 200-AMP METER PEDESTALS (Al, B1, cA po 107 AND Cl) PER DETAILS ON EA 3 $10,UbD $ 7jp�mU�" ELECTRICAL PLANS PULL BOXES, ROUND TYPE AND 00 to 108 TYPE 3 PER DETAILS ON EA 96 $ $ ELECTRICAL PLANS 109 LANDSCAPE / ACCENT LIGHTING LS 1 $ �°5�� $ a`c, �p PER PLANS 110 IRRIGATION SYSTEM LS 1 $3-tO �00D«' $ vm bw69 111 PLANTS & PLANTING MATERIAL LS 1 $ \.Arj ►'0b0 $ 6-lb) t) * 112 90 DAY MAINTENANCE LS 1 $a-b.90 O $_jon*p 113(F) JNCLASSIFIED EXCAVATION CY 3,600 $ so ft $ 180$ OaO2# NON -RUBBERIZED AC PAVEMENT �� 114 HMA BASE COURSE & FULL TRENCH TON 1,300 $ ry 5 $ r Be, 500V REPAIR PER PLANS) 115 DCC CURB RAMP (MOD) TYPE A PER EA 25 $ 1 600 $ s-" y0`000 SDRSD NO. G-27 116 CROSS -GUTTERS & SPANDRELS -SF 6,650 $ (3 $ �� 86, H 50 L PER CPD. STANDARDS 106 & 108 117 AY APRONS PER SF 2,120 $ 1 3 �' - $ 27, sj,00-- CPD STANDARD 1 p 118 JUNCTION STRUCTURE NO. 3 PER EA 14 $ 4 0WTO $ S(, OCop" RCFC&WCD DETAIL 228 119(S) SPECIALTY, ARTIST -DESIGNED CROSSWALK MARKINGS PER PLANS SF 976 $ S5 *0 $ 53, bd0 'CHROMATIC CROSSWALK' DETAIL 120 BOCCE BALL COURT LS 1 $ 9, 000'- $ 8, 000 =� TOT '-BASE BID PRICE $ Addendum Note: Bid Items 22 & 27 were moved to Additive Alternate Bid Items The costs of any work shown or required in the Plans and Specifications, but not specifically identified as a Pay Item are included in the related Pay Item(s), and no additional compensation shall be due CONTRACTOR by virtue of CONTRACTOR'S compliance with the Plans and Specifications. TOTAL BASE BID AMOUNT IN FIGURES: $1•a1�1 TOTAL BASE BID AMOUNT IN WORDS: 5eNert MIAIDn N-�\ Foy �t,\y OhC vVlr\d\Yea P\�r'k�s C-8-R-3 Additive Alternate Bid Items Specialty, Artist -Designed SHADE 00 AAA(S) STRUCTURES PER PLANS AND EA 2 S3-j5�app $ 7So�ppb� CONTRACTOR SHOP DRAWINGS ADJUST EXISTING SEWER °O o -2 MANHOLES TO NEW GRADE 9 $Z, 760 — 2'i, 3ao— ADJUST EXISTING WATER VALVE, •o Of AA-3 AIR VENT & BLOW -OFF COVERS TO EA 37 $ 11300 $ gig i00— FINISHED GRADE TOTAL.ADDITIVE,ALTE' E,BiD�PRICE: S SZ21 yoo The costs of any work shown or required in the Plans and Specifications, but not specifically identified as a Pay Item are included in the related Pay Item(s), and no additional compensation shall be due CONTRACTOR by virtue of CONTRACTOR'S compliance with the Plans and Specifications. TOTAL ADDITIVE ALTERNATE BID AMOUNT IN FIGURES: $ 822, 400 TOTAL ADDITIVE ALTERNATE BID AMOUNT IN WORDS: E►Wff HvwbmcO -rWe7N7"/ TWa T"Okii►No, FouR HupicadD UOL6AiLt AND TOTAL BASE BID PLUS ADDITIVE ALTERNATE BID AMOUNT IN FIGURES: $ TOTAL BASE BID PLUS ADDITIVE ALTERNATE BID AMOUNT IN WORDS: - v Notes: 1. Determination of the lowest bid shall be based solely on the lowest "TOTAL AMOUNT BASE BID bid item estimate of costs. 2. Unit Prices shall prevail over extended total and grand total prices. 3. Late bids will not be accepted. 4. The following "Description of Bid Items" are part of the Bid Schedule and shall be submitted with the Bid. 5. See Witness/Notary Page, next page, Required with submitted Bid. C-9-R-3 IN WITNESS WHEREOF CONTRACTOR executed this Bid as of date set forth on Page By: /eph nature (must be notarized) JP.Richardson Title: Reqional Chief Estimator A notary public or other officer completing this certificate verges only the identity of the individual who signed the document, to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of Riverside On April 2 , 20 19 before me, Carolyn Maness personally appeared Joseph P. Richardson who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signatures(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. AZXNhp CAAOM MMIESS Inv" C&fq CpnunisMonl22111472 Myfow.E*ftNw12.2W1 CD Sig Lure of Notary Public C-10-R-3 GRANITE CONSTRUCTION COMPANY CERTIFICATE OF SECRETARY RESOLVED, that, effective January 1, 2019 through December 31, 2019, the individuals named on the attached Exhibit 1 are authorized to negotiate, execute and/or attest electronic and paper documents and contracts necessary for the conduct of the Company's affairs with respect to the submission and execution of construction project bids, bid proposals, bid addenda and all other bid -related documents prepared and submitted on behalf of the Company not to exceed $25 million, relating to any and all domestic construction projects arising out of the Company's operations. RESOLVED, that, effective January 1, 2019 through December 31, 2019, the individuals named on the attached Exhibit 2 are authorized to negotiate, execute and attest electronic and paper documents and contracts necessary for the conduct of the Company's affairs with respect to the submission and execution of construction project bids, bid proposals, bid addenda and all other bid -related documents prepared and submitted on behalf of the Company not to exceed $75 million, relating to any and all domestic construction projects arising out of the Company's operations. RESOLVED FURTHER, that the authority provided for herein shall be in accordance with applicable policies, procedures and limits of authority previously approved and the Granite Construction Incorporated Delegation of Authority and Policy then in effect. 1, M. Craig Hall, do hereby certify that I am duly qualified as Secretary of GRANITE CONSTRUCTION COMPANY, a California corporation (the "Company"); that the foregoing is a true and correct copy of resolutions duly adopted effective January 1, 2019 by unanimous written consent of the Executive Committee of the Board of Directors, held without a meeting in accordance with the provisions of Article III, Section 9 of the Bylaws of the Company; that the Directors acting were duly and regularly elected; and that the resolution adopted has not been modified or repealed and is still in full force and effect. `���rtrrrr Dated: January 1. 2019 C i all ;moo -bgpoi r.y . Z .Ian. 4,1022 EXHIBIT 1 AUTHORIZED SIGNERS Granite Construction Company California Group Desert Cities Region AUTHORIZED SIGNERS Brad J. Williams, VP Desert Cities Region Brian Caris, Senior Project Manager Joseph P. Richardson, Regional Chief Estimator Jeff J. Mercer, Region Construction Manager Ralph M. Pipkin, Project Manager Fausto Gonzalez, Project Manager Rudy Barela, Regional Controller ATTESTORS Brian Caris, Senior Project Manager Joseph P. Richardson, Regional Chief Estimator Jeff J. Mercer, Regional Construction Manager Ralph M. Pipkin, Project Manager Carley L. Cechin, Project Manager Fausto Gonzalez, Project Manager Rudy Barela, Regional Controller Carolyn Maness, Estimating Assistant EXHIBIT 2 AUTHORIZED SIGNERS Granite Construction Company California Group AUTHORIZED SIGNERS Jim Radich, VP Coastal Region Michael Tatusko, VP Valley Region Brent Fogg, VP Central Region Richard Scott McArthur, VP Northern Los Angeles Region John Boies, VP South Coast Region Brad J. Williams, VP Desert Cities Region Bradly Estes, VP Construction Materials A. Description of Bid Items: Bid Item 1. Mobilization & Demobilization: Bid item shall include full compensation for all bonds, insurance, sureties, licenses, permits, facilities, labor, equipment and material necessary to complete all work required in advance of construction operations, and upon the initiation of construction operations, to mobilize all required equipment, materials and personnel on -site, and complete all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The Bid Item shall also include all labor, equipment and material required to clean-up and restore the site, demobilize and remove all equipment, materials, and staging, and complete all work required at the end of construction operations in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The lump sum price for this item shall not exceed 5% of the total contract price. Bid Item 2. Proiect Information Siqn: Bid item shall include full compensation for labor, materials and equipment to fabricate, install and maintain project information signs, in advance of the project, providing project and funding information throughout to project duration. Bid Item 3, Public Notification per Special Provisions, Section 1.29: Bid item shall include full compensation for labor, materials and equipment to provide public communications materials to the City for their use, individual residents and business, general public, fabricate, install and maintain project information signs such as "open for business" signs for individual businesses, throughout to project duration. Bid Item 4. Develop and Implement Risk Level 1 Storm Water Pollution Prevention Plan (SWPPP): Bid item shall include full compensation for labor, materials and equipment to review, modify, implement SWPPP, all work necessary to complete a project NOI, certify the project SWPPP, compile and submit project PRDs (Permit Registration Documents), appoint a project QSD and QSP, install all required construction phase BMPs, complete all required pre -construction SWPPP documentation and associated work as required to ensure the project's full compliance with State Water Resources Board's General Construction Permit (Order No. 2009-0009-DWQ) and Section 1.14 of the Special Provisions. Bid Item 5, Implementation of Erosion Control, Sediment Control. Waste Management, Trackino Control, Contractor SWPPP Documentation upon Mobilization: The monthly unit Bid item shall include full compensation for all labor, equipment and materials required to complete all work necessary to maintain, repair and replace all temporary construction BMPs, provide project oversight by the QSD and QSP, monitor, document and report project compliance, complete all SWPPP administration and associated work as required to ensure the project's full compliance with State Water Resources Board's General Construction Permit (Order No. 2009-0009-DWQ) and Section 1.14 of the Special Provisions. C-11-R-3 Bid Item 6. Temnorary Water Quality Manaaement BMPs: Bid item shall include full compensation for labor, materials and equipment to install and maintain additional units of this bid item required by the City and not included in the bid item required in the SWPPP documentation or for routine maintenance of BMP's to keep BMP's in good working order. This bid item is not intended to compensate Contractor for damage to BMP's caused by normal wear and tear. This Bid Item is not subject to Section 3 Changes In Work. This Bid Item shall account for Silt Fence, Sand/Gravel Bags, Straw Wattles, Inlet Protection, and any additional BMP's as required by the approved Contractor SWPPP. Bid Item 7. Changeable Message Boards for Travel Conditions and Advanced Proiect Wamina:, Bid item shall include full compensation for labor, materials and equipment to place, install and maintain project changeable message boards warning and informing motorist, pedestrians and the general public to use alternate routes and other information as directed by the Engineer throughout to project duration. Traffic control signage needed for changing lane conditions not included in this bid item. Bid Item 8. Traffic Control and Construction Staaina: Bid item shall include full compensation for all labor, equipment and materials required to complete all work required to prepare, submit and obtain approved Traffic Control Plans from the City of Palm Desert Public Works and Engineering Department, and any additionally affected state, federal and local agencies including Caltrans, CVAG and Riverside County; handle traffic (including flagging costs and person(s) to safely control pedestrian and vehicular traffic), furnish tools, equipment and incidentals, and for doing all work involved in staging constructing, furnishing, placing, removing, storing, maintaining, moving to new locations, replacing and disposing of the components of the traffic control system (including traffic control devices, temporary steel plate bridging, temporary road resurfacing); temporary pavement per plans and Section 302-5 Asphalt Concrete Pavement of the "Standard Specifications for Public Works Construction (Greenbook)," (SSPWC) (latest edition); installation and removal of all required temporary striping and signing associated and appurtenant work as specified in the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Bid Item 9. Potholing - Locate, Protect and Restore Existing Utilities and Improvements: Bid item shall include full compensation for all labor, equipment and material required to locate, protect and restore all existing utilities and improvements which `may be affected" or "are affected" by the Work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. The location, protection and restoration of existing utilities and improvements specifically identified for payment under other bid items shall not be included for payment within this bid item. All other location, protection and restoration required to complete the Work shall be incorporated into this bid item. Bid Item 10. Survev Monument Preservation: Bid item shall include full compensation for all labor, equipment and material required to locate, protect and restore all existing survey monumentation within the project limits. C-12-R-3 Bid Item 11. Record Drawing ("As -Built") Plans (stivulated amount): Bid item shall include full compensation for all labor, equipment and material required to provide City with accurate "red line" plans showing the exact location of all improvements, existing utilities, that have been modified as part of the Work. Bid Item 12. Class "A" Field Office: Bid item shall include full compensation for all labor, equipment and material required to provide a class "A" field office as described in Section 1.30 and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 13. Clear and Grub With Clean-Ur)/Maintenance: Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to remove and dispose all natural and artificial objectionable material within the limits of excavation, as required to complete the Work and additional clearing and grubbing as may be identified within the Contract including but not limited to, concrete pavement, concrete walks, curbs, gutters, cross gutters, driveways and alley intersections in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Included in this bid item shall be full compensation for all labor, equipment and material required to remove existing dry -wells identified on the plans as part of this project that conflict with the Work shown on the plans, and any other related work shall be considered as included or included in the costs of other work. The infiltrating pipe within and extending below the dry -well may be abandoned in place; and any required street sweeping or trash removal activities. Removal and disposal of trees, street lights, and bituminous pavement is not included in this bid item. No additional compensation will be made. This Bid Item is not subject to Section 3 Changes In Work. Bid Item 14. Remove and Dispose of Existing Tree and Root Svstem. Grind StumD: Bid item shall Include full compensation for all labor, equipment and material required to complete all work necessary to remove, grind, and dispose of identified trees and associated stumps, within the limits of excavation, as required to complete the Work. Bid Item 15, Remove Existina AC Pavement: Bid item shall Include full compensation for all labor, equipment and material required to complete all work necessary to remove and dispose of bituminous asphalt concrete pavement, base and sub -grade to the depth and limits identified within the Contract Drawings and as may be necessary to reconstruct and re -pave existing streets and drives in accordance with the Contract Drawings, Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer. Existing asphalt thickness may vary. Depth of AC Pavement has been measured at 6" typical, but varies throughout the project limits. No additional compensation will be made due to variable thickness of AC Pavement. Bid Item 16. Sawcut and Remove Existina PCC Sidewalk (4" thick tvvical) and Driveways f6" thick tvvical); Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to remove and dispose of existing concrete surface improvements as shown on the Plans and any other related work shall C-13-R-3 be considered as included or included in the costs of other work. Existing thickness may vary. No additional compensation will be made. Bid Item 17. One Foot (1') AC Slot Cut For Removal of Curb & Gutter. Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to sawcut, remove and dispose of existing AC improvements as shown on the Plans and any other related work shall be considered as in the costs of other work. No additional compensation will be made. Bid Item 18. Remove Existina PCC Curb & Gutter (6" C.F. tvvical): Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to remove and dispose of existing curb & gutter. Bid Item 19, Remove Existinq PCC Curb (6" C.F. tvvical): Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to remove and dispose of existing curb. Bid Item 20. Grind Existing AC 2' (0.171 Min Depth: Bid item shall include full compensation for all labor, equipment and material required to complete all work necessary to grind or cold plane existing AC to a minimum depth of 2", provide leveling course of AC as -needed to provide an even paving surface to receive a 2" AC overlay, remove and dispose of AC grindings. Bid Item 21. Relocate Existina Private Siqn: Bid item shall include full compensation for all labor, equipment and material required to remove and relocate existing private sign as shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 22 — Moved to Additive Alternate Item 2 (AA-2) Bid Item 23. Adiust Storm Drain Manholes to New Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing and proposed storm drain manholes to flush and even with final and temporary finish surfaces, concrete collar, all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer as shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 24. Adiust Existina Storm Drain Catch Basin to New Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing storm drain catch basins to flush and even with final and temporary finish surfaces, all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer as shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-14-R-3 Bid Item 25. Remove Existing Storm Drain Catch Basin: Bid item shall include full compensation for all labor, equipment and material required to remove existing storm drain catch basins identified on the plans as part of this project that are in conflict with the Work shown on the plans, and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. This Bid Item is not subject to Section 3 Changes In Work. Bid Item 26. Remove Portions of Existing Storm Drain PIDe in Conflict w/ Work: Bid item shall include full compensation for all labor, equipment and material required to remove any portions of existing storm drain lines abandoned as part of this project that are in conflict with the Work shown on the plans, and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. This Bid Item is not subject to Section 3 Changes In Work. Bid Item 27 — Moved to Additive Alternate Item 3 (AA-3) Bid Item 28, Coordinate with CVWD to Relocate Water Meter & Reconnect (Work to be done by CVWD): Bid item shall include full compensation for all labor, equipment, time and material required to coordinate with CVWD on the relocation and reconnection of existing water meters per CVWD Specifications. CVWD to perform the work, which shall include installation of meter box per CVWD Std. Dwg. W-5A & W-513 and street trench repair, trench, place pipe bedding, in accordance with the Contract Drawings, Standard Specifications, the Supplementary General Provisions, as shown on the plans and any other related work shall be considered as included or included in the costs of other work. Contractor shall be responsible for connecting Irrigation service lines to the new, relocated meter. Contractor shall be responsible to coordinate with CVWD to prepare the work area prior to relocation of the meter and upon completion of the work to return service and surrounding area to operating conditions. No additional compensation will be made. Bid Item 29, Remove and Relocate Existing Private Mailbox: Bid item shall include full compensation for all labor, equipment and material required to remove, replace, and relocate existing private mailbox as shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 30, Coordinate with CVWD to Relocate Existinq Fire Hydrant (Work to be done by CVWD): Bid item shall include full compensation for all labor, equipment, time and material required to coordinate with CVWD on the removal and relocation of existing fire hydrant, including thrust blocks, per CVWD Specifications, as shown on the plans and any other related work shall be considered as included or included in the costs of other work. Contractor shall be responsible to coordinate with CVWD to prepare the work area prior to relocation of the hydrant and upon completion of the work to return service and surrounding area to operating conditions. No additional compensation will be made. C-15-R-3 Bid Item 31. 18" RCP Storm Drain: Bid item shall include full compensation for all labor, equipment and material required to trench, place pipe bedding, install 18" 2000-D RCP storm drain and back fill per RCFCBWCD "Normal Conditions" MB15 as shown on the plans, and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 32. Modifv Catch Basin: Bid item shall include full compensation for all labor, equipment and material required to modify existing catch basins as shown on the plans and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 33. Catch Basin No. 1 (<10' Lono): Bid item shall include full compensation for all labor, equipment and material required to construct CB 100 catch basin per RCFCBWCD where L=10' or less as shown on the plans, includes curb face transitions each side of inlet, and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 34. Catch Basin No. 1 0 0 -20' Lon4J: Bid item shall include full compensation for all labor, equipment and material required to construct CB 100 catch basin per RCFC&WCD where L=10' to 20' as shown on the plans, includes curb face transitlons each side of inlet, and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Did Item 36. Junction Stnacture No. 2 oer RCFCBWCD Detail 227: Bid item shall include full compensation for all labor, equipment and material required to construct storm drain junction structure No. 2 and No. 3 per RCFCBWCD JS 227 and JS 228 respectively, as shown on the plans and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 118. Junction Structure No. 3 per RCFC&WCD Detail 228: Bid item shall include full compensation for all labor, equipment and material required to construct storm drain junction structure No. 3 per RCFC&WCD JS 228 as shown on the plans and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 36. Manhole No. 1: Bid item shall include full compensation for all labor, equipment and material required to construct storm drain manhole per RCFC&WCD MH 251 as shown on the plans and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 37. Offsite Runoff BMPs (Jensen Structures and JDS HvdrodvnamIc Separator C-16-R-3 Unit w/ Low -Flow Diversion): Bid item shall include full compensation for all labor, equipment and material required to construct the substructure systems and JDS hydrodynamic separator unit, including all pipe line connections between Jensen Structures, as shown on the plans and any other related work, including excavation and backfili, shall be considered as included or included in the costs of other work. Where indicated on the Plans, a stub shall be provided for future connections to the BMPs. The stub shall be sized and positioned as indicated. The end of the stub shall be stopped with a PVC cap to prevent water, earth or other substances from entering the pipe. All storm drain pipe lines entering upstream of the JDS unit paid for as separate bid items. No additional compensation will be made. There is no substitute for this item. Bid Item 38. Silva Cell Svstem and Appurtenances per Details on BMP Plans (Includina Sub -Drains and Risers oer Plans):, Bid item shall include full compensation for all labor, equipment and material required to construct and assemble complete Silva Cell BMP unit, 6" perforated PVC sub -drain, geotextile fabric, 6" PVC inspection risers, 6" PVC sub -drain lug connections, 6" PVC tight line connecting individual units and to storm drain, engineered soil, 2" pea gravel, utility sleeves for crossing utilities and any additional assembly appurtenances as directed by the Engineer, shown on the plans and any other related work, including excavation and backfill, shall be considered as included or included in the costs of other work. No additional compensation will be made. There Is no substitute for this Item. Bid Item 39, Rubberized AC Pavement {Too 2" R-HMA Surface Course oer Plans):. Bid item shall include full compensation for all labor, equipment, material, and mobilization for installation of 2" surface course of Rubberized Hot Mix Asphalt (R-HMA), compacted in place. The final AC surface will be completed at the end of the project to provide a clean, uniform, and finished look throughout the project limits. A trackless tack coat will be used with the final paving operation to minimize tracking over new improvements. The Contractor will be responsible to clean any tracking that stains or discolors newly constructed improvements. The Work shall include, but may not necessarily be limited to prime coat, tack coat or trackless tack coat, distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 302-5 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 114. Non -Rubberizes AC Pavement (HMA, Base Chi arse & Full Trench R air oer Plans): Bid item shall include fullcompensation for all labor, equipment, material, and mobilization for installation of base course asphalt concrete, i.e. Hot Mix Asphalt (HMA), compacted in place. The Work shall include, but may not necessarily be limited to prime coat, tack coat or trackless tack coat, distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 302-5 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, C-17-R-3 called for in the plans and any other related work shall be considered as included or included in the costs of other work. Bid item includes work related to full depth of paving restoration required for trench repair work. No additional compensation will be made. Bid Item 40, Class 2 Ag4reQate Base: Bid item shall include full compensation for all labor, equipment and material for trucking, placing, grading, and compacting class 2 aggregate base per geotechnical recommendations. The Work shall include, but may not necessarily be limited to distribution, spreading, rolling, compacting, joining, adjusting (resetting) of manholes and other structures, associated and appurtenant work, in accordance with Section 400-2.3 of the Supplementary General Provisions, the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. Class 2 aggregate base required under curbs, curb & gutters, cross -gutters & spandrels, pavers, and driveways shall be considered incidental to those items of work and not included in the price paid per cubic yard for class 2 aggregate base within the roadway section. No additional compensation will be made. Bid Item 41. PCC Curb Only 8" CF: Bid item shall include full compensation for all labor, equipment and material required to construct 8" curb per CPD STD 103, place minimum of 6" class 2 base under curb and gutter as directed by the Engineer, shown on the plans and any other related work shall be considered as Included or included in the costs of other work. No additional compensation will be made. Bid Item 42. PCC Curb & Gutter 8" CF: Bid item shall include full compensation for all labor, equipment and material required to construct 8" curb and gutter per CPD STD 102, place minimum of 6" class 2 base under curb and gutter as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 43, PCC Curb Only 6" CF: Bid item shall include full compensation for all labor, equipment and material required to construct 6" curb per CPD STD 103, place minimum of 6" class 2 base under curb and gutter as directed by the Engineer, shown on the plans and any other related work shall be considered as included or Included in the costs of other work. No additional compensation will be made. Bid Item 44. PCC Curb & Gutter 6" CF: Bid item shall include full compensation for all labor, equipment and material required to construct 6" curb and gutter per CPD STD 102, place minimum of 6" class 2 base under curb and gutter as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 45, 6" PCC Rolled Curb & Gutter: Bid item shall include full compensation for all labor, equipment and material required to construct 6" Type A rolled curb and gutter per SDRSD G-4A, place minimum of 6" class 2 base under curb and gutter as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-18-R-3 Bid Item 46(51. SPECIALTY ITEM: Artist -Designed Crosswalk Markings Per Plans "Polka Dots Crosswalk" Detail: Bid item shall include full compensation for all labor, equipment and material required to construct specialty, artist -designed crosswalk markings as directed by the Engineer, shown on the plans denoted as "Polka Dots Crosswalk" and any other related work shall be considered as included or included in the costs of other work. Contractor will be required to obtain approvals of stencils, marking colors, and work flow to be used prior to beginning work. The "Polka Dots" decorative crosswalks shall use six (6) different colored circles of various sizes ranging from 2" diameter to 10" diameter, none overlapping each other, to create a random pattern as depicted on the plans. A separate pre -construction meeting for the specialty crosswalk markings shall include the Artist Paul Hobson and Engineer. No additional compensation will be made. There is no substitution for this item. Bid Item 119(S), SPECIALTY ITEM: Artist -Designed Crosswalk Markings Per Plans "Chromatic Crosswalk" Detail: Bid item shall include full compensation for all labor, equipment and material required to construct specialty, artist -designed crosswalk markings as directed by the Engineer, shown on the plans denoted as "Chromatic Crosswalk" and any other related work shall be considered as included or included in the costs of other work. Contractor will be required to obtain approvals of stencils, marking colors, and work flow to be used prior to beginning work. The "Chromatic" decorative crosswalks shall use seven (7) different colored lines at equal, six-inch (6") thicknesses for each line. A separate pre -construction meeting for the specialty crosswalk markings shall include the Artist Paul Hobson and Engineer. No additional compensation will be made. There is no substitution for this item. Bid Item 47. 6" Concrete Header per Landscape Plans: Bid item shall include full compensation for all labor, equipment and material required to construct 6" concrete header as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 48, Concrete with Deeper Edge: Bid item shall include full compensation for all labor, equipment and material required to form, grade, compact subgrade, place, finish, sidewalk in areas that require the construction of a concrete header with deeper edge adjacent to improvements as directed by the Engineer, shown on the plans and any other related work shall be considered as included or Included in the costs of other work. No additional compensation will be made. Bid Item 49. PCC Curb Ramo Tvne A oer SDRSD No. G-27: Bid item shall include full compensation for all labor, equipment and material required to construct PCC curb ramp per Type A, SDRSD G-27 and Truncated Domes per SDRSD G-30. The Work shall include, but may not necessarily be limited to monolithic curb if required, 12" border, curb and gutter adjacent to the ramp, transition areas, landing areas, and all concrete work necessary to meet and match PCC sidewalk joining the ramp as directed by the Engineer, shown on the plans and any other related work shall be considered as included or C-19-R-3 included in the costs of other work. No additional compensation will be made. Bid Item 115. PCC Curb Ramo (Mod) Tvoe A per SDRSD No. G-27: Bid item shall include full compensation for all labor, equipment and material required to construct modified PCC curb ramp per Type A, SDRSD G-27 and Truncated Domes per SDRSD G-30. The Work shall include, but may not necessarily be limited to monolithic curb if required, 12" border, curb and gutter adjacent to the ramp, transition areas, landing areas, and all concrete work necessary to meet and match PCC sidewalk joining the ramp as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 50. Pedestrian CQrLga ft PAvinn (Bmnm Finish) (Pedestrian Pavina "C" per plans): Bid item shall include full compensation for all labor, equipment and material required to construct pedestrian concrete paving with a broom finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 51. Pedestrian Concrete Pavina: Streefront. (Tog -Cast. Etch Finis I, (Pedestrian Pavina "B" per plans); Bid item shall include full compensation for all labor, equipment and material required to construct pedestrian concrete paving for streetfront with top -cast, etch finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 52„ Vehicular Concrete Pavina: Streetfront (Top -Cast. Etch Finish) (Vehicular Pavinq "B" per plans): Bid item shall include full compensation for all labor, equipment and material required to construct vehicular concrete paving for streetfront with top -cast, etch finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 53. Vehicular ConcretA Pavina (Broom Finish) (Vehicular Pavina "C" per plans): Bid item shall include full compensation for all labor, equipment and material required to construct vehicular concrete paving with a broom finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 54., Pedestrian Concrete Paving: Storefront (;olorad Concrete. Exposed Agareoate) (Pedestrian Pavina "A" oer plans):. Bid item shall include full compensation for all labor, equipment and material required to construct pedestrian concrete colored paving for storefront with exposed aggregate as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 55. Vehicular Concrete Pavina: Storefront (Colored Concrete. Exposed ,6fflreaatel (Vehicular Pavina "A" perplans) Bid item shall include full compensation for C-20-R-3 all labor, equipment and material required to construct vehicular concrete colored paving for storefront with exposed aggregate as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 56, PCC Truck Apron Pavers (Dublin Cobble) and Subsection Der Plan: Bid item shall include full compensation for all labor, equipment and material required to construct brick/concrete pavers, place minimum of 16" class 2 base, compacted to 95%, under pavers, 1" sand leveling course as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 57. PCC Median Island Pavers (Dublin Cobble) and Subsection Der Plan: Bid item shall include full compensation for all labor, equipment and material required to construct brick pavers, place minimum of 4" class 2 base under pavers, 1" sand leveling course, 12" PCC band as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 58, Pavers — Giant Chess Board: Bid item shall include full compensation for all labor, equipment and material required to construct giant chess board paver as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 59. Theme Wall: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of theme wall as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. Theme wall to be paid for at the contract price per cubic foot. No additional compensation will be made. Bid Item 60, Theme Davina band: Bid item shall include full compensation for all labor, equipment and material required to construct theme paving band as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 61, Concrete Retaininq Wall: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of concrete retaining wall as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 62, Concrete Seat Wall: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of seat wall as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-21-R-3 Bid Item 63. Pour -in -Place Concrete Steos: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of concrete steps as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Gampensailan far. —all Ica' via Bid Item 65. Bike Bollard: Bid item shall include full compensation for all labor, equipment and material required to install bike bollard, foundation, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 66. Bollard (Fixed); Bid item shall include full compensation for all labor, equipment and material required to install fixed bollard, foundation, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 67. Bollard (Removeable): Bid item shall include full compensation for all labor, equipment and material required to install removeable bollard, foundation, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 68. Children's Plav Features: Bid item shall include full compensation for all labor, equipment and material required to install children's play features, foundation, appearance and finish as directed by the Engineer and ASTM 1487 standards, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 69. Freenotes Harmonv Park Musical Feature: Bid item shall Include full compensation for all labor, equipment and material required to install musical features, foundation, appearance and finish as directed by the Engineer and ASTM 1487, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 70. Par Course Eauinment: Bid item shall include full compensation for all labor, equipment and material required to install par course equipment, foundation, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-22-R-3 Bid Item 71. Trash Receptacle: Bid item shall include full compensation for all labor, equipment and material required to install trash receptacle, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 72. Recvclina Receptacle: Bid item shall include full compensation for all labor, equipment and material required to install recycling receptacle, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 73. Plav Surface: Bid item shall include full compensation for all labor, equipment and material required to install play surface, foundation, appearance and finish as directed by the Engineer and ASTM 1292 standards, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 74. Puttina Green: Bid item shall include full compensation for all labor, equipment and material required to install putting green, foundation, appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 75, Bench "A" (QCP Bench "Kernel Small"): Bid item shall include full compensation for all labor, equipment and material required to construct Kernel small bench, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 76. Bench "B" (QCP Bench "Kernel Large"): Bid item shall include full compensation for all labor, equipment and material required to construct Kernel large bench, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 77. Bench "C" (QCP Bench "Boo"): Bid item shall Include full compensation for all labor, equipment and material required to construct bog bench, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 78, Bench "D" (80" Bench): Bid item shall include full compensation for all labor, equipment and material required to construct 80" bench, concrete support bands and C-23-R-3 anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 79. Game Table (5' x 5'): Bid item shall include full compensation for all labor, equipment and material required to construct game table, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or Included in the costs of other work. No additional compensation will be made. Bid Item 80, Table (5' x 51: Bid item shall include full compensation for all labor, equipment and material required to construct 5' x 5' table, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 81. Table (6' x 81: Bid item shall include full compensation for all labor, equipment and material required to construct 6' x 8' table, concrete support bands and anchoring in pavers, anchoring in concrete surfaces as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the ' costs of other work. No additional compensation will be made. Bid Item 82. Tree Grate (3' x 61: Bid item shall include full compensation for all labor, equipment and material required to construct complete tree well system that is integral with Silva Cell system, 3' x 6' tree grate, tree guard, steel frame with PCC border curb as directed by the Engineer, shown on the plans and any other related work shall be considered as Included or included in the costs of other work. No additional compensation will be made. There is no substitution for this item. Bid Item 83. Tree Grate (4' Round): Bid item shall include full compensation for ail labor, equipment and material required to construct complete tree well system, 4' round tree grate, steel frame with PCC border curb as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. There is no substitution for this item. Bid Item 84, Skateboard Deterrent (Stainless Steel & Brass Finish); Bid item shall include full compensation for all labor, equipment and material required to install skateboard deterrent, in areas that are required as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 85, Chalk Board & Custom Build Steel Frame: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of chalk board & custom steel frame as directed by the Engineer, shown on the plans and any other related work shall be considered as included or C-24-R-3 included in the costs of other work. No additional compensation will be made. Bid Item 86, Handrails: Bid item shall include full compensation for all labor, equipment and material required to construct form, foundation, appearance and finish of handrail as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 88(S). SPECIALTY ITEM: Artist -Designed Bike Racks Per Plans: Bid item shall include full compensation for all labor, equipment and material required to construct specialty, artist -designed bike rack as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. Contractor will be required to obtain approvals of stencils, marking colors, and work flow to be used prior to beginning work. A separate pre -construction meeting for the specialty bike racks shall include the Artist Paul Hobson and Engineer. No additional compensation will be made. There is no substitution for this item. Bid Item 89, Roundabout Infield Foundation Details Per Landscape Plans: Bid item shall include full compensation for all labor, equipment and material required to construct pedestrian concrete roundabout infield foundation as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 90. Traffic StriDinq. Pavement Markings and Sionaue Der Plans: Bid item shall include full compensation for all labor, equipment and material required to provide all traffic striping as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. Bid item shall include full compensation for all labor, equipment and material required to provide all traffic markings as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. Bid item shall include full compensation for all labor, equipment and material required to provide and install all signs, ornamental sign posts, sign foundations, as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 91. Maintain Existinq Signal & Lightinq Svstems Through Construction: Bid item shall include full compensation for all labor, equipment and material required to maintain existing signal systems and equipment needed during staged construction as called for in the plans, by the contractor's staging, and any other related work shall be considered C-25-R-3 as included or included in the costs of other work. No additional compensation will be made. Bid Item 92. Temporary Traffic Signal: Bid item shall include full compensation for ail labor, equipment and material required to install and maintain temporary signal systems and equipment needed during staged construction as called for in the plans, by the contractor's staging, and any other related work shall be considered as included or included in the costs of other work. Temporary Video Detection Systems shall be installed where detector loops will be out of service for longer than 10 days or as directed by the Engineer. No additional compensation will be made. Bid Item 93. Modifv Traffic Signal (San Pablo Ave at Hiahwav 111) Der Plans: Bid item shall include full compensation for all labor, equipment and material required to install modify traffic signal systems and equipment needed as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 94. Modifv Traffic Signal (San Pablo Ave at Fred Warina Dr) Der Plans: Bid item shall include full compensation for all labor, equipment and material required to install modify traffic signal systems and equipment needed as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 95, Electric Trenching. Conduit, and Conductor: Bid item shall include full compensation for all labor, equipment, and material required to trench per City of Palm Desert Standard Drawing No. 113, export or dispose of excess excavated materials, conduit, bedding, pulling wire, setting vaults and structures, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 96. Street Light. Tvpe A (Single Head): Bid item shall include full compensation for all labor, equipment, and material required to construct street light foundation, install street light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. There is no substitution for this item. Bid Item 97. Street Liaht Tvpe. B (Double Head): Bid item shall include full compensation for all labor, equipment, and material required to construct street light foundation, install street light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. There is no substitution for this item. C-26-R-3 Bid Item 98, Palm Tree Liqhts, TVDe C per Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install type C light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 99. In-Roadwav Pavement Liqhts, Tvpe D per Details on Electrical Plans: Bid Rem shall include full compensation for all labor, equipment, and material required to construct light foundation, install in -roadway light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as Included or included in the costs of other work. No additional compensation will be made. Bid Item 100. Liahted Bollard. Tvpe E Der Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install type E light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. There is no substitution for this item. Bid Item 101, Tree Grate Liqhts per Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install tree grate light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as Included or included in the costs of other work. No additional compensation will be made. Bid Item 102. TvDe 15TS Street Light Der Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install Type15TS street light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 103. Ty4e 15TS Street Light with Pedestrian Push -Button Per Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install Type15TS street light with pedestrian push-button, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-27-R-3 Bid Item 104. Push -Button Pole Der Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install pedestrian push-button pole, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 105. Tree Barrier Mounted Junction Box Der Details on Electrical Plans: Bid item shall Include full compensation for all labor, equipment, and material required to mount weather proof junction box on tree guard, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 106. 160-AMP Meter Pedestals 'A' and 'B': Bid item shall include full compensation for all labor, equipment, and material required to construct meter pedestal, foundation, concrete pad, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as Included or included in the costs of other work. No additional compensation will be made. Bid Item 107, 200-AMP Meter Pedestals 'Al' and '131': Bid item shall include full compensation for all labor, equipment, and material required to construct meter pedestal, foundation, concrete pad, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 108. Pull Boxes. Round TvDe and TvDe 3 Der Details on Electrical Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct and install round type and Type 3 pull boxes, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 109. Landscape / Accent Liahtina Der Details on Landscape Plans: Bid item shall include full compensation for all labor, equipment, and material required to construct light foundation, install landscape / accent light, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. C-28-R-3 Bid Item 110. Irrigation Svstem: Bid item shall include full compensation for all labor, equipment, and material required to install a fully functioning irrigation system, piping, sleeves, control panels, electrical system, valves, controllers, trench, export or dispose of excess excavated materials, conduit, bedding, pulling wire, pull boxes, hand holes, and backfill trenches as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 111. Plants & Plantina Material: Bid item shall include full compensation for all labor, equipment, and material required, blend, amend, provide soil sample tests and certifications, install trees and shrubs, fertilize, export or dispose of excess excavated materials as directed by the Engineer, called for in the plans (see Planting Legend, Specs & Notes on sheet 87 of the Plans) and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 112. 90-Dav Landscape Maintenance Period: Bid item shall include full compensation for all labor, equipment, and material to maintain, replace, water, amend soil, fertilize, weed landscaping and irrigation, as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. (Note: this maintenance period is not a part nor included in the Working Days) Bid Item 113(F). Unclassified Excavation: Bid item shall include full compensation for all labor, equipment, and material required for the purposes of excavating, removing, hauling and disposing of all materials to the sub -grade elevations as required to construct the new improvements. This item involves removal and disposal of all soil, and similar appurtenances that are within the grading and excavation section. Unclassified excavation shall be done in accordance with Section 300-2 of the Standard Specifications and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 116. Cross -Gutters & Spandrels Der C.P.D. Standards 106 & 108: Bid item shall include full compensation for all labor, equipment, and material required for the purposes of constructing cross -gutters and spandrels in compliance with City of Palm Desert Standard Plans 106 and 108 and place a minimum of 6" class 2 base under cross -gutters and spandrels as directed by the Engineer. This item involves formwork, concrete pouring/paving, and hand -troweling as needed to construct the cross -gutters and spandrels in a manner that allows for the conveyance of water as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 117. Concrete Drivewav Aprons per C.P.D. Standard 105: Bid item shall include full compensation for all labor, equipment, and material required for the purposes of constructing driveway aprons in compliance with City of Palm Desert Standard Plan 105 and place a minimum of 6" class 2 base under driveway aprons as directed by the C-29-R-3 Engineer. This item involves formwork, concrete pouring/paving, and hand -troweling as needed to construct the driveway aprons per the standard and plans and as directed by the Engineer, called for in the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Bid Item 120, Bocce Ball Court: Bid item shall include full compensation for all labor, equipment and material required to install bocce ball court, foundation, drainage, concrete header, wood header, fill material (oyster shell, class 2 base, landscape fabric, and crushed rock), appearance and finish as directed by the Engineer, shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. Additive Alternate Bid _Item AA -US), SPECIALTY ITEM: Artist -Designed Shade Structures Per Plans: Bid item shall include full compensation for all labor, equipment and material required to construct specialty, artist -designed shade structures as directed by the Engineer, shown on the plans and any other related work shall be considered as Included or included in the costs of other work. Contractor will be required to obtain approvals of stencils, marking colors, and work flow to be used prior to beginning work. A separate pre -construction meeting for the specialty shade structures shall include the Artist Paul Hobson and Engineer. No additional compensation will be made. There is no substitution for this item. Additive Altemate Bid Item AA-2, Adiust Existing Sewer Manholes to New Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing sewer manholes to flush and even with final and temporary finish surfaces as shown on the plans, concrete collar, all associated and appurtenant work in accordance with the Standard Specifications, the Supplementary General Provisions, and as directed by the Engineer and any other related work shall be considered as in the costs of other work. No additional compensation will be made. Additive Alternate Bid Item AA-3, Adiust Existinq Water Valve, Air Vent, & Blow -Off Covers to Finished Grade: Bid item shall include full compensation for all labor, equipment and material required to adjust existing water valve covers flush and even with final and temporary finish surfaces per CVWD Specifications as shown on the plans and any other related work shall be considered as included or included in the costs of other work. No additional compensation will be made. If this work is performed by CVWD forces the Contractor will not be entitled to perform this work. This Bid Item is not subject to Section 3 Changes In Work. C-30-R-3 City of Palm Desert I San Pablo Avenue Condor Improvements . Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 TABLE OF CONTENTS LETTEROF TRANSMITTAL........................................................................................................... 1 TECHNICALPROPOSAL............................................................................................................ 2 QUALIFICATIONS, RELEVANT EXPERIENCE AND REFERENCES....................................................................2 OtMifrcabons....................................................................................................................................................... 2 R*vaN Experience 8nd RefBa'I ces.................................................................................................................3 MANAGEMENTAPPROACH................................................................................................................................5 ProposedTeam.................................................................................................................................................5 OrganizationalChart...........................................................................................................................................8 TECHNICAL APPROACH 1 WORK PLAN.............................................................................................................11 CONFLICT OF INTEREST DISCLAIMER.............................................................................................................14 EXCEPTIONS AND DEVIATIONS.......................................................................................................................14 FEEPROPOSAL..............................................................................................................................................14 APPENDICES........................................................................................................................... 15 0 1 P a g e 4 Leighton Consulting, Inc. A LEIGHTON GROUP COMPANY City of Palm Desert, Department of Public Works 73-510 Fred Waring Drive Palm Desert, California 92260-2578 Attention: Mr. Bo Chen, PE, City Engineer Friday, March 15, 2019 Opportunity Number P019-M Subject: Proposal for Materials Testing and Special Inspection Services for Project No. 691.16 San Pablo Avenue Corridor Improvements — Phase 1 Palm Desert, California Leighton Consulting, Inc,, is pleased to present this proposal to provide materials testing and inspection services for the San Pablo Avenue corridor. Our team is uniquely qualified to provide these services; able to identify and quickly address any material testing issues during construction. We have already worked on similar projects in this area and are very familiar with applicable City, County and Caltrans standards. Our services will be supported by our local Palm Desert office. Our contact person for this project is Simon Saiid, PE, GE, and can be reached at: (760) 776.4192. We hereby confirm that we have received and reviewed the RFP and Addendum 1, the plans and specifications for this project, as well as, the proposed Draft Agreement provided with the RFP. Furthermore, Leighton is fully qualified and capable of performing the specified work to achieve the City's objective for these services. All information submitted with the proposal is true and correct. This proposal will remain valid for 120 days from the date of this submittal. As President and CEO of Leighton Consulting, Inc., Tom Benson is authorized to legally bind, negotiate and execute all contracts on behalf of the firm. We thank you for your consideration and look forward to the opportunity to be of service. If you have any questions regarding this proposal or our qualifications, please do not hesitate to contact us at (866) LEIGHTON, or directly at the e-mail addresses and phone extensions listed below. Respectfully submitted, LEIGHTON CONSULTING, INC. �OOOZ Simon . Saiid, PE, GE Thomas C. Benson, Jr., PE, GE Principal Engineer President and CEO Extension 8013. ssaiidCcDleiahtonoroup.com Extension 8771. tbensonpleiahtonconsuttinq.com Distribution (1) original, (5) copy of Technical Proposal, and (1) original and (4) copy of the Fee Proposal under separate cover. 41715 Enterprise Circle N., Suite 103 ■ Temecula, CA 92590-5661 951.296.0530 ■ Fax 951.296.0534 111 www.leighlonconsulfing.com APAMMM City of Palm Desert I San Pablo Avenue Corridor Improvements • Phase I March 15.2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-M TECHNICAL PROPOSAL QUALIFICATIONS, RELEVANT EXPERIENCE AND REFERENCES Qualifications Leighton Consulting Inc. (Leighton), a Leighton Group Company, founded in 1961, provides geotechnical, geo- environmental, and materials testing and inspection services for transportation and infrastructure projects. Our staff of more than 175 is located in eight offices across southern California, including Palm Desert, Temecula, Rancho Cucamonga, Irvine (HQ), Los Angeles, Ventura, Santa Clarita and San Diego. Our project experience includes municipal projects such as roadways and local streets, water infrastructure and public facilities. Services for this project will be provided out of our local Palm Desert office, with support from our 7 other southern California locations, if needed. Leighton is in a solid financial position, and unaware of any condition (e.g., bankruptcy, pending litigation, planned office closures, impending merger) that could impede our ability to provide services to the City of Palm Desert (City) over the life of this contract. Our field personnel have years of construction geotechnical work experience and follow all relevant industry standards of practice for the safe execution of quality public works construction projects. Our selected field personnel are able to understand and interpret project construction plans and specifications and applicable standards for Public Works Construction (Greenbook, Caltrans Standard Plans and Specifications; and CaUOSHA Construction Safety Orders). Our field technicians have repeatedly demonstrated their ability to interact professionally with contractors, engineers, inspectors, and the public at large. They typically coordinate with other City personnel and consultants; promote quality customer service and a professional image of the City; and respond promptly and courteously to requests. All of our technicians work under the responsible charqe of a person registered by the California State Board of Reqistration as professional civil engineer and/or geotechnical enqineer. 2 1 P a g e City of Palm Desert I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 Leighton has served the communities and public agencies of the greater Coachella Valley area for over 20 years. Leighton's experience on similar projects in this immediate area and our familiarity with City requirements will be critical for efficient testing procedures and will allow us to respond quickly to unexpected construction related issues. Leighton's services are supported by our in-house laboratory. All Leighton laboratories participate bi-yearly in Cement and Concrete Reference Laboratory (CCRL) Sample Proficiency Testing and consistently achieve the highest possible ratings. We hold certification from Caltrans, AASHTO, and others. Our laboratory participates in the Cement and Concrete Reference Laboratory (CCRL) Sample Proficiency Testing, AASHTO Materials Reference Laboratory (AMRL) Proficiency Sample Program, and Caltrans Reference Sample Program (RSP). Relevant Experience and References A representative list of similar projects completed in Palm Desert and other local cities is as follows: STREET IMPROVEMENT PROJECTS I City of Palm Desert, CA Crienf Leighton has provided observation and testing services associated with various City of Palm Desert street improvement projects for the City of Palm Desert. Our scope of services has Ryan Gayler Project Administrator included; field observation and testing for compaction of AC pavement construction 73510 Fred Waring Drive on Mesa View Drive, Park Center Drive, and Springfield, Enfield, Garand, and Palm Desert, CA 92260 T. 760- 776-6393 Entrepreneur Lanes. Leighton provided laboratory testing of asphalt materials for conformance with project specifications. All field and laboratory testing results were documented and submitted to the City. Our field technicians worked closely with the City Inspector and contractor to coordinate field testing and compliance with the project requirements. 3 1 P a g e City of Palm Desert I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 STREET IMPROVEMENT PROJECTS I City of Rancho Mirage, CA Crient Leighton has provided observation and testing services associated with multiple City of Rancho Mirage street improvement projects for the City of Rancho Mirage, Our scope of services William Enos, PE, City Engineer included; field observation and testing for compaction of subgrade and aggregate 69-825 Highway 111 base for pavement construction, concrete sidewalks, curb and gutter, as well as Rancho Mirage, CA 92270 T. 760-770-3224 retention basins, drainage pipes, and catch basin backfill. Laboratory testing of aggregate base and asphalt materials for conformance with specifications. Concrete sampling and testing for slump and compressive strength testing. Field and laboratory testing was documented and submitted to the City. Our field technicians worked to coordinate field testing and compliance with the project requirements. CACTUS AVENUE/NASON STREET IMPROVEMENTS I Moreno Valley, CA Client Leighton performed geotechnical engineering services during design and construction City of Moreno Valley phases of street widening associated with Cactus Avenue, from Lassalle Street to Viren Shah !Guy Pegan Viren Frederick Street Nason Street, and widening and/or completion of Nason Street, from Cactus Avenue Moreno Valley, CA 92552 to Iris Avenue, in Moreno Valley. Both streets were widened to accommodate four T. 951-413-3115 `Project of the Year travel lanes including a bridge crossing over Line F Channel. 2013 by the APWA Leighton provided geotechnical observation and materials testing services for all aspects of the project including concrete box culverts and wing walls, fill placement, bridge construction, channel lining, aggregate base, and asphaltic concrete. Leighton maintained close coordination with project CM and updated City PM on work progress and budget status. 41Page dwmh CAy of Palm Desert I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-M MANAGEMENT APPROACH Primary communications will be through Leighton's Project Manager, who will be the single point of contact regarding this project, and thus greatly reduces the potential for miscommunications. * Mr. Mitchel Bomyasz, PG, CEG, will serve as Primary Contact and Task Manager. Mr. Bomyasz has worked on numerous municipal, commercial, and private development projects throughout Southern California. He has a hands on approach to project oversight and will be involved in all technical and administrative aspects of the project. Mr. Simon Saiid, PE, GE, is our Principal Engineer for the Palm Desert office and will provide QA/QC oversight. Mr. Saiid has over 29 years of geotechnical and materials testing experience involving public streets and bridges including numerous projects within the City of Palm Desert and other local Cities. PROPOSED TEAM 8GRWAIL&WCNEL S LICENSE NUMBER: 2416 LICENSE TYPE: ENGINEERING GEOLOGIST LICENSE STATUS: CLEAR 0 EXPIRATION DATE: OCTOBER 31.2020 SECONDARY STATUS: WA CITY: VALLEY CENTER STATE: CALIFORNIA COUNTY. SAN DIEGO ZIP: 92080 6ORNYA=M17C11EL S LICENSE NUMBER: ?M LICENSE TYPE: GEOLOGIST LICENSE STATUS: CLEAR 0 EXPIRATION OATE: OCTOBER 31. 2020 SECONDARY STATUS: WA CITY: VALLEY CENTER STATE: CALIFORNIA COUNTY: SAN DIEGO ZIP: 92082 SAIID, SIMON 1 LICENSE NUMBER: 2611 LICENSE TYPE: GEOTECHNICAL ENGINEER LICENSE STATUS: CLEAR O EXPIRATION DATE: SEPTEMBER 30.2019 SECONDARY STATUS: WA CITY: MURRIETA STATE: CALIFORNIA COUNTY: RIVERSIDE ZIP: 92562 SAID, SIMON I LICENSE NUMBER:42375 LICENSE TYPE: CIVIL ENGINEER LICENSE STATUS: CLEAR 0 EXPIRATION DATE: SEPTEMBER 30 2019 SECONDARY STATUS: WA CITY: MURRIETA STATE: CALIFORNIA COUNTY: RIVERSIDE ZIP: 92562 The team that has been specifically selected for this project and expected rote and availability is provided in the table on the following page. The key personnel will be available to the extent proposed for the duration of the required services. Leighton understands that no changes in key staff will be made without prior written consent from the City. A summary of project personnel, their roles and credentials are provided below. Brief resumes and professional credentials of key personnel are included in the appendix to this submittal. 51Page City of Palm Desert I San Pablo Avenue Comdor Improvements - Phase I PROPOSAL FOR MATERIALS TESTING ANO SPECIAL INSPECTION SERVICES SIMON SAIID, PE, GE I Principal in Charge Quality Assurance and Oversight BS, Civil Engineering March 15, 2019 P019.009 Experience: 29 years / Leighton -12.5 years Civil Engineer - 62375 Current Assignments: Transportation, public works and land development Geotechnical Engineer - 2641 projects with various completion dates. ✓ Verify that our deliverables fully meet project requirements ✓ Ensures Leighton has adequate resources assigned ✓ Provide technical quality review of testing reports and understands the critical importance of timely, accurate, and fully vetted technical information ✓ Experienced with both conventional on -site materials and laboratory testing MITCHEL BORNYASZ, PG, CEG I Project Manager Project Administration and Management BS, Geological Sciences Geologist - 7973 Experience: 22 years / Leighton - 8 years Engineering Geologist - 2416 Current Assignments: Transportation, public works and land development projects with various completion dates. ✓ Primary point of contact during project / Coordinates with City management and field personnel ✓ Communicates any field issues with designated City personnel and others, as needed ✓ Provides technical support, attends progress meetings as needed, and reviews daily reports ✓ Tracks project performance, schedule, and budget and updates project metrics BASHIR SAIID, EIT I Senior Staff Engineer BS, Mathematics/Geology Experience: 15 years / Leighton -11 years Current Assignments: Transportation, public works and land development projects with various completion dates. ✓ Provides Field and Office data management and analysis ✓ Ensures testing conformance and regulatory guidelines Engineer in Training-13583-14318, Nuclear Gauge Certification 6 1 P a g e City of Palm Desert I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 IFPROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 MATTHEW VINET I Materials Laboratory Manager BS, Civil Engineering Experience: 7 years /Leighton — 7 years Caltrans - ACI - AASHTO Current Assignments: Transportation, public works and land Certifications development projects with various completion dates. ✓ Responsible for the quality of laboratory personnel, and training and test certifications. ✓ Oversees quality assurance of all test reports and test methods by providing review of all testing reports TECHNICIANSANSPECTORS ✓ Geotechnical observation and compaction testing / Site soils and materials sampling ✓ Prepare and submit daily field reports, communicate with project management and contractor MIKE THOMPSON I Lead Field Technician Caltrans - ACI Experience: 20 years / Leighton —10 years Nuclear Gauge Certification Current Assignments: Transportation, public works and land development projects with various completion dates. MARIO APARICIO I Field Technician Caltrans - ACI Experience: 15 years / Leighton — 4 years Nuclear Gauge Certification Current Assignments: Transportation, public works and land development projects with various completion dates. MANUEL GARCIA ( Field Technician Nuclear Gauge Certification Experience - 6 years / Leighton - .5 year Current Assignments: Transportation, public works and land development projects with various completion dates. 71Page MECity of Palm Des el I San Pablo Avenue Corridor Improvemerds - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES P019-QQ9 ORGANIZATIONAL CHART MITCH BORNYASZ PG, C G Task ManagerlPrimary Contact I N Sr. Staff Engineer Laboratory Supervisor FIELD TECHNICIANS Mike Thompson Maria Apadcio Manuel Garcia We believe that our staff has a clear understanding of the various construction aspects of the proposed improvements. Our experience and knowledge from recently completed projects will provide the City a team that is uniquely qualified to identify and quickly address geo#echnical and materials testing issues during construction, 8IPa9e 99=- City of Palm Desert I San Pablo Avenue Corridor Improvements - Phase 1 March 15.2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19a9 SIMON SAIID, PE, GE I Principal Engineer Education Mr. Saiid has over 29 years of engineering design and construction M.S., Civil Engineering, Rensselaer Polytechnic Institute, Troy, New York supervision experience for the civil and geotechnical aspects of projects B.S., Civil Engineering, Rensselaer Polytechnic Institute, Troy, New York related to infrastructure, public facilities, and land development. Mr. Saiid is Professional Registrations California Geotechnical Engineer - 2641 California Civil Engineer - 62375 responsible for review of geotechnical engineering analyses, laboratory testing, and quality control. He is practiced in geotechnical site investigations, shallow and deep foundation design, buttress and structural landslide mitigation, seismic hazard evaluations and mitigation design, grading control, ground improvement, pipelines, pavement design, and forensic evaluations. Mr. Saiid contributes to the success of construction projects by interacting with the project team during planning and design phase and providing cost-effective solutions for challenging geologic conditions. He also attends project team meetings, reviews bid and submittals to clarify geotechnical recommendations, and recognizes the importance and results of working collaboratively with the client and project team to achieve efficient design and construction procedures. MITCHEL BORNYASZ, PG, CEG ( Project Geologist/Manager Education Mr. Bomyasz has extensive professional experience in the geosciences with B.S., Geological Sciences, San Diego State University, San Diego, Cal'tfomia Professional Registrations specific focus in engineering geology. He has contributed as the lead Certified Engineering Geologist - 2416 Professional Geologist - 7973 geologist and project manager for projects involving commercial, residential, and public works development throughout southern California. Through his work history he has developed the skills and knowledge necessary for determining geotechnical mitigation procedures and design alternatives for geologically sound site development. In addition to having geotechnical expertise, he is a dedicated project manager who prides himself on efficient and effective management of personnel and deliverables throughout the project duration. 9 1 P a g e Cily of Palm Desed I San Pablo Avenue Cwkior Improvements - Phase I PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERY[CES MATTHEW VINET ( Laboratory Supervisor Education B.S., Civil Engineering, California State Polytechnic University, Pomona. Degree in Progress Professional Certifications ACI, (Concrete, Aggregate, Laboratory Technician 1) Caltrans, (105,106,125, 201, 202, 217, 226, 227, 301, 304, 308, 309, 382, 521, 523) AASHTO (T11, T27, R47, R76, T166, T176, T209, T248, T255, T269, T275, T308, T329, T335) March 15, 2019 PD19-009 Mr. Vinet has over seven years of professional experience performing a variety of soil and material testing procedures. His responsibilities include performing testing procedures in accordance with current standards, reviewing and finalizing data, communicating results with clients and project managers, ensuring lab equipment is calibrated and managing laboratory staff. BASHIR SAID, EIT I Senior Staff Engineer Education B.S., Mathematics (minor in Geology), University at Albany, New York, 2006 Professional Certifications Engineer in Training (NCEES ID:13583-14318) Nuclear Soil Gauge Certificate ACI Concrete Field Testing Technician Mr. Saiid's experience includes a projects throughout Riverside, Orange, and San Bernardino Counties. He has performed geotechnical/geologic investigations, including site characterization, field classification of soils, and samples collection. Mr. Saiid is experienced in geotechnical observation and testing during rough- and post -grading, and geotechnical analysis and evaluation of field and lab data. 10IPa9e City of Palm Desert I San Pablo Avenue Corridor Improvements • Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 TECHNICAL APPROACH I WORK PLAN Based on our review of the RFP and project plans and specifications, we understand that the current project phase includes substantial improvements to San Pablo Avenue between Highway 111 and Fred Waring Road. The work consists primarily of vehicle lane realignment / pavement replacement and associated construction of traffic roundabouts, sidewalks, and drainage improvements. Additional improvements include stormwater catch basins, ADA ramps, and curb and gutter replacements. The following approximate material quantities are anticipated: 3054 tons of AC pavement (-1700 feet full section replacement and -1500 feet grind and overlay), -70,000 square feet concrete paving (-5,000 feet pedestrian sidewalk), '8,500 linear feet curb and gutter, 15 catch basins and 591 feet RCP storm drain, 1,915 yards aggregate base, 49 ADA ramps, and -600 feet retaining/seat wall. A construction schedule was not available for our review at the time of this proposal; however, the overall project construction is anticipated to require approximately 10 months duration and will begin in May or June 2019. Based on our extensive experience in this area and with similar projects, issues that are likely to require Leighton's services during construction are as follows: Preconstruction Meeting and Review of Submittals: Leighton has demonstrated a proactive approach to construction projects by attending construction meetings and reviewing bid documents and submittals as necessary to provide clarification or solutions. We will routinely work with your project manager/inspector regarding work progress, and resolve any pending issues to keep the project on time and alleviate unnecessary activities. Geotechnical Observations and Compaction Testing: Leighton will coordinate with the City PM/Inspector to provide geotechnical observation and compaction testing during all earthwork and pavement construction. This field observation is a crucial part of the overall QA testing to ensure that proper compaction procedures are being implemented to achieve the required compaction. Due to their very extensive experience with such construction procedures and different soils conditions, our technicians will play an important role in supporting your staff and take a proactive approach in identifying any potential deficiencies in the contractor's compaction methods and OC testing I I I P a 9 e APJKM City of Palm Desed I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19.009 procedures. In addition to the project plans and specifications, our staff will ensure that the testing procedures comply with applicable California Test Methods and per project specifications. Our QA field density testing will be performed in accordance with ASTM D-6938 (nuclear gage method) and follow frequencies set forth in the construction documents and pmject/City Quality Control Plan (QCP), if any. Leighton can provide daily field reports and progress reports, if needed. These reports may include the following: ■ Daily field reports (DFRs) will be prepared and distributed on the same day or the following day to you or your CM, or when needed. These reports and any field photographs of construction progress will be maintained for the project team's ready reference. Our DFR is typically prepared electronically and can submitted or emailed in a short notice. A sample report showing the type of information typically included in our DFR is presented as Exhibit 1. This report typically includes information such as test results, location and depth, and other pertinent field observations, etc. ■ Laboratory test reports as requested or needed during construction. ■ Interim compaction reports to approve final subgrade or trench backfill prior to placement of Aggregate Base and pipeline testing, if needed. • Final compactiontsoils report can be provided at completion of work to summarize our observations and present density tests taken for various aspects of the project. This table can be customized and specific for various elements of the projects. This table can also keep track of any failing tests and confirming test results and frequencies of tests taken by the QC technician. Leighton project manager/engineer will provide timely, same -day, corrective and/or remedial recommendations that may be needed due to site conditions, materials, or contractor methods. Materials Testing: Leighton will perform QA materials testing in accordance with the contract documents and as requested by the CM. This testing is expected to include, but may not be limited to, the following: i2jPage City of Palm Desert I San Pablo Avenue Corridor Improvements - Phase I March 15, 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19-009 a Asphalt Testing. Verify HMA Mix Design and perform CIA testing that will typically include extraction, gradation, bitumen content, Hveem or Stabilometer. Laboratory testing will also be performed on collected import or batch plant samples to verify conformance with the project specifications. ■ Aggregate Base: Tests will comply with applicable City standards, "Greenbook" and the Special Provisions for this project and may include Gradation, Durability Index, R-Value, and Sand Equivalent. Laboratory testing will also be performed on collected source and onsite samples to verify conformance with the project specifications During the course of the project, Leighton will maintain and provide to the City, when required, records of sampling and testing for the project that may include the following: Sampling and Testing Logs Daily Reports for Acceptance Testing activities • Laboratory Test Results We believe that our staff has a clear understanding of the various construction aspects of the project. Our experience and knowledge from recently completed similar projects will provide the City a team that is uniquely qualified to identify and quickly address geotechnical and materials testing issues during construction. Cost effectiveness/budget control: Our approach is to provide a thorough review of the project documents and include sufficient time for our engineers and techniciantinspectors to perform the necessary services and be able to foresee or deal effectively with arising issues. We consistently provide our clients cost savings by minimizing construction delays and change orders related to unexpected soils and materials issues. As a standard in-house procedure, our project managers always closely monitor field activities with an eye toward mitigating redundant field inspection and testing time to stay within budget. 131Page City of Palm Desert I San Paulo Avenue Corridor Improvements - Phase I March 15. 2019 PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES PD19.009 IRROW CONFLICT OF INTEREST DISCLAIMER Leighton Consulting, Inc. has no conflict of interest relating to this project. EXCEPTIONS AND DEVIATIONS Leighton Consulting, Inc. does not have any exceptions or deviations from the requirements of this RFP. FEE PROPOSAL Our total fee proposal and schedule of Hourly Rates are submitted in a separately sealed envelope. 1410age Milt City of Palm Desert I San Pablo Avenue Cofridor Improvements • Phase I PROPOSAL FOR MATERIALS TESTING AND SPECIAL INSPECTION SERVICES APPENDICES nAo noass: u/rRAars At[AAb71rArTON urau7wlr arsPac7loar A[PORr VAN of CAWornla Department of transportation CALTRMS ACCREDITATION LABORATORY INSPECTION REPORT Explradon Date: 2019-I1.30 Inspected By: Seree Yerilal form T1-0113 IA No.: 93 Phone: 916.247.1911 RSP S. 207 Fite: Material Category 500 Laboratory: Leighton Consulting.Inc. Address: 41715 Enterprise Circle North. Ste 103 CRY: Temecula State: CA Zkp: 92590 Lab OC Mgr.: Matthew 1/41et E•ma7: mvinet®leightongroup.com Telephone: 951.296.0530 Fax At.: 951.296.0534 A Carolled independent Assurance (NI vitae thb laboratory on 10ste) _//- W zofb 0" the equipment to ee used on Clams Constnxbon Dialects Inolortocal construction Wgects on the National Hqhway System was Checked for qualJkatlon At the tans of CYtranf Actrtdtation. this laboratory had NI necessary equipment to perform tre test methods ...lndtCoted below-TesUng personnel 3hallbe Caltrans OuaoRld And possru a currentCattrans CertAlcabon form TL-0111 or AASHTO Pmllclency form TL-0115 pow to peAornrrrg any samprmq or tesbn9. AASHTO T I I AASKTO T27 AASHTO R47 AASHTO R76 AASHTO T166 MStirO T176 AASHTO T209 AASHTO T248 AASHTO T255 AASHTO T269 AASHTO T27S AASKTO T308 AASHTO T329 AASHTO T335 Cr 105 CT106 CT 125 ADMIX Cr 125 AGG CT 1I5 BIT Cr 125 GEN CT 125 HMA Cr 125 PCC CT 201 CT 202 Cr 206 CT 207 CT 212 CT 213 CT 216 CT 217 CT 226 CT 227 CT 229 Cr 231 CT 234 CT 235 CT 301 CT 304 Cr 305 Cr 309 CT 366 CT 370 CT 375 CT 382 CT 504 CT 518 CT 521 CT SI3 CT 533 Ct 539 CT 540 Cr 541 Cr 556 CT 557 A Visual check WAS pectwme0 and dooaanems PM-- as necessary for the followkt9 Rams: March 15, 2019 PD19.009 ,j" Facilky Safety Manual YrS Laboratory Procedures Mamal su011uINuurw9%ACCOWAT111111tAeoaama.nsnCTICRUroar ref. Laboratory Oualry can" Manual 7_Preper test equipment _MW,_Cop.es of Cu"M apolicsde test procedures *_calbration am semce documentation yF4 Gllindrin socaers ached to test equipment Idated wiokn the 12 moralist On it-V2,.rt7"i. W S laboratory was Canrans "Vied by: svmv ybmll t ("@a name of U person) '(SigrsaGxe person) (g14,t4-7• WII 151Pa9e MAT(.'NI-INN 5FF 9FLDW LEFT STA. 12+00 �; : , i - i Jijti • EI Rol b x iLLi�{ I _ r:10-7.11—Ld9 Re _ AVE } ann- _� y I WrAbib • S10-[-I r x) I. ,.I dl 1..YiYS } I�:arss- NacHoas AVE n M-CO1-L49 NW z Q Fi `' x r Q „n .. ,a .�ogo_..c_�.'a.emen ls.a�J�uwH nen c•n �,wel rr.•M �•nwil e.q �ovswn ne. .� t � •wm ...waon. r r} i c� Q n n = s x n VI r V to z r — m z n N N I ALESSAND" ` 1oU•-1 iaa 1401 � t �It��' f Hdd 1 11 .__,_ 1 1�