Loading...
HomeMy WebLinkAboutC35310 - Line 4 Drainage ProjectContract No. C 35310 CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: AWARD CONTRACT NO. C 35310 FOR PROFESSIONAL ENGINEERING AND DESIGN SERVICES FOR THE LINE 4 DRAINAGE PROJECT TO MICHAEL BAKER INTERNATIONAL, INC., OF IRVINE, CALIFORNIA, IN AN AMOUNT NOT TO EXCEED $281,744 SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works CONSULTANT: Michael Baker International, Inc. 14725 Alton Parkway Irvine, CA 92618 DATE: May 12, 2016 CONTENTS: Agreement Consultant's Proposal Recommendation By Minute Motion: 1. Award Contract No. C for professional engineering and design services for the Line 4 Drainage Project to Michael Baker International, Inc., of Irvine, California, in an amount not to exceed $281,744; 2. Authorize the Director of Finance to set aside a 10 percent contingency in the amount of $28,174; 3. Appropriate $309,918 from unobligated drainage funds to Account No. 2324690-4400100, Storm Drain Improvement; and 4. Authorize the Mayor to execute the contract. Strateqic Plan Obiective Although this project doesn't fit neatly into any one of the nine Strategic Results Areas outlined in the Strategic Plan, this project will add to the City's flood protection system. The City has an outstanding infrastructure system including streets and storm drains, and those are the foundational elements and underpinning that the Strategic Results Areas are built upon. Contract No. C 35310 Staff Report Award Contract for Engineering for the Line 4 Drainage Project Page 2 of 3 May 12, 2016 Background The City has invested heavily in storm drain systems, and that investment has paid off by protecting property owners from damage due to major storms. Even in heavy down pours, most of the City never experiences road closures due to flooding. However, when the City contracted with a consultant to study the drainage patterns in the north sphere (everything north of Country Club Drive within the city limits — see attached), the study identified the eastern portion of the City as an area requiring improvements. During a major storm in September 2014, Country Club Drive was inundated with water, breaching the City's right-of-way. Those flood waters spilled onto Washington Street stranding motorists, and disrupting access for emergency services. There are several small retention basins in the area, but they are not properly sized to accept all the water that comes in with a major storm. One solution that the study identified was acquiring land east of Washington Street in Bermuda Dunes for use as a retention basin. If procuring land is necessary to accommodate the water, Public Works would like to secure it before it is developed, or prices increase further. However, it is possible that there are other solutions that don't involve land acquisition. Therefore, Public Works has solicited proposals from professional engineering consultants to perform a feasibility study to determine the most cost effective solution to eliminate the flooding along Country Club Drive and surrounding areas. Once the best alignment is selected, the consultant will perform survey, utility research, hydrological and hydraulic analysis, environmental documentation, and right-of-way services, if necessary. This represents the first phase of engineering required to create a complete design package for the construction project. The second phase will be under a separate contract and will include geotechnical analysis, construction drawings, specifications and a cost estimate. Proposals were solicited, and on March 8, the City received five proposals. The consultants were ranked by the selection committee, based on the strength of the proposal, the location of the consultant, and the cost. Following are the top three firms in the order in which they were ranked by the selection committee. Consultant Location Michael Baker International, Inc. Irvine, CA Dudek Palm Desert, CA PACE Fountain Valley, CA Although Michael Baker International has an office located in Palm Desert, and some of the work will be performed out of the Palm Desert branch, the hydrology team and the project manager are based in Irvine. Based on this review, the selection committee Contract No. C 35'it o Staff Report Award Contract for Engineering for the Line 4 Drainage Project Page 3 of 3 May 12, 2016 recommends awarding the contract to Michael Baker International, Inc., to provide the engineering and design services for the Line 4 Drainage Project. Fiscal Analysis The first phase of engineering will cost $281,744. The second phase of the project will be dependent upon the results of the feasibility study, but the design, possible future land acquisition and infrastructure construction are estimated to exceed $10 million. Although the Drainage Fund would initially advance the funds for the design and construction of the Line 4 Drainage Project, the City will be reimbursed by the Successor Agency pursuant to the approved Project Area 4 Bond Fund Agreement. Prepa�By: , _ / Department Head: r, ject Administrator Mark Greenwood, P.E. Director of Public Works J net . Moore, Director of Finance Approval: ow� hy, Interim C:y7 er Contract No. C35310 LINE 4 DRAINAGE PROJECT CITY OF PALM DESERT PROFESSIONAL CONSULTANT SERVICES AGREEMENT PARTIES AND DATE. This Agreement is made and entered into this 12th_ day of May , 20 16 , by and between the City of Palm Desert, a municipal corporation, organized under the laws of the State of California, with its principal place of business at 73-510 Fred Waring Drive, Palm Desert, California, 92260 ("City") and Michael Baker International, Inc., a Pennsylvania Corporation, with its principal place of business at Irvine, California ("Consultant'). City and Consultant are sometimes individually referred to herein as "Party" and collectively as "Parties." 2. RECITALS. 2.1 Consultant. Consultant desires to perform and assume responsibility for the provision of certain professional ENGINEERING consulting services required by the City on the terms and conditions set forth in this Agreement. Consultant represents that it is experienced in providing professional ENGINEERING consulting services to public clients, is licensed in the State of California, and is familiar with the plans of City. 2.2 Project. City desires to engage Consultant to render such professional ENGINEERING consulting services for the LINE 4 DRAINAGE PROJECT, ("Project') as set forth in this Agreement. 3. TERMS. 3.1 Scope of Services and Term. 3.1.1 General Scope of Services. Consultant promises and agrees to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately supply the professional ENGINEERING consulting services necessary for the Project ("Services"). The Services are more particularly described in Exhibit "A" attached hereto and incorporated herein by reference. All Services shall be subject to, and performed in accordance with, this Agreement, the exhibits attached hereto and incorporated herein by reference, and all applicable local, state and federal laws, rules and regulations. Contract C 3.1.2 Term. The term of this Agreement shall be from June 1, 2016 to December 17, 2016, unless earlier terminated as provided herein. Consultant shall complete the Services within the term of this Agreement, and shall meet any other established schedules and deadlines. 3.2 Responsibilities of Consultant. 3.2.1 Independent Contractor: Control and Pavment of Subordinates. The Services shall be performed by Consultant or under its supervision. Consultant will determine the means, methods and details of performing the Services subject to the requirements of this Agreement. City retains Consultant on an independent contractor basis and not as an employee. Consultant retains the right to perform similar or different services for others during the term of this Agreement. Any additional personnel performing the Services under this Agreement on behalf of Consultant shall also not be employees of City and shall at all times be under Consultant's exclusive direction and control. Neither City, nor any of its officials, officers, directors, employees or agents shall have control over the conduct of Consultant or any of Consultant's officers, employees, or agents, except as set forth in this Agreement. Consultant shall pay all wages, salaries, and other amounts due such personnel in connection with their performance of Services under this Agreement and as required by law. Consultant shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, disability insurance, and workers' compensation insurance. 3.2.2 Schedule of Services. Consultant shall perform the Services expeditiously, within the term of this Agreement, and in accordance with the Schedule of Services set forth in Exhibit "B" attached hereto and incorporated herein by reference. Consultant represents that it has the professional and technical personnel required to perform the Services in conformance with such conditions. In order to facilitate Consultant's conformance with the Schedule, City shall respond to Consultant's submittals in a timely manner. Upon request of City, Consultant shall provide a more detailed schedule of anticipated performance to meet the Schedule of Services. 3.2.3 Conformance to ADDlicable Reouirements. All work prepared by Consultant shall be subject to the approval of City. 3.2.4 Substitution of Kev Personnel. Consultant has represented to City that certain key personnel will perform and coordinate the Services under this Agreement. Should one or more of such personnel become unavailable, Consultant may substitute other personnel of at least equal competence upon written approval of City. In the event that City and Consultant cannot agree as to the substitution of key personnel, City shall be entitled to terminate this Agreement for cause. As discussed below, any personnel who fail or refuse to perform the Services in a manner acceptable to the City, or who are determined by the City to be uncooperative, incompetent, a threat to the adequate or timely completion of the Project or a threat to the safety of persons or property, shall be promptly removed from the Project by the Consultant at the request of the City. The key personnel for performance of this Agreement are as follows: Michael Sutton, P.E., Principal (Civil 57667); John McCarthy, P.E., Project Manager (Civil 47583); Alan Ashimine, Environmental Lead. 3.2.5 City's Representative. The City hereby designates Mark Greenwood, P.E., Director of Public Works, or his/her designee, to act as its representative in all matters pertaining to the administration and performance of this Agreement ("City's Representative"). Consultant shall not accept direction or orders from any person other than the City Manager, City's Representative or his/her designee. City's Representative shall have the power to act on 2 Contract C behalf of the City for review and approval of all products submitted by Consultant, but not the authority to enlarge the Scope of Work or change the total compensation due to Consultant under this Agreement. The City Manager shall be authorized to act on City's behalf and to execute all necessary documents which increase the Scope of Work or change the Consultant's total compensation, subject to the provisions contained in Section 3.3 of this Agreement. 3.2.6 Consultant's Representative. Consultant hereby designates John McCarthy, P.E., Project Manager (47583), or his/her designee, to act as its representative for the performance of this Agreement ("Consultant's Representative"). Consultant's Representative shall have full authority to represent and act on behalf of the Consultant for all purposes under this Agreement. The Consultant's Representative shall supervise and direct the Services, using his/her best skill and attention, and shall be responsible for all means, methods, techniques, sequences, and procedures and for the satisfactory coordination of all portions of the Services under this Agreement. 3.2.7 Coordination of Services. Consultant agrees to work closely with City staff in the performance of Services and shall be available to City's staff, consultants and other staff at all times. 3.2.8 Standard of Care; Performance of Emplovees. Consultant shall perform all Services under this Agreement in a skillful and competent manner, consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Consultant represents and maintains that it is skilled in the professional calling necessary to perform the Services. Consultant warrants that all employees and subconsultants shall have sufficient skill and experience to perform the Services assigned to them. Finally, Consultant represents that it, its employees and subconsultants have all licenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Services, and that such licenses and approvals shall be maintained throughout the term of this Agreement. As provided for in the indemnification provisions of this Agreement, Consultant shall perform, at its own cost and expense and without reimbursement from the City, any services necessary to correct errors or omissions which are caused by the Consultant's failure to comply with the standard of care provided for herein. Any employee of the Consultant or its sub -consultants who is determined by the City to be uncooperative, incompetent, a threat to the adequate or timely completion of the Project, a threat to the safety of persons or property, or any employee who fails or refuses to perform the Services in a manner acceptable to the City, shall be promptly removed from the Project by the Consultant and shall not be re-employed to perform any of the Services or to work on the Project. 3.2.9 Laws and Re4ulations. Consultant shall keep itself fully informed of and in compliance with all local, state and federal laws, rules and regulations in any manner affecting the performance of the Project or the Services, including all Cal/OSHA requirements, and shall give all notices required by law. Consultant shall be liable for all violations of such laws and regulations in connection with Services. If Consultant performs any work knowing it to be contrary to such laws, rules and regulations, Consultant shall be solely responsible for all costs arising therefrom. Consultant shall defend, indemnify and hold City, its officials, directors, officers, employees, agents, and volunteers free and harmless, pursuant to the indemnification provisions of this Agreement, from any claim or liability arising out of any failure or alleged failure to comply with such laws, rules or regulations. 3 Contract C 3.2.10 Insurance. Consultant shall not commence work under this Agreement until it has provided evidence satisfactory to the City that it has secured all insurance required under this section. In addition, Consultant shall not allow any subconsultant to commence work on any subcontract until it has provided evidence satisfactory to the City that the subconsultant has secured all insurance required under this section. Without limiting Consultant's indemnification of City, and prior to commencement of Work, Consultant shall obtain, provide and maintain at its own expense during the term of this Agreement, policies of insurance of the type and amounts described below and in a form satisfactory to City. General Liabilitv insurance: Consultant shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage, including without limitation, blanket contractual liability. Defense costs shall be paid in addition to the limits. The policy shall contain no endorsements or provisions limiting coverage for (1) contractual liability; (2) cross liability exclusion for claims or suits by one insured against another; or (3) contain any other exclusion contrary to the Agreement. Automobile Liability Insurance: Consultant shall maintain automobile insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and property damage for all activities of the Consultant arising out of or in connection with Work to be performed under this Agreement, including coverage for any owned, hired, non -owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident. Professional Liabilitv (Errors S Omissions) Insurance: Consultant shall maintain professional liability insurance that covers the Services to be performed in connection with this Agreement, in the minimum amount of $1,000,000 per claim and in the aggregate. Any policy inception date, continuity date, or retroactive date must be before the effective date of this agreement and Consultant agrees to maintain continuous coverage through a period no less than three years after completion of the services required by this agreement. Covered professional services shall specifically include all work to be performed under the Agreement and delete any exclusions that may potentially affect the work to be performed (for example, any exclusions relating to lead, asbestos, pollution, testing, underground storage tanks, laboratory analysis, soil work, etc.). If coverage is written on a claims -made basis, the retroactive date shall precede the effective date of the initial Agreement and continuous coverage will be maintained or an extended reporting period will be exercised for a period of at least three (3) years from termination or expiration of this Agreement. Workers' Compensation Insurance: Consultant shall maintain Workers' Compensation Insurance (Statutory Limits) and Employer's Liability Insurance (with limits of at least $1,000,000). Consultant shall submit to City, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of the City of Palm Desert, its officers, agents, employees and volunteers. 4 Contract C Other provisions or requirements Insurance for Subconsultants: All Subconsultants shall be included as additional insureds under the Consultant's policies, or the Consultant shall be responsible for causing Subconsultants to purchase the appropriate insurance in compliance with the terms of these Insurance Requirements, including adding the City as an Additional Insured to the Subconsultant's policies. Consultant shall provide to City satisfactory evidence as required under Insurance Section of this Agreement. Proof of Insurance: Consultant shall provide certificates of insurance to City as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers' compensation. Insurance certificates and endorsement must be approved by City's Risk Manager prior to commencement of performance. The certificates and endorsements for each insurance policy shall be signed by a person authorized by that insurer to bind coverage on its behalf. Current certification of insurance shall be kept on file with City at all times during the term of this contract. City reserves the right to require complete, certified copies of all required insurance policies, at any time. Duration of Coveraae: Consultant shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the Work hereunder by Consultant, his agents, representatives, employees or subconsultants. Citv's Rights of Enforcement: In the event any policy of insurance required under this Agreement does not comply with these specifications or is canceled and not replaced, City has the right but not the duty to obtain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Consultant or City will withhold amounts sufficient to pay premium from Consultant payments. In the alternative, City may cancel this Agreement. Acceptable Insurers: All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance in the State of California, with an assigned policyholders' Rating of A- (or higher) and Financial Size Category Class VI (or larger) in accordance with the latest edition of Best's Key Rating Guide, unless otherwise approved by the City's Risk Manager. Waiver of Subrociation: All insurance coverage maintained or procured pursuant to this agreement shall be endorsed to waive subrogation against the City of Palm Desert, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow Consultant or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. Consultant hereby waives its own right of recovery against the City of Palm Desert, and shall require similar written express waivers and insurance clauses from each of its subconsultants. Enforcement of Contract Provisions (Non Estoppel): Consultant acknowledges and agrees that any actual or alleged failure on the part of the City to inform Consultant of non-compliance with any requirement imposes no additional obligations on the City nor does it waive any rights hereunder. Primary and Non -Contributing Insurance: All insurance coverages shall be primary and any other insurance, deductible, or self-insurance maintained by the indemnified parties shall not contribute with this primary insurance. Policies shall contain or be endorsed to contain such provisions. 5 Contract C Reauirements Not Limitina: Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type. Notice of Cancellation: Consultant agrees to oblige its insurance agent or broker and insurers to provide to City with a thirty (30) day notice of cancellation (except for nonpayment for which a ten (10) day notice is required) or nonrenewal of coverage for each required coverage. Additional Insured Status: General liability, Automobile Liability, and if applicable, Pollution Liability, policies shall provide or be endorsed to provide that the City of Palm Desert and its officers, officials, employees, and agents shall be additional insureds with regard to liability and defense of suits or claims arising out of the performance of the Agreement, under such policies. This provision shall also apply to any excess liability policies. Citv's Riaht to Revise Specifications: The City reserves the right at any time during the term of the contract to change the amounts and types of insurance required by giving the Consultant ninety (90) days advance written notice of such change. If such change results in substantial additional cost to the Consultant, the City and Consultant may renegotiate Consultant's compensation. Self -Insured Retentions.: Any self -insured retentions must be declared to and approved by City. City reserves the right to require that self -insured retentions be eliminated, lowered, or replaced by a deductible. Self-insurance will not be considered to comply with these specifications unless approved by City. Timely Notice of Claims: Consultant shall give City prompt and timely notice of claims made or suits instituted that arise out of or result from Consultant's performance under this Agreement, and that involve or may involve coverage under any of the required liability policies. Safety: Consultant shall execute and maintain its work so as to avoid injury or damage to any person or property. In carrying out its Services, the Consultant shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the work and the conditions under which the work is to be performed. Safety precautions, where applicable, shall include, but shall not be limited to: (A) adequate life protection and lifesaving equipment and procedures; (B) instructions in accident prevention for all employees and subconsultants, such as safe walkways, scaffolds, fall protection ladders, bridges, gang planks, confined space procedures, trenching and shoring, equipment and other safety devices, equipment and wearing apparel as are necessary or lawfully required to prevent accidents or injuries; and (C) adequate facilities for the proper inspection and maintenance of all safety measures. Additional Insurance: Consultant shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the work. 6 Contract C 3.3 Fees and Payments. 3.3.1 Compensation. Consultant shall receive compensation, including authorized reimbursements, for all Services rendered under this Agreement at the rates set forth in Exhibit "C" attached hereto and incorporated herein by reference. The total compensation shall not exceed Two hundred eighty-one thousand seven hundred forty- four dollars ($281,744) without authorization of the City Council or City Manager, as applicable, per the Palm Desert Municipal Code. Extra Work may be authorized, as described below, and if authorized, will be compensated at the rates and manner set forth in this Agreement. 3.3.2 Pavment of Compensation. Consultant shall submit to City a monthly invoice which indicates work completed and hours of Services rendered by Consultant. The invoice shall describe the amount of Services provided since the initial commencement date, or since the start of the subsequent billing periods, as appropriate, through the date of the invoice. City shall, within 30 days of receiving such invoice, review the invoice and pay all non -disputed and approved charges thereon. If the City disputes any of Consultant's fees, the City shall give written notice to Consultant within thirty (30) days of receipt of an invoice of any disputed fees set forth therein. 3.3.3 Reimbursement for Expenses. Consultant shall not be reimbursed for any expenses unless authorized in writing by City, or included in Exhibit "C" of this Agreement. 3.3.4 Extra Work. At any time during the term of this Agreement, City may request that Consultant perform Extra Work. As used herein, "Extra Work" means any work which is determined by City to be necessary for the proper completion of the Project, but which the Parties did not reasonably anticipate would be necessary at the execution of this Agreement. Consultant shall not perform, nor be compensated for, Extra Work without authorization from the City Council or City Manager, as applicable, per the Palm Desert Municipal Code. 3.3.5 Rate Increases. In the event that this Agreement is renewed pursuant to Section 3.1.2, the rate set forth in Exhibit "C" may be adjusted each year at the time of renewal as set forth in Exhibit "C." 3.3.6 Prevailing Wages. Consultant is aware of the requirements of California Labor Code Section 1720, et seq., and 1770, et seq., as well as California Code of Regulations, Title 8, Section 16000, et seq., ("Prevailing Wage Laws"), which require the payment of prevailing wage rates and the performance of other requirements on "public works" and "maintenance" projects. SINCE the Services are being performed as part of an applicable "public works" or "maintenance" project, as defined by the Prevailing Wage Laws, Consultant agrees to fully comply with such Prevailing Wage Laws. City shall provide Consultant with a copy of the prevailing rates of per diem wages in effect at the commencement of this Agreement. Consultant shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at the Consultant's principal place of business and at the project site. Consultant shall defend, indemnify and hold the City, its officials, officers, employees, agents, and volunteers free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. 7 Contract C officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Consultant's Services, the Project or this Agreement, including without limitation the payment of all consequential damages, expert witness fees and attorneys fees and other related costs and expenses. Notwithstanding the foregoing, to the extent Consultant's Services are subject to Civil Code Section 2782.8, the above indemnity shall be limited, to the extent required by Civil Code Section 2782.8, to claims that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the Consultant. 3.5.6.2 Additional Indemnitv Obliqations. To the fullest extent permitted by law, Consultant shall defend, with counsel of City's choosing and at Consultant's own cost, expense and risk, any and all claims, suits, actions or other proceedings of every kind covered by Section 3.5.6.1 that may be brought or instituted against City or its directors, officials, officers, employees, volunteers and agents. Consultant shall pay and satisfy any judgment, award or decree that may be rendered against City or its directors, officials, officers, employees, volunteers and agents as part of any such claim, suit, action or other proceeding. Consultant shall also reimburse City for the cost of any settlement paid by City or its directors, officials, officers, employees, agents or volunteers as part of any such claim, suit, action or other proceeding. Such reimbursement shall include payment for City's attorney's fees and costs, including expert witness fees. Consultant shall reimburse City and its directors, officials, officers, employees, agents, and/or volunteers, for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. Consultant's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by the City, its directors, officials officers, employees, agents, or volunteers. 3.5.7 Entire Agreement. This Agreement contains the entire Agreement of the parties with respect to the subject matter hereof, and supersedes all prior negotiations, understandings or agreements. This Agreement may only be modified by a writing signed by both parties. 3.5.8 Governing Law. This Agreement shall be governed by the laws of the State of California. Venue shall be in Riverside County. 3.5.9 Time of Essence. Time is of the essence for each and every provision of this Agreement. 3.5.10 Citv's Right to Emplov Other Consultants. City reserves right to employ other consultants in connection with this Project. 3.5.11 Successors and Assigns. This Agreement shall be binding on the successors and assigns of the parties. 3.5.12 Assignment or Transfer. Consultant shall not assign, hypothecate, or transfer, either directly or by operation of law, this Agreement or any interest herein without the prior written consent of the City. Any attempt to do so shall be null and void, and any assignees, hypothecates or transferees shall acquire no right or interest by reason of such attempted assignment, hypothecation or transfer. 3.5.13 Construction: References: Captions. Since the Parties or their agents have participated fully in the preparation of this Agreement, the language of this Agreement shall be construed simply, according to its fair meaning, and not strictly for or against any Party. Any term referencing time, days or period for performance shall be deemed calendar days and not work days. All references to Consultant include all personnel, employees, agents, and subconsultants of Consultant, except as otherwise specified in this Agreement. All references to City include its elected officials, officers, employees, agents, and volunteers 10 Contract C except as otherwise specified in this Agreement. The captions of the various articles and paragraphs are for convenience and ease of reference only, and do not define, limit, augment, or describe the scope, content, or intent of this Agreement. 3.5.14 Amendment; Modification. No supplement, modification, or amendment of this Agreement shall be binding unless executed in writing and signed by both Parties. 3.5.15 Waiver. No waiver of any default shall constitute a waiver of any other default or breach, whether of the same or other covenant or condition. No waiver, benefit, privilege, or service voluntarily given or performed by a Party shall give the other Party any contractual rights by custom, estoppel, or otherwise. 3.5.16 No Third-Partv Beneficiaries. There are no intended third party beneficiaries of any right or obligation assumed by the Parties. 3.5.17 Invaliditv: Severabilitv. If any portion of this Agreement is declared invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions shall continue in full force and effect. 3.5.18 Prohibited Interests. Consultant maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Consultant, to solicit or secure this Agreement. Further, Consultant warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Consultant, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Agreement, no member, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom. 3.5.19 Eoual Ormortunity Emr)lovment. Consultant represents that it is an equal opportunity employer and it shall not discriminate against any subconsultant, employee or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex, or age. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination. 3.5.20 Labor Certification. By its signature hereunder, Consultant certifies that it is aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for Worker's Compensation, or to undertake self- insurance in accordance with the provisions of that Code and agrees to comply with such provisions before commencing the performance of the Services. 3.5.21 Authoritv to Enter Agreement. Consultant has all requisite power and authority to conduct its business and to execute, deliver, and perform the Agreement. Each Party warrants that the individuals who have signed this Agreement have the legal power, right, and authority to make this Agreement and bind each respective Party. 3.5.22 Counterparts. This Agreement may be signed in counterparts, each of which shall constitute an original. 11 Contract C 3.6 Subcontracting. 3.6.1 Prior Approval Required. Consultant shall not subcontract any portion of the work required by this Agreement, except as expressly stated herein, without prior written approval of City. Subcontracts, if any, shall contain a provision making them subject to all provisions stipulated in this Agreement. CITY OF PALM DESERT in Justin McCarthy, Interim City Manager ATTEST: M Rachelle D. Klassen, City Clerk APPROVED AS TO CONTENT: By: Mark Greenwood, P.E. Director of Public Works APPROVED AS TO FORM: am Robert Hargreaves, City Attorney Best Best & Krieger LLP MICHAEL BAKER INTERNATIONAL, INC. in an Michael Sutton, P.E., Vice President [INSERT NAME AND TITLE] 12 Contract C EXHIBIT "A, - SCOPE OF SERVICES t 'Prohssional Engineering & Design S'wv' ces br . Une 4 Drsinagsf Project No. 522-16., TECHNICAL APPROACHMORK PLAN UNDERSTANDING THE TECHNICAL APPROACH Project Understanding The City is requesting proposals from qualified firms for the preparation of a feasibility study, data collection, hydrology and hydraulic analysis, recommended facility plan, and required environmental documents for the Line 4 Storm Drain System identified in the North Sphere Drainage Master Plan. The storm drain lines would be installed in portions of Country Club Drive, Eldorado Drive, Frank Sinatra Drive and Tamarisk Row. These systems were recommended as part of the City's North Sphere Drainage Master Plan prepared by VA Consulting in October, 2007. The recommended system (Line 4A and 4B) in the Master Plan also includes a five acre retention basin located easterly of Washington Street on a vacant parcel in unincorporated RC. The design work will be completed in two phases, with the first phase to include the feasibility study, preliminary design and environmental documentation for the project. The second phase would include the final design for the recommended improvements. This proposal is for the Phase 1 work. The recommended improvements in the Master Plan include a five acre storm water retention basin as the terminus of the Line 4A and 46 improvements. The land cost for the basin was identified to be $5,000,000 in 2007. A key element of the work will be the preparation of a feasibility study to re-evaluate the Master Plan recommendations to determine if there is a more cost-effective solution for the terminus of the storm drain. Potential alternatives identified in the RFP include extending the storm drain to outlet into the Thousand Palms Channel or the Whitewater Channel. The Thousand Palms Channel is approximately 4,000 feet from the basin site across the 1-10 freeway. The 5 Ames basin site south of Country Club and east of Washington Street. Whitewater Channel is approximately 18,000 feet from the basin down Country Club and Indio Boulevard. Numerous other vacant lots along these alignments may also provide retention basin opportunities. The CVWD is currently developing improvements to various portions of these channel systems and coordination with CVWD will be an important element of the feasibility analysis. Future CVWD improvements such as the Avenue 38 channel just north of the 1-10 could potentially offer opportunities to outlet Line 4B and eliminate the need for the significant facilities along Tamarisk row. Understanding the future regional improvements and identifying opportunities to work with these planned facilities could result in cost-effective alternative solutions. Desert hydrology and the design of appropriate flood protection can be challenging in Michael Baker understands the Coachella Valley due to the flashy nature of storm events and the terrain in the desert hydrology and the design of flood protection valley. The City needs a consultant Team with the experience, advanced tools, and systems in this environment agency relationships to develop a cost-effective solution for the Line 4 Storm Drain including the effective use of 2D modeling to reduce cost. System. The preliminary design of the Line 4A & B systems include almost 32,000 feet Technical Approach/Work Plan I Page 12 of new storm drain box culverts and reinforced concrete pipe at a project cost of over $23 million. In addition, Country Club Drive and Washington Street are major City roadways with heavy traffic loads. Considering the improvement cost and impacts to the City residences and businesses we believe it is important to use advanced 1 D and 2D hydrology and hydraulic modeling to more accurately model the proposed system and develop recommendations for the final design. The Michael Baker Team has the necessary experience and tools to effectively and efficiently complete the analysis and design to establish the recommended improvements. Technical Approach The Team will engage City staff, stakeholders, and approving agencies in a collaborative and proactive process to define the recommended storm drain improvements, resolve outstanding issues, support environmental clearance, and lead to the final design and construction of the Line 4 improvements within the established schedule. The development of the evaluation and development of a recommended design for the Line 4 system will be orchestrated in a dynamic process that is linked by a genuine spirit of team work between Michael Baker, the City, stakeholders, and the approving agencies. Michael Baker has identified several key issues which will need to be addressed to successfully complete this project. Resolution of these key issues is incorporated into our project approach and scope and work. We have provided a brief description of the issues, and our methods and innovative approaches to resolve them Hydrology and Hydraulic Modeling The existing hydrology by VA Consulting was prepared in 2007 at a master plan level and is proposed to be updated as part of the Phase 1 work. In 2006, the National Oceanic and Atmospheric Administration (NOAA) published Atlas 14. Atlas 14 is an update to the precipitation frequency data previously published in Atlas 2. The document includes approximately 40 years of additional rainfall record data. RCFC&WCD hydrology manual guidelines indicate that the latest version of the NOAA atlas will be used for precipitation data. Additional detail is necessary for the design of the project including the evaluation of street flow depths to comply with City standards, using current rainfall and topographic data. Modifications to the hydrology to revise the rainfall data and hydrology procedure are anticipated to modify the design flow rates. Michael Baker will use the latest Advanced Engineering Software (AES) computer software to perform rational method hydrology analysis. Hydrology will be performed for the 3, 6 and 24-hour duration storms for the 10-year and 100-year events, and following the procedures outlined in the RCFC&WCD's Hydrology Manual. Innovative Value -Added Approach: Desert hydrology can be described as flashy with short -duration high -intensity storm events. These types of events can produce high peak flow rates with limited runoff volume due to the short duration. Designing a storm drain system using a traditional 1D steady-state peak flow rate can result in significantly oversizing the storm drain system by not accounting for the storage volumes in the street sections and storm drain facilities. Michael Baker proposes to compare the results of traditional 1 D steady-state model to an advanced 2D unsteady model, with a goal of saving money on storm drain construction costs. Technical Approach/Work Plan I Page 13 rofessbnal Engineering & Design Servicis for , ne 4 Drainagj Project Na 522-16`.;, To begin, Michael Baker will use WSPGW hydraulics program developed by CIVILDESIGN Corp., which has recently been incorporated into the XP Solutions software. The WSPGW program is a 1 D hydraulic analysis based on a steady-state flow rate. This methodology does not account for the actual volume of runoff during a storm event, and only uses the peak flow rates calculated in the hydrology analysis. This program has been widely used throughout Southern California and can be effective for the design of storm drain systems. However, in areas with flat gradients, short -duration storm events, and high downstream surface water controls, which is very common in the desert areas like the City, the program can result in extremely large storm drain systems. Michael Baker has extensive experience Coupled 2D modeling used to develop storm improvements for downtown Redlands. performing hydrology and hydraulics analyses in these areas, including projects in La Quinta, Palm Springs, and Cathedral City. Storms in the low desert regions come and go quickly and traditional hydraulic modeling does not realistically mimic their peak scenarios. WSPGW hydraulics does not consider the unsteady nature of storm water runoff or the volume of the runoff compared to the volume of the street sections and storm drain conduit system. These factors can only be considered using an unsteady dynamic model, and can potentially result in significant cost savings on a project. Therefore a second model, XP-SWMM, part of the XP Solutions software package, will also be used to effectively model the physical realities of the proposed storm drain system. A combined 1 D and 2D model will be developed to size the storm drain system and evaluate the street flooding using unit hydrographs prepared in accordance with the RC guidelines. The Team has used the XP software for other Southern California cities with construction cost savings up to 30% compared to steady-state modeling, with the recent applications in the Coachella Valley. A comparison of the WSPGW and XP-Storm results will be prepared and discussed with the City to determine which method is best used for the final design. Available storm water retention opportunities exist along the project alignment that could be used to reduce or eliminate some storm drain requirements. Also, acceptable levels for flood conveyance in street sections and opportunities to pond water in parking lots, fields, and other open space could further reduce facility costs. For the City of Tustin, Michael Baker prepared detailed 1 D/21) models of the existing and proposed storm drain systems to identify ponding depths in streets and parking lots and worked with the developers to grade lots to allow peak flow storage that eliminated the need for costly drainage improvements outside of the City limits which saved millions of dollars in cost and construction delays. 1 D and 2D analysis of subsurface storm drain and acceptable flooding depths in street and parking areas in the City of Tustin. Technical Approach/Work Plan I Page 14 Proh'ssional Engineering & Design Servkes for Line 4 Drainage Protect No. 522-16 I'Q7Q -1 The Team will evaluate all potential sites and options in conjunction with the City to identify the advantages and disadvantages for the sites and their potential to reduce the overall system costs. The use of the 2D flood modeling is Existing fields at a Ronald Reagan School and Freedom Park are currently being proposed for the modeling to full used for storm water storage and have opportunities for increased capacities. evaluate the storm water runoff volumes and to consider both the volume in the existing/proposed retention basins and the proposed storm drain facilities themselves. This evaluation by itself has the potential to significantly reduce storm drain pipes and box culvert sizes. Utility Coordination and Constructability Utility coordination and mapping is critical on this project due to the potential for conflict with the existing utilities within the street sections. It is essential that a good management plan and effective quality control be carved out during the planning phase to minimize costly changes during the final design and construction that can overrun a project budget. Michael Baker has extensive experience using the Virtual Design and Construction (VD&C) approach to project design management. Civil 3D models give a real life visualization of a design. Michael Baker proposes to complete the utility mapping during the initial stages of the Preliminary Design Phase. By doing the research up front, we will identify constructible systems that minimizes final design and construction cost overruns due to re -work and construction delays. During the alignment analysis, the locations of the utilities will be critical in determining the final alignment of the proposed storm drain systems. The Michael Baker Team includes Kana, who have extensive experience potholing to assist in understanding the constraints if necessary. ROW Constraints and Acquisition Civil 3D model of existing utility systems in a street section used to facilitate a planned storm drain alignment. The conceptual alignment of the storm drainage and retention basin improvements in the RFP includes impacts to private properties. An evaluation of other possible alignment or basin locations will also have private property impacts. Effective ROW coordination, management, and acquisition will be critically important in the feasibility study and for the final recommendations and project implementation. The engineers and environmental specialists at Michael Baker will work in conjunction with the City to assess the ROW requirements and develop an alignment to minimize the required acquisition of Technical Approach/Work Plan I Page 15 35r1l� P7- mall En�nooring & > gn Services for winaoo Probd No. 522-16 * J land. The Michael Baker Team is supported by TJC Property services to effectively assess real estate acquisition costs and opportunities. Multi -Agency Coordination The project is located predominately in the City, however, the proposed retention basin is located in unincorporated RC, and alternative connections to regional facilities will require approval from CVWD. Connections to the Thousand Palms Channel could also impact Caltrans highways and Union Pacific Railroad (UPRR) tracks. The Team has a close relationship and experience working with RC (Flood and TLMA), CVWD, Caltrans, and UPRR. We will coordinate with the City, CVWD and the other agencies early and often to facilitate dialogue and direction for the alternative alignment study and project recommendations. It is important to understand the requirements of the City, County, and CVWD as well as getting input from the other impacted agencies in order to fully evaluation alternatives and develop a project that will be acceptable for final design and construction. WORK PLAN AND PROJECT SCHEDULE The Phase 1 work will focus on the preparation of technical studies and a comprehensive alternatives analysis for selection of the recommended alternative to address the project goals, and to support the CEQA documentation. The City, CVWD and others have prepared several hydrologic and hydraulic models of this watershed and surrounding facilities during previous studies. This phase of work will focus on coordinating and expanding the studies and level of detail to develop a recommended system for the storm drain improvements to provide the required level of protection and minimize project impacts. The work effort during this phase will include collecting data/models from the previous studies, and completing the hydrology and detailed hydraulic analyses for the development of an alternatives feasibility analysis. Detailed hydrology will be prepared for the study area. We will use the previous hydrology models where possible and modify them as necessary to provide the required level of detail. Coupled 1 D and 2D hydraulic flood routing models will be used to develop the system requirements. This phase will also include baseline studies for the preparation of topographic mapping, utility coordination, ROW mapping, and environmental constraints that will be important factors in the alternatives analysis. Coordination with CVWD and RCFC&WCD will be initiated early in the process to discuss opportunities and constraints, and alternatives for the discharge of Line 4. A feasibility and value -engineering assessment for the project alternatives will be prepared, and a recommended project for final design will be identified. A technical project report will be prepared to support the recommendation and for inclusion as part of the alternatives analysis for the City's CEQA document. The Michael Baker approach is to develop an Alternatives Analysis that is prepared in a way so that it can be used for CEQA compliance (typically two separate analyses are required). The conclusion of the Phase 1 work will result in the conceptual approval of the preliminary design plans for the recommended improvements. Technical Approach/Work Plan I Page 16 � s:,-;c+c gyp'.. t. �:, a�N!'k-t►��'.,.: „f� .:_ • "li'rofassional EnginNrIIng & Design Services for Una 4 Dninaga fhrojact No. 522- Recommended Scope of Work Addressing the key issues associated with the project will dictate the work approach which basically follows a sequential and logical planning process. We will avoid schedule and budget problems through early resolution of project issues, and timely consultation with the City, CVWD, and other agencies. The goal of the project will be to develop a cost-effective and feasible alternative for the installation of the proposed Line 4 improvements. In our experience in the development of major storm drain facilities, there are several essential factors involved in providing the most effective product that satisfies the goals of the project. These factors have been incorporated into the technical work program that we have developed for the project. • Develop a solid technical analysis of the baseline existing conditions to provide a foundation for innovation and formulation of alternatives. • Clearly define the project goals, and establish the design criteria used for all technical analysis, alternative formulation, and feasibility comparison including hydraulics results comparisons (WSPGW versus XP storm). • Identify design constraints early in the project development. • Provide a clear line of communication for the resolution of project issues, conflicts and constraints identified in the development process with the City, County, CVWD and other reviewing agencies. The proposed Work Plan is based upon our previous experience with the engineering and design of similar storm drain improvement projects and the requirements in the RFP. The following task items are proposed to be prepared to successfully complete the project: Task 1— Project Administration and Meetings 1.1 Kick-off Meeting. Michael Baker will hold a Kick-off meeting to commence the project with the City. Michael Baker will prepare the meeting agenda and meeting minutes. The meeting will be used to initiate the project and discuss schedules, communications, expectations, critical issues, and design criteria. Deliverables: Meeting agenda and meeting minutes 1.2 Project Meetings and Coordination. Michael Baker will manage project duties for the full project in order to assure a cost-efficient, quality process. As the prime contractor, our staff will provide a suite of disciplines to effectively coordinate and communicate leading to design approval. This task includes overall project management, project schedule and maintenance, liaison with affected agencies, meeting leadership, progress monitoring and maintenance of project files. Michael Baker will supervise, coordinate, monitor and review design for conformance with agency standards, policies and procedures. As a part of this task, Michael Baker will have monthly progress meetings with the City. Deliverables: Meeting attendance, agendas, and minutes; project schedules Technical Approach/Work Plan I Page 17 `• 'A"r qeY' -• ,a,,,iamS"`c• t-I.r "A115 ,; n 1,4 -at" ' , • t ,Professional Engineering & Design Services for; : Une 4 Drainage Project No. 522-16 ;; r Task 2 — Project Research and Data Collection Michael Baker will obtain and review existing available technical studies from the City, CVWD, Caltrans, USACE, Federal Emergency Management Act (FEMA), and other known sources related to the project improvements. The information collected will include hydrology and hydraulics studies, environmental documents, geotechnical studies, future proposed development projects, as well as as -built plans for existing facilities along the project reach including the upstream and downstream tie-in locations. Deliverables: Summary of existing data pertaining to the project improvements Task 3 — Surveying and Mapping 3.1 Survey Control/ROW Mapping. Michael Baker will research and review record information and other survey and mapping control data to compile a preliminary base map. Upon completion of this review and compilation, Michael Baker will perform a field survey to establish control for the project to locate and measure existing monumentation, including, but not limited to, quarter corners and section comers, including City benchmarks local to the project. The data from the field survey will be processed through a least squares adjustment, analyzed and constrained to local CORS stations to establish coordinate values for monuments, aerial targets, benchmarks and other survey control points observed in the field survey. The basis of horizontal control will be State Plane coordinates on the North American Horizontal Datum of 1983 (NAD83), and the vertical control will be based on North American Vertical Datum of 1988 (NAVD88). All survey data will be combined and compiled together with record information to establish a base map showing the project rights of way, property lines and centerline control. 3.2 Topographic Survey Base Map. Michael Baker will prepare an Aerial Topographic Map of the project at a scale of 1 "=40' with one foot contour intervals. The work will include preparation of the flight plan and target layout, acquiring imagery, analytical aerotriangulation, compilation of the plannimetric and topographic features to digital medium, and final analysis of ground survey check profiles to verify ground truth and accuracy of the compiled aerial map. Additionally, Michael Baker will perform a supplemental field survey to augment the Aerial Topographic Map and locate and identify any utilities obstructed from aerial view and verify the character of above -ground utilities. This field survey work will also obtain invert elevations of required underground facilities along the proposed route. 3.3 Utility Base Map. The City will relay the utility plans from various purveyors to Michael Baker so that data can be inserted into a CAD base map. Michael Baker will review record drawings, utility maps and proposed future utility improvements received from the utility companies, and will prepare a utility base map based upon the information provided on the drawings. Deliverables: Topographic and utility maps Technical Approach/Work Plan I Page 18 MOProfessional Engineering do Design Services for Line 4 Drainage Project No. 522-76 Task 4 — Hydrology and Hydraulic Studies Michael Baker will review all relevant existing drainage study documents and verify existing drainage conditions within North Sphere Line 4 area delineated in the Drainage Master Plan (VA 2007). Michael Baker will then perform an independent Hydrology Study that will update the recommendations and findings of the Drainage Master Plan. The hydrology study will conform to the current RCFC&WCD Hydrology Manual and guidelines, will incorporate changes in field conditions, and provide sufficient hydrology detail that can be used in the proposed system design. For drainage area delineation, Michael Baker will utilize topographic data developed from aerial and field survey, and supplement with existing County of Riverside and CVWD topographic data. Hydrology calculation will be performed utilizing the latest version of AES software (RATSCx and FLOODSCx for rational method and unit hydrographs methods, respectively). The rational method hydrology will be used to size the storm drain inlets while synthetic hydrographs will be used to determine flow volumes for the 2D flood routing analysis pipe system and retention basin sizing. This hydrology study will evaluate the 3-, 6-, and 24-hour duration storm for the 10- year and 100-year events based on the most current rainfall data published in the NOAA Atlas 14. The proposed storm drain systems will be sized to convey the worst case duration, 1 0-year storm below the top of curb elevation and the 100-year storm within the public ROW. This task will include delineation of the tributary drainage area and project hydrology map. Deliverables: Hydrology and hydraulics studies Task 5 — Feasibility Study Michael Baker will prepare an alternatives analysis to determine the most viable project option that is acceptable to City, County, CVWD, stakeholders, and the regulatory agencies. The proposed retention basin and storm drain identified in the RFP will be evaluated, along with new alternative alignments and modifications identified by the Team. A matrix of evaluation criteria will be developed and analyzed in conjunction with City to identify a recommended project. The analysis will include concept design plans, hydraulic effectiveness, preliminary construction costs, utility conflicts, ROW, environmental impacts and mitigation requirements, traffic control, constructability, and other intangible impacts. A conceptual plan will be developed for each alternative that is evaluated in detail. The Team will prepare the conceptual plan for the alternatives and use the horizontal and vertical alignments for the preliminary system hydraulics. The concept plans will be used to identify ROW constraints, environmental impacts, and utility conflicts. Michael Baker's environmental and regulatory staff will use the analysis to support the environmental documentation. Michael Baker's in-house construction management staff will review each alternative for value engineering and constructability. The Alternatives Analysis will serve as the foundation for the environmental documentation. Deliverables: Alternative conceptual designs; altematives evaluation matrix; recommended improvements Technical Approach/Work Plan I Page 19 ' rrJ : -.: fir: .h;�: r.::i�j -&'*'.Pr;QAX84ngI6�dng 8 Design Servkesfore` Linn 4 Drainage Project - No. 522- 6 Task 6 — Preliminary Design Report Michael Baker will prepare a preliminary design report which will present and document the results of the alternatives analysis. The report will include text, graphics, preliminary plan layouts, alternatives analysis discussion, and recommendation of a preferred project. Technical analysis will be summarized with detailed analysis provided as an appendix. Deliverables: Draft and Final Preliminary Design Reports Task 7 - Preliminary Improvement Plans Michael Baker will develop preliminary design plans for the recommended alternative from the project refinement and Alternatives Analysis. The plans will be prepared for all sections of the recommended improvements. The plans will include a detailed plan layout utilizing the compiled base mapping. Additional information to be included on the plans will be facility sizes, typical cross sections, utility locations/conflicts, and ROW requirements. A vertical profile of the systems will be developed and used for the detailed hydraulic analysis. The plans will clearly delineate and define the project improvements to develop a project description necessary for the preparation of the regulatory permits. Deliverables: Preliminary improvement plans, preliminary engineers estimate Task 8 — Environmental Documentation Michael Baker will prepare an Initial Study/Mitigated Negative Declaration (IS/MND) under CEQA. While the use of a Categorical Exemption was explored for the project, the proposed facilities would involve a sizable increase in drainage capacity within the area. The length of pipeline improvements would require construction in proximity to a diverse range of land uses and result in traffic disruption over the short term. As such, based on a preliminary review of the proposed project, a scope of work for the IS/MND is provided below. 8.1 Technical Studies. Michael Baker will prepare the following technical studies to support the analysis within the IS/MND: Task 8.1.1 Air Quality. Fugitive dust and equipment exhaust emissions from construction activities will be quantitatively evaluated using the California Emissions Estimator Model version 2013.2.2 (CalEEMod). The air pollutant emissions during construction will be compared to the SCAQMD regional thresholds of significance. Modeled construction will also be compared to the SCAQMD Localized Significance Thresholds to determine whether the localized impacts would occur. The operational analysis will be qualitative and address the fact that the project would not include any operational equipment or generate a significant amount of vehicle trips. Project consistency with the 2012 Air Quality Management Plan will be evaluated. Michael Baker will also qualitatively discuss naturally occurring asbestos impacts. The results of the air quality analysis will be summarized within the IS/MND. A description of existing conditions, potential impacts, and mitigation measures (if applicable) will be provided. 8.1.2 Greenhouse Gas Emissions. Michael Baker will prepare an inventory of the greenhouse gas (GHG) emissions (i.e., nitrous oxide, methane, and carbon dioxide) from direct sources (i.e., construction equipment). The emissions inventory will Technical Approach/Work Plan I Page 20 row- t ~Professional Engineering & Design Services for `Line 4 Drainage.Projs No. 522- 6 � be compiled utilizing CaIEEMod. The operational analysis will qualitatively describe operational activities based on the assumption that the project would not include any operational equipment or generate a significant amount of vehicle trips. The results of the GHG analysis will be summarized within the IS/MND. A description of existing conditions, potential impacts, and mitigation measures (if applicable) will be provided. 8.1.3 Noise. Michael Baker will review applicable noise and land use compatibility criteria for the project area. Noise standards regulating noise impacts will be discussed for land uses adjacent to the proposed roadway improvements. The construction noise impacts will be evaluated in terms of maximum levels (Lmax), hourly equivalent continuous noise levels (Leq), and the frequency of occurrence. The operational noise analysis will qualitatively address the fact that the project would not include any operational equipment or generate a significant amount of vehicle trips. Compliance with applicable noise standards will be evaluated, with recommended mitigation measures included where appropriate. This scope excludes on -site noise measurements. The results of the noise analysis will be summarized within the ISIMND. A description of existing conditions, potential impacts, and mitigation measures (if applicable) will be provided. 8.1.4 Cultural Resources. Michael Baker has retained Cogstone Resource Management, Inc. to prepare a Cultural Resources Report for the project. The Report will be based upon a literature search to be performed at the Eastern Information Center (EIC) and the Western Science Center (WSC). The Report will also include assistance to the City with consultation with Native American tribes as required under CEQA and AB 52. The report will characterize the results of the records search and previous consultation efforts, to determine baseline conditions, assess potential impacts to cultural resources resulting from the project, and make appropriate recommendations to avoid or minimize any potentially significant impacts. The results of the Cultural Resources Report will be summarized within the IS/MND. A description of existing conditions, potential impacts, and mitigation measures (if applicable) will be provided. 8.1.5 Biological Resources. Michael Baker's in-house team of biologists will prepare a Biological Habitat Assessment for the proposed project, Given the developed nature of the proposed pipeline alignment within City roadway ROW, it is anticipated that the Habitat Assessment would focus on potential impacts at the five -acre basin included as part of the project. The Habitat Assessment would include a literature review existing database and agency records, a detailed field survey, and preparation of a biological technical report. The report will document all plant and wildlife species and habitats currently occurring onsite, the site's potential to support any special -status species, and whether the site supports potential jurisdictional and riparian/riverine features. The report will include a map of the plant communities occurring onsite and their respective acreages. The report will include a brief analysis of the project impacts to biological resources, suggestions for updating previous clearances issued for the project that may be needed prior to development, and mitigation measures, if needed. 8.2 Research and Investigation. Michael Baker will initiate the CEQA process by attaining and evaluating necessary information with respect to the proposed project. Project research will include coordination with the City to acquire relevant environmental data, previous studies for the area and other available files, exhibits, maps, and reference documents. The Technical Approach/Work Plan I Page 21 Pro%ssllonal Engineering dr Design Services for. Line 4 Drainage Project . No. 522-16 , .� . lk investigation will include a site visit to review existing land uses and environmental conditions, as well as a photographic inventory of on -site and surrounding uses. Based upon the detailed information obtained during project initiation, Michael Baker will draft a preliminary project description for incorporation into the Initial Study. 8.3 Preparation of Initial Study. Michael Baker will prepare an Initial Study in accordance with the CEQA Guidelines. The Initial Study will include detailed explanations of all checklist determinations and discussions of potential environmental impacts. The analysis will be in accordance with Public Resources Code Section 21080 (c) and CEQA Guidelines Section 15070. 8.4 Preparation of the Public Review IS/MND. With the anticipated conclusion in the Initial Study that no significant environmental effects will occur, a Mitigated Negative Declaration (MND) will be prepared. Following this determination, Michael Baker will prepare the Notice of Intent to Adopt (NO1) and the MND for City review. The NO1 and MND will be attached to the Initial Study to fully explain the proposed project and its effects. Twenty-five (25) copies, one (1) camera-ready original, and an electronic file of the IS/MND will be provided to the City. All technical appendices will be provided in PDF format on CD. Michael Baker will submit the IS/MND to the State Clearinghouse and additional agenciesfinterested parties as directed by the City. This task assumes that the City would be responsible for any radius mailing or newspaper noticing required for public review. The ISIMND would be subject to a mandatory 30-day public review period. 8.5: Preparation of the Final ISIMND. Michael Baker will prepare a draft Final ISIMND for City review and approval. Michael Baker will respond to City comments on the draft final document. The final document will include a purpose subsection, reference the review process, comments letters received, responses to comments, and any required edits/updates to the Public Review document. Also included within this task is the Mitigation Monitoring and Reporting Program (MMRP) in accordance with Public Resources Code Section 21081.6 (AB 3180). Fifteen copies (15), one (1) camera-ready original, and an electronic file of the Final IS/MND will be provided to the City. Michael Baker will provide the document to each agency/interested party who submitted a comment letter during the 30-day public review period. Due to the unpredictable nature of potential comment letters received during the public review period, this task is limited to a maximum of twelve (12) hours for Responses to Comments. Additional effort necessary for the Responses to Comments process (due to a high volume of comment letters, complex issues raised in comment letters, etc.) would be performed on a time and materials basis. Upon adoption of the IS/MND by the City, Michael Baker will prepare a Notice of Determination (NOD) and will file the notices at the County Clerk's Office. 8.6 Coordination and Meetings. Michael Baker will provide project oversight, quality assurance, and quality control. This will include consultation and coordination of the project and the environmental review for compliance with CEQA requirements and consultation with State and local agencies regarding the environmental documents. Michael Baker will provide management services to implement the work program and coordinate the effort with City staff. This task also covers costs necessary to administer the contract for this effort. Michael Baker will attend up to one (1) staff -level meeting and two (2) Technical Approach/Work Plan I Page 22 ofessional Engiiniariny & Design Senrk.es f4 public hearings for the project. Should the City determine that additional meetings are necessary, services will be provided under a separate scope of work on a time and materials basis. Deliverables: Five (5) copies of the Administrative Draft Initial Study with Technical Appendices on CD; Twenty-five (25) copies of the Public Review IS/MND with Technical Appendices on CD; and Fifteen (15) copies of the Final IS/MND. Task 9 — ROW Acquisition, Feasibility and Cost Estimate TJC will review the preferred alignment and will provide feasibility and costs to acquire the ROW necessary for completion of the storm drain project. TJC will meet with the Team and assist in the identification of locations for potential retention basins and necessary access rights to same. TJC will assume two Team/project meetings and approximately 10 hours of field research for site identification. TJC will research title and ownership data of identified sites and access rights. TJC will also research and estimate ROW and ancillary costs associated with the acquisition of the alternative retention basin sites and attendant access rights. It is assumed that a maximum of three alternative sites will be analyzed. A ROW cost analysis will be written and submitted for each alternative. Project Schedule The Michael Baker Team will compile existing data, complete technical studies, and develop and evaluate alternative designs and identify a recommended alignment and configuration for the Line 4 Storm Drain System improvements. The following schedule is based upon our understanding of the scope of work. We believe this schedule is feasible within the usual constraints experienced on similar projects. The project schedule by task and sub -task item is included on the following page. QUALITY, BUDGET, AND SCHEDULE CONTROL METHODS Project Management and Control Our experience has allowed us to establish a project management/delivery plan that Michael Baker's internal controls can be organized and executed efficiently, ensuring smooth operational control focus on providing a quality throughout the project. Project Manager (PM)John McCarthy will be responsible for Project with every submittal, monthly project reporting, scheduling, organization of meetings and preparation of meeting minutes, and all routine project coordination. As an integral part of project management, John will be responsible for the implementation, tracking, and maintenance of the project scope and costs, schedule, and QA/QC. Scope/Cost Controls John will monitor design contract costs against the established baseline fee. He will employ the Work Breakdown Structure (WBS) and Earned Value Management (EVM) systems to control consultant contract costs. Each task and sub -task in the WBS will have its own budget. All tasks will be included in one EVM report, which will be the basis for invoicing. John will monitor progress on the EVM against the percent budget spent. Technical Approach/Work Plan I Page 23 EXHIBIT "B" SCHEDULE OF SERVICES t i egtM. .am - A-- P rofessionalnal Engineering & Design Servkes for Line 4 Drainage Pro". No. 522-16 L Schedule Control John will develop and maintain a critical path method schedule for each project awarded to Michael Baker. He will also organize and provide the staffing and technical resources required to meet the schedule. Job progress is monitored with establishment and monitoring of milestone dates, and continually updating the schedule throughout project and briefing the City monthly, at a minimum. Quality Control Brad Losey, QA/QC Manager will ensure an auditable and back checked process is in place to comply with project standards. John will work with Brad and the City's PM to develop a Project Specific Quality Management Plan (PSQMP) for all deliverables developed by our Team. This plan will define specific criteria, processes, and roles/responsibilities of all project Team members. SCHEDULE 10 jTask Name I 1 ]lPHASE 1: PRELIMINARY DESIGN 1 z 1 Task 1- Project Meetings and Coordination 7 I 1 1 Project Notice to Proceed / Kick oft Meeting 12 Project Meetings and Coordination i s i Task 2 - Project Research and Data Collection e Collect and Review Data Task 3-Survey and Mapping ie 3 1 Survey ControllRight-of-Nay Mapping s i 3 2 Topogrephldt Survey Base Map 10 3 3 Unity Base Map 11 Task 4 - Hydrology and Hydraulic Studies tz Hydrology Analysis 13 I Hydraulic Modeling 14 Tasks 5, 6, and 7 - Atterantrves and Preliminary Design tS I 5 Feasibility Study 1e 6 Draft Preliminary Design Report 17 I Design Review Meeting lie City Review to Final Preliminary Design ReporURecommended AR (F 7 Preliminary Improvernont Plans f DistrIMCity Review $ Task 6 - Envlronmental Documentoon b 7 Prgect sort Up T4 Technical Studies/Supporting Documentation D Adtrinstrative Draft IS/MND 6 Agency Review x 30-0ay Public Review 21 Final IS/MND and Agony Review Task 9 - Right -of -Way Acquisition and Cost Estimates ClienTask Dirts, on 0` Palm DMM Dan Mon l/7n a h"evixio # L-- — —�T Project Summary Schedule Palm Desert Line 4 Duration; Stan Feist, av 1 I June 1 I .IY 1 I AATIt 1 NptamWr IOelaOr 1 IOY�mO�r �cwnhM ill ii�l �! kttq 7n nn77g11-6L+llu2abn llsrnlloAiu�jl kill ICldt yaj y1 145 days Mon N16116 Fr11212H6 145 days Mon 51IN16 Fri 12/2116� 0 days Mon 5118116 Mon 5H6/18 Slfe 29 wks Mon 5116/18 Fri 12018 30 days Mon 5M W16 FM W24116 6 wks Mon 5116/16 Fri 824118 30 days Mon 5123116 Fri 711116, 2 As Mon Fri 8/3/16� h a wks &16 B/& Mon 8/16 Fri 7/1/161 4 wks Mon 816116 Fri 7/1/11% 45 days Mon 5123116 Fri 7/22/1Is 4 wits Mon 5123/18 Fri 8/17/1d 6 wks Mon 15113/16 Fri 722115 m� 65 days Mon 714116 Fri 900116 4 wks Mon 714/16 Fn 7rAVM6 2 wks Mon 7/18/18 Fri 7/29/16 1wk Mon 811/1a Fri 815M6 3 wks Mon 8/1/16 Fri 8/1&18. 4 wks Mon 822/18 Fri8/18M8 4 wks Mon 8122/18 Fri 9/1611tf 2 wks Mon 9119116 Fri 9/3W & I 1: 110 days Mon 79116 Fri 1212H6, 2 wks Mon 7/4/16 Fn 7115/18: Its 10 wks Mon 7/18/18 Fri 923118 1 6 wks Mon WINII6 Fri 10/7116 30 edays Fn 10R/16 Sun 11/8/16 4 wks Mon 11/7/16 Fn 12/2/16 3 wks Mon 7111116 Fri 7IM6. VmMk Summoy • • Sul- vullant Ylilm r•••- .... �l1 City Review OtMr 1lgonty Revkw Technical Approach/Work Plan I Page 24 EXHIBIT "C" COMPENSATION ff c A 3 _ F r IF ' L ti w : o p p ^ IS a1. G M p o g---� S A _ C p e P ^ Gn g. as z =s YQ ti G �T_ a nA-s - r CCDD lam) c n a d CD p CD CD CD �. cn Cn = CD = Ca si N � O N N CD d O CS S = C_ u d = Cn Q. CD A 01 CL Cv `O v n cn CD CCDD v cn o O O O CD °r O C- a O O = cn cn O O CD _ n CD O CD cr (n cD O C _ CD w n O C Cn n O cn C') O _ 0 O CD C7 c� (U CD W Cv _ Q O C_ n CD cn CD 3 O Q CD (n C N O 3 c�D �J L O:s1a;-