HomeMy WebLinkAboutC34320 - Change Order 1 - Notice of Completion - Highway 111 Right Turn to Westbound Fred Waring Drive 659-14Contract No. C34320 CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: APPROVE CHANGE ORDER NO. 1 AND REQUEST ACCEPTANCE OF WORK FOR CONTRACT NO. C34320 WITH GRANITE CONSTRUCTION COMPANY FOR THE HIGHWAY 111 RIGHT TURN TO WESTBOUND FRED WARING DRIVE (PROJECT NO. 659-14) SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works CONTRACTOR: Granite Construction Company 38000 Monroe Street, Indio CA, 92203 DATE: September 24, 2015 CONTENTS: Change Order No. 1 Notice of Completion Vicinity Map Recommendation By Minute Motion: 1. Approve Change Order No. 1 to Contract No. C34320 in the amount of $10,400 for the Highway 111 Right Turn to Westbound Fred Waring Drive Project; 2. Authorize the transfer of $10,400 from contingency to base; 3. Authorize the Mayor to execute said Change Order No. 1; and 4. Accept the work as complete and authorize the City Clerk to file a Notice of Completion for Contract No. C34320. Background In September 2011, the City of Palm Desert acquired right-of-way from N and D Restaurants, Inc., the owner of the property at the Red Lobster development. The additional right-of-way was required to construct a dedicated right turn onto westbound Fred Waring Drive from Highway 111 to mitigate traffic congestion. In addition to the Staff Report Approve Change Order No Page 2 of 2 September 24, 2015 1 and NOC for Contract C34320 work at the Highway 111 and Fred Waring Drive intersection, the project included sidewalk and ADA compliant driveways at the MOR Furniture store. On June 11, 2015, City Council awarded Contract No. C34320 in the amount of $404,000 to Granite Construction Company of Indio, California, for the Highway 111 Right Turn to Westbound Fred Waring Drive Project. During construction of the project, unsuitable material was discovered and had to be removed and replaced with aggregate base. The contractor also made minor adjustments during construction including adding additional traffic loops that were outside of the original scope. The amount associated with the additional work is $10,400 and is reflected on Change Order No. 1. The amount represents 2.57 percent of the original contract amount and is well within the contingency already approved by Council. Staff has inspected the work performed by the contractor and has found said work to be complete and in accordance with the contract requirements. Fiscal Analysis The initial contract amount was $404,000, and Change Order No. 1 will increase the contract amount to $414,400. There is no fiscal impact beyond the cost of the project. Prepared By: Depart9AJH�ad: /Oel Montalvo, P.E., Senior Engineer Paul S. Gibson, Director of Finance al: n M. Wohlmuth, City Manager Mark qref nwood, P.E., Direct r c1f Public Works G IPub WorkslStaH Reports120151September 24110 NOC and C01 Rt Turn 659-141SR NOC Approve C0#1 HWY 111 Fred Waring Right Turn 659-14 docx CITY OF PALM DESERT CONTRACT CHANGE ORDER Contract Purpose Highway 111 Right Turn to Fred Waring Consultant's Name Granite Construction Company Address: 38000 Monroe Street Indio, CA 92203 Contract # / P.O. # Change Order No. Contingency: Account No. Project No. Vendor No. C34320 P111991 1 YES NO 2134383-4400100 659-14 V0001010 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans, Specifications, and Directives dated Attached In Contract Price In Contract Price Unanticipated construction issues such as removal of unsuitable material, 10,400.00 additional traffic loops, removal of concrete foundation, additional irrigation sleeves and lines at MOR Fumiture. TOTALS: - 10, 400.00 NET CHANGE IN CONTRACT PRICE: 10,400.00 JUSTIFICATION: Additional cost due to unanticipated asbestos removal and abatement. TOTAL BUDGET FOR PROJECT: + 414,400.0000NTINGENCY: Less: Expend. & Encumb. To Date: - 404,000.00 Amount Approved by Council: + 40,400.00 Less: This Change Order Amount: - 10,400.00 Less: Prior Change Order(s): - - BALANCE OF BUDGET Less: This Change Order: - 10 400.00 REMAINING FOR PROJECT: - Balance Remaining of Contingency: 30,000.00 The amount of the Contract will be Increased by the Sum of: Ten Thousand Four Hundred and 00/100 Dollars ($10,400.00). See reverse Contract C27690C Change Order No. 1 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension 0 Days. Revised Contract Total $414,400.00 The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONTRACTOR Date Accepted CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR SUSAN MARIE WEBER, MAYOR Date Approved NOTE: No payments will be made prior to City Manager and Council approval CITY MANAGER Date Approved See reverse ... To be recorded with the Riverside County Recorder within 10 days after completion and acceptance by the City Council. NO RECORDING FEE PER SECTION 6103 OF THE GOVERNMENT CODE. When recorded, return to: Office of the City Clerk City of Palm Desert 73-510 Fred Waring Drive Palm Desert, CA 92260 NOTICE OF COMPLETION (Cal. Civ. Code § 3093 — Public Works) NOTICE IS HEREBY GIVEN: 1. That the interest or estate stated in paragraph 3 herein in the real property herein described is SOLELY OWNED by the CITY OF PALM DESERT, A MUNICIPAL CORPORATION, a political subdivision of the State of California, and whose address is 73-510 FRED WARING DRIVE, PALM DESERT, CALIFORNIA, 92260. 2. That the full name and address of the owner of said interest or estate is set forth in the preceding paragraph. 3. That the nature of the title of the stated owner, as set forth in paragraph 1, is IN FEE 4. That on the 24th day of September, 2015, a work of improvement described as the Highway 111 Right Turn to Westbound Fred Waring Drive Project, Project No. 659-14, Contract No. C34320 on the real property herein described was completed. 5. That the name of the original contractor, if any, for said work of improvement was: Granite Construction Company, 38000 Monroe Street, Indio, California, 92203. 6. That the real property herein referred to is situated in the City of Palm Desert, County of Riverside, State of California, and is described as being within the City Right of Way adjacent to 72-291 and 72-115 Highway 111. CITY OF PALM DESERT Dated: 9/24/2015 0 Susan iviane vveoer, mayor STATE OF CALIFORNIA } } ss COUNTY OF RIVERSIDE } I hereby certify that I am the City Clerk of the governing board of the CITY OF PALM DESERT, CALIFORNIA, the political subdivision which executed the foregoing Notice and on whose behalf I make this verification: That I have read said Notice, know its contents, and that the same is true. I certify under penalty of perjury that the foregoing is true and correct. Executed at Palm Desert, California, on this day of 20 RACHELLE D. KLASSEN, CITY CLERK Rev. Oct 02