HomeMy WebLinkAboutC34370A - NOC - CO1 - Joslyn Ctr Generator 763-15 Contract No. C34370A
STAFF REPORT _- k-\
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
MEETING DATE: November 16, 2017
REQUEST: Approve Change Order No. 1 in the amount of$1,500, and approve
acceptance of work for Contract No. C34370A with California
Building Evaluation and Construction, Inc., of Anaheim, California,
for the Joslyn Center Generator Project (Project No. 763-15)
Recommendation
By Minute Motion,
1. Approve Change Order No. 1 to Contract No. C34370A in the amount of
$1,500;
2. Authorize the transfer of $1,500 from contingency to base;
3. Authorize the City Manager to execute Change Order No.1; and
4. Accept the work as complete and authorize the City Clerk to file a Notice
of Completion for Contract No. C34370A, Joslyn Center Generator Project
(Project No. 763-15).
Strategic Plan
This matter is related to the Public Safety and Emergency Services section of the Palm
Desert Strategic Plan, specifically under Priority 3: Help the community become more
prepared for disasters and public safety emergencies.
Background Analysis
On March 9, 2017, the City Council awarded Contract No. C34370A to California
Building Evaluation and Construction, Inc., of Anaheim, California, in the amount of
$189,820 for the construction of the Joslyn Center Generator Project. Staff has
inspected the work performed by the contractor and has found said work to be complete
and in accordance with the contract requirements. The work was completed on time,
however, there were some unexpected issues related to utilities that have caused
increases in the project cost.
The contractor has submitted two change order requests for utility work associated with
the project. Change Order Request No.1 is for grading and the construction of a
retaining wall to maintain the requisite clearance around an electrical transformer.
November 16, 2017 - Staff Report
NOC and CO#1for Contract No. C34370A, Joslyn Center Generator Project
Page 2 of 3
Southern California Edison required the changes to the project before they would
schedule the electrical switchover for the facility. Change Order Request No.1 will
increase the contract amount by $1,500.
Change Order No. 2 is for the relocation of a gas line. The relocation of the gas line
was an unexpected requirement from So Cal Gas. Once the generator was installed,
So Cal Gas was concerned that the existing gas meter was closed in by the generator
and related equipment. Because gas meters have the tendency to vent excess gas,
and the generator has some electrical components that can generate sparks, So Cal
Gas engineers thought it best to relocate the gas line to a less confined location. Staff
thought the chances of a fire due to the location of the gas meter were slim, but So Cal
Gas would have required the City to sign a waiver of liability in favor of So Cal Gas if we
chose to leave the gas meter where it was. For this reason, staff agreed to relocate the
gas line.
The contractor indicated that they have performed similar work in the past and that they
would be able to relocate the gas line. Staff performed a rough calculation and
determined the estimated amount of the gas line relocation would likely be under the
contingency amount of $18,982. Public Works discussed the matter with the City
Manager, and instructed the contractor to proceed with the relocation on a time-and-
materials basis.
The contractor did not perform the work in an efficient manner, spending nearly three
weeks to run approximately 110 feet of gas line and dig pot holes for So Cal Gas. In
addition to the fact that the contractor took too long to perform the work, when staff
received the change order request, many items that were included in the support
documentation were not related to the change order work. Staff has indicated to the
contractor that the City will not pay the change order until it is revised to include only
work and materials associated with the relocation of the gas line. Negotiations are
currently underway with the contractor to come to a reasonable cost.
The City Attorney has been advised of the situation and is working with staff to ensure
that the City is acting in accordance with applicable laws and standards. The City
Attorney advised staff to proceed with filing the Notice of Completion in spite of the fact
that the second change order request is still under negotiation. Staff will return to the
City Council for approval of Change Order No. 2.
Fiscal Analysis
The initial contract amount was $189,820, and Change Order No. 1, in the amount of
$1,500, increased the contract amount to $191,320. When Change Order No. 2 is
negotiated the contract i a be increased by that amount.
Prepare , y: Ryan O yler, Project Administrator
November 16, 2017 - Staff Report
NOC and CO#lfor Contract No. C34370A, Joslyn Center Generator Project
Page 3 of 3
LEGAL REVIEW DEPT. REVIEW FINANCIAL REVIEW CITY MANAGER
N/A ( �
i(OZE-& ,•
ane 4- ce-(4 -
Robert W. Hargreaves Mark reenwood, P.E. boore Lauri Aylaian
City Attorney Director of Public Works Director of Finance City Manager
APPLICANT: California Building Evaluation and Construction, Inc.
2115 W. Crescent Avenue, Ste. #236
Anaheim, CA 92801
ATTACHMENTS: Change Order No. 1
Notice of Completion
Location Map
CITY OF PALM DESERT Contract#/P.O.# C34370A P113340
Change Order No. 1
CONTRACT CHANGE ORDER Contingency: NO
Contract Purpose Install Generator at Joslyn Center Account No. 4504164-4400100
Consultant's Name California Building Evaluation and Construction, Inc. Project No. 763-15
Address: 2115 W. Crescent Avenue, Ste. #236 Vendor No. V0014234
Anaheim, CA 92801
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
(Supplemental Plans, Specifications, and Directives dated Attached) In Contract Price In Contract Price
1. Install retaining wall to provide requisite clearance for SCE equipment 1,500.00
TOTALS: - 1,500.00
NET CHANGE IN CONTRACT PRICE: 1,500.00
JUSTIFICATION:
SCE required a 3' clear area around the sides and the back of the new transformer.
TOTAL BUDGET FOR PROJECT: + 208,802.00 CONTINGENCY:
Less: Expend. & Encumb.To Date: - 189,820.00 Amount Approved by Council: + 18,982.00
Less:This Change Order Amount: - 1,500.00 Less: Prior Change Order(s): - -
BALANCE OF BUDGET Less: This Change Order: - 1,500.00
REMAINING FOR PROJECT: 17,482.00 Balance Remaining of Contingency. 17,482.00
The amount of the Contract will be Increased by the Sum of: One Thousand Five Hundred and 00/100
Dollars ($1,500.00).
See reverse ...
Contract C34370A Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension 0 Days.
Revised Contract Total $191,320.00
The undersigned Contractor approves the foregoing Change Order# 1 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order# 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
DEPARTMENT HEAD CONTRACTOR Date Accepted
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR LAURI AYLAIAN Date Approved
CITY MANAGER
NOTE: No payments will be made prior _
to City Manager and Council approval CITY MANAGER Date Approved
See reverse ...
To be recorded with the Riverside County Recorder
within 10 days after completion and acceptance by
the City Council. NO RECORDING FEE PER
SECTION 6103 OF THE GOVERNMENT CODE.
When recorded, return to:
Office of the City Clerk
City of Palm Desert
73-510 Fred Waring Drive
Palm Desert, CA 92260
NOTICE OF COMPLETION
(Cal. Civ. Code§ 3093—Public Works)
NOTICE IS HEREBY GIVEN:
1. That the interest or estate stated in paragraph 3 herein in the real property herein described is SOLELY
OWNED by the CITY OF PALM DESERT, A MUNICIPAL CORPORATION, a political subdivision of the State
of California, and whose address is 73-510 FRED WARING DRIVE, PALM DESERT, CALIFORNIA, 92260.
2. That the full name and address of the owner of said interest or estate is set forth in the preceding
paragraph.
3. That the nature of the title of the stated owner, as set forth in paragraph 1, is IN FEE.
4. That on the 16th day of November, 2017 work of improvement described as the Joslyn Center
Generator Project, Project No. 763-15, Contract No. C34370A, on the real property herein described was
completed.
5. That the name of the original contractor, if any, for said work of improvement was: California Building
Evaluation and Construction, Inc., 2115 W. Crescent Avenue, Ste. #236, Anaheim, CA, 92801
6. That the real property herein referred to is situated in the City of Palm Desert, County of Riverside,
State of California, and is described as 73-750 Catalina Way, Palm Desert, California 92260.
(APN 627-111-028)
CITY OF PALM DESERT
A MUNICIPAL CORPORATION
Date: By:
Jan C. Harnik, Mayor
STATE OF CALIFORNIA }
}ss
COUNTY OF RIVERSIDE }
I hereby certify that I am the City Clerk of the governing board of the CITY OF PALM DESERT,CALIFORNIA,the political subdivision
which executed the foregoing Notice and on whose behalf I make this verification: That I have read said Notice, know its contents, and
that the same is true. I certify under penalty of perjury that the foregoing is true and correct.
Executed at Palm Desert, California,on this day of , 20
RACHELLE D.KLASSEN,CITY CLERK
Rev.Sept 2016
,._
, t_
. f
FRED WARING DRIVE
1
—1 - l I
1
I L _ ` r
SANTA ROSA WAY
w 1 ❑
U 7
- _
- _ -. Li!
W U —
J a w o , _ ! - a
J ' — ---
d , U
z (s]
1 N aa.
Z
Aig ,
L I I
CATALINA WAY• / .
r
1
j - i W
iW
aI 1
w ' I
a-_
a
- Q� ____________ _ /
ROYAL y/------
PALM / ; ~~7\ /
DRIVE
a 4p �A, Joslyn Senior Center
4
ate �� 0
``"FOR'' Date: 2015 VICINITY MAP