HomeMy WebLinkAboutRES 2022-044RESOLUTION NO. 2022-44
' A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
PALM DESERT, CALIFORNIA, ADOPTING A LIST OF
PROJECTS FOR FISCAL YEAR 2022-23 FUNDED BY SB 1:
THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the
Governor in April, 2017, in order to address the significant multi -modal transportation funding
shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure
that the residents of our City are aware of the projects proposed for funding in our community,
and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive
fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created
by SB 1, which must include a description and the location of each proposed project, a
proposed schedule for the project's completion, and the estimated useful life of the
improvement; and
WHEREAS, the City, will receive an estimated $1,228,450 in RMRA funding in Fiscal
Year 2022-23 from SB 1; and
' WHEREAS, this is the sixth year in which the City is receiving SB 1 funding which may
enable the City to continue essential road maintenance and rehabilitation projects, safety
improvements, and increasing access and mobility options for the traveling public that would
not have otherwise been possible without SB 1; and
WHEREAS, the City used a Pavement Management System to develop the SB 1
project list to ensure revenues are being used on the most high -priority and cost-effective
projects that also meet the communities priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate
streets/roads throughout the City this year and similar projects into the future; and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs
Assessment found that the City's streets and roads are in a "good" condition and this revenue
will help us increase the overall quality of our road system and over the next decade will bring
our streets and roads into a "excellent" condition: and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting -edge technology, materials and practices, will have
significant positive co -benefits statewide.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City
' Council of the City of Palm Desert, State of California, as follows:
1. The foregoing recitals are true and correct.
RESOLUTION NO. 2022-44
2. The following previously proposed and adopted projects may utilize Fiscal Year 2022- ,
23 Road Maintenance and Rehabilitation Account revenues in their delivery. With the
relisting of these projects in the adopted fiscal year resolution, the City is reaffirming
the public and the State our intent to fund these projects with Road Maintenance and
Rehabilitation Account revenues:
Citvwide Pavement Condition Evaluation,
• Location: Citywide
• Description: Contract with a consultant to perform a pavement condition survey,
assessment, and inventory services on the entire City street network.
• Estimated Useful Life: The information in the report will be accurate for a period
of three to five years but will be updated regularly to maintain accurate data.
• Anticipated Completion Date: June 2023
Cook Street Resurfacina Proiect - Phase 2,
• Location: Cook Street from Frank Sinatra Drive to Merle Drive.
• Description: The asphalt will be milled down two inches and capped with
rubberized asphalt concrete.
• Estimated Useful Life: 25 years
• Anticipated Completion Date: September 2022
Portola Avenue Repavinq Proiect
• Location: Portola Avenue between Fred Waring and Hwy 111
• Description: A survey will be conducted to establish the limits of repair. The '
street will be regraded to reduce crossfall, the asphalt will be milled down, cross
gutters will be replaced at the correct grade, and the street will be capped with
warm mix asphalt.
• Estimated useful life: 25 years
• Anticipated Completion Date: May 2023
PASSED, APPROVED, AND ADOPTED on this 26th day of May 2022 by the following
vote, to wit'.
AYES: JONATHAN, KELLY, NESTANDE, QUINTANILLA, and HARNIK
NOES: NONE
ABSENT: NONE
ABSTAIN: NONE
3 N C. HARNIK, MAYOR
ATT T:
-�31 1?D2v
A�TNY J. M CIT RK
CITY OF PALM ES CALIFORNIA