HomeMy WebLinkAbout23C DSRT SURF powerpointDSRT SURF
City Council
January 27, 2022
VICINITY
Cook Street
BACKGROUND
Amended DSRT SURF Project (Specific Plan, Precise Plan, Tentative Tract Map, DDA, and addendum to the EIR):
•Architectural Review Commission –Recommendation of approval with conditions on April 27, 2021
1 Public comment received expressing concerns mainly with water assessment & consumption
•Planning Commission –Recommendation of approval to the City Council on December 21, 2021
1 Public comment received in support at the public hearing
November 19, 2019, City Council approved the following:
•DSRT SURF Specific Plan (SP 18-0002)
•Precise Plan (PP 18-0009) –Planning Area 1 only
•Tentative Tract Map No. 36379
•Disposition and Development Agreement (DDA)
•Certified the Environmental Impact Report (EIR) & adopted Mitigation Measures
DSRT Surf
(Project Comparison)
Scope of Development Current Entitlement Amended Application Delta
Surf Lagoon 5.5 Acres, Wave Garden 5.5 Acres, Wave Garden No Change
Surf Center 31,800 sq. ft. Surf Center and Amenities
8,757 sq. ft.
Surf Center and Clubhouse
(Amenities have been relocated to the Hotel
and 15,674 sq. ft. Hotel deck)
-7,369 sq. ft.
Hotel
130 (min) Hotel Room Keys 92 (min) Hotel Room Keys -38 keys (Hotel)
70 (min) Villa Keys (units plus lock offs)33 (min) Villa/50 Stacked Condos (plus lock
offs)+13 keys (villas)
Hotel Quality
STR Upper Upscale or Luxury Brand AAA Four Diamond Hotel Increase
Must carry flag of major hotel brand (Marriott,
Hilton, Hyatt)
Independent boutique or major hotel brand
(Marriott, Hilton, Hyatt)No Change
$44,500 (min) FF&E and OS&E if
Boutique/Independent Operator
$46,050 (min) FF&E and OS&E if
Boutique/Independent Operator +$1,550
Hotel Operator: 10 yrs (min) experience at
appropriate quality
Hotel Operator: 10 yrs (min) experience at
appropriate quality if Boutique/Independent
No Change
Multiple restaurants, spa facilities, pool
facilities, group meeting space
Multiple restaurants, spa facilities, pool
facilities, group meeting space No Change
Villas 35 –88 units 83 total units: 33 Villas, 50 Stacked condos,
private club house and amenities -5 units
Parking
86 suspended deck surface stalls for Surf
Center and DW overflow
Parking Structure -Surf Center & DW
Overflow: 151 stalls
Hotel parking per code: 130 stalls Hotel: 30 on-site stalls / 62 off-site (92)
160 underground stalls for Surf Center and
DW overflow
Surface Parking -Surf Center and DW
overflow:
96 on-site surface stalls
288 surface stalls off-site (mitigation
requirement)
226 surface stalls off-site (mitigation
requirement)
Total Parking: 464 stalls Total Parking: 565 stalls (473 public)Totals: '+101
SPECIFIC PLAN
AMENDMENT
NO. 1
(Land Uses, Development Standards,
and Design Guidelines)
Land Uses
Development Standards
Design Guidelines
•“Desert Mid-Century Modern”theme architecture, drought tolerant landscape,
lighting, and signage remain unchanged.
•No Major Land Use Changes
Land Use Max/Min Allowed
Surf Lagoon Max 6 acres
Surf Center Max 35,000 SF
Hotel(s) Max 350 rooms
Villas 15 units per acre/88 villas max.
Villa Clubhouse Max 3,125 SF
Maintenance and Equipment Buildings Max 15,000 SF
Landscaping/OS/Pool /Recreational Minimum 20% Planning Area
•Proposed Changes:
Development Standards 2019 2021/2022
Building Height 50 feet/ 4 Stories 50 feet + 10 feet additional for parapets, towers, &
similar elements
50 feet + 15 feet additional for roof stairs & elevators
Setbacks for Stacked Flats None New housing type introduced
Indoor/Outdoor Music
Events:
Friday through
Sunday
7 days a week
No. of Surfers (maximum)75 occupants 70 occupants
PRECISE PLAN
Land Use Description 2021/2022
Development Intensity
Surf Lagoon
•5.5-acre surf lagoon
•Control/Lifeguard Tower (429 square feet)
•Beach area, boardwalk, and support facilities.
Site Amenities
•Surf Center (7,263 square feet)
•Clubhouse (approximately 1,494 square feet)
•Kids Play area
•Pickle Ball Court/Crane Pad
•Pump Track
•Pools/Spas
Hotel
One (1) Hotel operator
•92 rooms
•2,217 SF Restaurant
•955 SF Bar
•885 SF Spa
•920 SF Fitness Center
•1,229 SF Flex Space
•2nd Level Amenity Deck
Residential
83 Residential units with two (2) housing types
•50 stacked flats
•33 villas 2019
Building Architecture-Hotel
North Elevation
Hotel –1st Floor Plan
Building Architecture-Surf Center
Height: 26 feet
Building Architecture-Lagoon Tower
Height: 26 feet & 7 inches
Building Architecture-Maintenance
Height: 24 feet
Building Architecture-Stacked Flats
Height: 37 feet & 9 inches
Building Architecture-Villas
Height: 26 feet & 6 inches to 33 feet & 6 inches
Building Architecture-Club House
Height: 24 feet & 6 inches
Landscape
Trees
Shrubs
TENTATIVE TRACT MAP
Parcel Size Use
Parcel 1 9.27 acres Surf Lagoon
Parcel 2 2.54 acres Hotel/Surf Center
Parcel 3 2.95 acres Stack Flats
Parcel 4 0.74 acres Villas
Parcel 5 2.19 acres Stack Flats
Total 17.69 acres
CEQA
Addendum to EIR –reviewed changes to the Specific Plan and analyzed Proposed Plan.The addendum compared the currently proposed project and the impacts in
the EIR was found to have less than significant impacts.
•Water Supply Assessment (WSA):
2019 WSA,gross water demand of 165.21 acre-feet per year (AFY)and net water demand of 58.46 AFY with the turf removal and replacement with desert
landscaping.
2021 WSA,gross water demand of 114 .35 acre-feet per year (AFY)and net water demand of 7.6 AFY after accounting for the turf removal and
replacement with desert landscaping.
In perspective, the “7.6 AFY is equivalent to the annual water demands of 58 residential units.”
•Conversion of Desert Willow (Turf Reduction Program):
Removal -One (1)million square feet of turf within the Desert Willow Golf Courses
Replacement with drought-tolerant planting materials and low water usage irrigation systems
Surf Lagoon Water Demand
Evaporation Rate
(annual)
DSRT SURF (WSA)16.48M gallons
CVWD (Standard Factor)8.28M gallons
Disposition and Development
Agreement (DDA)
Approved in 2019
Revised and Restated in 2022 to address project changes
Land Sale
Disposition of 3-ac of City land (DW parking area)
Disposition of 14.6-CA of SARDA land (Parcel B of LRPMP)
Acquisition of Public Improvements (use of Bonds Funds)
$20M for 473 public parking space of Desert Willow Golf Resort
Transient Occupancy Tax (TOT) rebate
$16.1M over 20-years
Schedule of Performance
Disposition and Development
Agreement (DDA)
Acquisition Agreement (Attachment No. 7 of DDA)
$20M for 473 public parking space of Desert Willow Golf Resort
151 structure parking spaces
96 surface parking spaces
226 off-site public parking spaces
Former RDA Bond Proceeds from Project Area 2 and 3
Payment is contingent on
City Inspections and acceptance of improvements
Project Milestones
City “Look Back” at construction completion
Disposition and Development
Agreement (DDA)
Payment of the $20M is provided in Exhibit BDrawPublic Parking Surf Lagoon and Center Hotel RESIDENTIAL UNITS
1st-$5M 30% construction cost of podium Parking
Structure
100% rough grading complete Commence foundation upon fully
approved and issued building
permits for the entire Hotel
2nd-$5M 60% of construction cost of podium Parking
Structure
100% Foundations Complete Completion of 60% of Hotel Parking
3rd-up to $5M 100% completion of all Public Parking and
compliance with the Acquisition Agreement
100% of Surf Lagoon floor
completed and surf equipment on
site
Completion of rough framing
construction of the Hotel
4th-up to $3M 100% of all other public infrastructure and
compliance with the Acquisition Agreement
100% complete certificate of
occupancy for Surf Lagoon and
Center approved
100% complete certificate of
occupancy for Hotel approved
5th-up to $2M 4th Payment has been made, and City “look-back”
approval of actual Project Costs in Section 4.5(d)
and in compliance with the Acquisition Agreement
100% complete
Certificate of
Occupancy for
Residential Units
Disposition and Development
Agreement (DDA)
Transient Occupancy Tax (TOT) Reimbursement (Attachment No. 8 of DDA)
$16.1M over 20-years
40% of TOT Reimbursement for Hotel
60% of TOT Reimbursement for Villas
Requires AAA 4 Diamond
If standard lapse reimbursement falls to 20%
After 9-months reimbursement falls to 0.0%
Amount was determined from review of project pro forma
Shows a feasibility gap of $24.7M for hotel and villa development
Over 20-years City expected to receive:
$39M in TOT
$2.2M in Sales Tax
$1.3M in Property Tax
42.5M in City Revenues
City expects $26.5M over 20-years after TOT Reimbursement
Disposition and Development
Agreement (DDA)
Schedule of Performance
Submit Construction Drawings –March 31, 2022
Rough Grading Plan Approval –April 30, 2022
Submit construction contracts –August 31, 2022
Close Escrow –October 31, 2022
Construction completion estimated in 24-months
Recommendation
Waive further reading and adopt the following City Council Resolution in support of the DSRT SURF Project:
Adopt City Council Resolution No.approving Case Nos.Amendment No.1 to SP 18-0002,PP 18-0009,TTM 37639,and an addendum to the
EIR for the DSRT SURF Project,subject to the conditions of approval.
By Minute Motion:
Approval of a Revised and Restated Disposition and Development Agreement (DDA)between the City of Palm Desert and Desert Wave
Ventures,LLC.
Approval of a Transient Occupancy Tax (TOT)Agreement as-to-form with Desert Wave Ventures,LLC,in an amount not to exceed $16.1
million for the operation of a 92-room AAA four-diamond hotel located on Parcel B within the Desert Willow Golf Resort.
Authorize the Mayor to execute said Agreements.
Authorize the City Manager to make non-substantive changes to the DDA and TOT Agreement as needed prior to execution by the Mayor.
Authorize the City Manager to draft,negotiate,and execute other supporting agreements that may be required by the DDA,including an
Acquisition Agreement as to form and the attached City Cost Reimbursement Agreement as to form.
Authorize the City Manager to execute said agreements.
Appropriate $20 million to Fund 451 for costs associated with the public improvements at identified sites of the Project.These funds are
reimbursable from the associated residual bond proceeds and controlled by the attached Acquisition Agreement as-to-form.
Disposition and Development
Agreement (DDA)