Loading...
HomeMy WebLinkAboutC37290 - Reject Bids - Street Light Consduit Install 599-17 CONTRACT NO. C37290 STAFF REPORT CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT MEETING DATE: September 27, 2018 PREPARED BY: Ryan Gayler, Project Manager REQUEST: Reject all bids for Contract No. C37290 for the Street Light Conduit Installation Project and authorize the City Clerk to re-advertise (Project No. 599-17). Recommendation By Minute Motion: 1. Reject all bids for Contract No. C37290 for the Street Light Conduit Installation Project (Project 599-17); and 2. Authorize City Clerk to re-advertise and call for bids for the subject project. Strategic Plan The proposed action will further the goals of the strategic plan by providing a safe and efficient transportation system for both drivers and pedestrians. Background Analysis The Public Works department has received requests for safety lighting at various intersections within the City. The requests were reviewed and a project was created to install pedestrian safety lighting at two intersections on El Paseo and one intersection on Country Club Drive. Public Works has coordinated with Southern California Edison to design the street light project. The project was advertised and the following three bids were received on August 21, 2018: Contractor Location Bid Amount Alfaro Communications Construction Compton, CA $ 54,000.00 PTM General Engineering Riverside, CA $ 78,778.00 Elecnor Belco Electric, Inc. Chino, CA $ 84,000.00 September 27, 2018 - Staff Report Reject all bids for Contract No. C37290 (Project No. 599-17) Page 2 of 2 Alfaro Communications Construction, the apparent low bidder at $54,000, contacted Public Works after the bid opening requesting that they be allowed to withdraw their bid. The contractor indicated that they made a mathematical error because their estimating software didn't include all the expenses when totaling the bid price. The next lowest bidder, PTM General Engineering, is almost 50 percent higher than the low bidder with a proposed contract cost of $78,778. Local contractors were contacted regarding the project, but the only bids received were from out-of-town contractors. Staff contacted various local contractors to inquire as to why they did not submit bids on the project. Several indicated that they missed the bid deadline due to timing and would be interested in bidding on the project should it be re- advertised. Others suggested that prevailing wage requirements deterred them from pursing the project. Public Works staff will reach out to local contractors and encourage them to bid on the project when it is re-advertised. Staff recommends that the City Council reject all bids and authorize the City Clerk to re-advertise the project for bid. Fiscal Analysis There is no fiscal impact associated with this action. LEGAL REVIEW DEPT. REVIEW FINANCIAL CITY MANAGER Approved as to Form REVIEW N/AJJII11y I Ali Robert W. Hargreaves Tom Garcia, P.E. et Moore \\ Lauri Aylaian �" City Attorney Director of Public Works Director of Finance City Manager ATTACHMENTS: Location Map it 04./..**14 )\..19,1 ..'. : . 14 3111.— ... • ?. -1 '- * --- .00 '3.4..1.W47) jb ,,,...........„ ..., . , : Y‘ ; #1)/ 1.4 ji° 4 }; • At:j, _ . ? IV ❑ j. r, .. . + 41 : ' ti �, 4� -11 — F � ■ 41:7•-" .4 ' --IP"' //: • .• ' _ iiiiii:14, - f. • • f . , ci) .F2 I ., . .. till , ,,,,.,„ _ __ ,_._ i . t, 1___..., _, r ,,i,,p, ii ,,,,.. „...,) . . ... ... .,.. . . , , , „, . , i -# .. , _ i ! .• . ..,..,. 6 '. •)11111 Ili 1 .--,- i - • - I , ;,. • SAGE-WO il, ,• ol, - • . ya _ L .0 V • . ,, ,...... ". 3 f • dile LIMO ill lit. .¶ ! p c' !. ..+-}t., If ..L :.P1 0 • St ) ' . ii -- 1 I • . * g..... ki, t it • i ir r 14 Tom. � f# -y. . . le WA BRAVA V .•• ''t. P.M I .4ip.,., " at •• . • .4 41 i 11F a �•... y i M.� y P.o e .. il fitor MN VAVIt) • Vas 7 li i 1 ' k ,— . s . .9 gli rY r r, 1 _ ,, . _ .- - i , ' i I et i±i1J r't: