HomeMy WebLinkAboutApp & Checklist PALM DESERT PERMIT CENTER
Expedited Solar Photovoltaic Permitting for One-and Two-Family Dwellings
This information bulletin is published to guide applicants through a streamlined permitting process
for roof-top solar photovoltaic (PV) projects 30kW in size or smaller. This bulletin provides
information about submittal requirements for plan review, required fees, inspections, and an
eligibility checklist.
1. Submittal Requirements
- Completed permit application form. This permit application form can be downloaded at:
https://www.cityofpaI mdesert.org/ou r-city/depa rtments/palm-desert-permit-center/building-safety-permits
- Demonstrate compliance with the eligibility checklist for expedited permitting. The criteria
is attached to this informational bulletin or can be downloaded at:
https://www.cityofpalmdesert.org/our-city/depa rtments/palm-desert-permit-center/building-safety-perm its/so lar-
information
- Provide a standardized or simplified photovoltaic plan that demonstrates:
✓ Title or Cover Sheet noting the 2019 California Electrical Code.
✓ Site and Roof Plan showing roof layout, PV panels and the following fire safety items:
Approximate location of roof access point, location of code-compliant access
pathways, and the locations of all required labels and markings.
✓ A simplified Electrical Plan:
1. Locations of main service or utility disconnect
2. Total number of modules, number of modules per string and the total number of
strings
3. Make and model of inverter(s) and/or combiner box if used
4. Single-line diagram of system
5. Specify grounding/bonding, conductor type and size, conduit type and size and
number of conductors in each section of conduit
- Provide a simplified structural design:
Provide structural drawings and calculations stamped and signed by a California-licensed
architect, civil or structural engineer, electrical engineer or licensed contractor along with
the following information.
1. The type of roof covering and the number of roof coverings installed
2. Type of roof framing, size of members and spacing
3. Weight of panels, support locations and method of attachment
4. Framing plan and details for any work necessary to strengthen the existing roof
structure
5. Site-specific structural calculations
6. Where an approved racking system is used, provide documentation showing
manufacturer of the rack system, maximum allowable weight the system can
support, attachment method to the roof or ground and product evaluation
information or structural design for the rack system
Updated June 2021
Eligibility Checklist
Expedited Solar Photovoltaic Permitting for
One- and Two-family Dwellings
These criteria are intended for expedited solar permitting process. If any items are UNCHECKED, revise
design to fit within Eligibility Checklist, otherwise permit application must go through standard process
which is (10 Business Day initial review/7 Business Day Follow-up Review)
1. General Requirements
X The photovoltaic system size is 30kW AC CEC rating or less.
The solar array is roof-mounted on a one-or two-family dwelling unit or permitted accessory structure.
X The photovoltaic system is utility interactive.
X Permit application and declaration is completed and attached.
2. Planning Department Requirements
X Existing MPU Amps Doubling,e.g. 100 to 200 OR 125 to 225. PLANNING WILL NEED TO REVIEW.
X Maximum height of"tilted"panels shall not exceed eighteen (18)inches.
X All wires shall be strapped to the modules/racking system. No loose or hanging wires are permitted.
The racking system shall match the module frame and shall be a color compatible with the architectural
character of the home or building.
X Modules shall be flush with one another and gaps between panels shall be minimized.
X Screening of panels is not required.Any screening material proposed shall be compatible with the
architectural character of the home of building.
3. Electrical Requirements
X No more than four photovoltaic module strings are connected to each Maximum Power Point Tracking
(MPPT)input where source circuit fusing is included in the inverter:
1) No more than two strings per MPPT input where source circuit fusing is not included
2) Fuses(if needed)are rated to the series fuse rating of the PV module
3) No more than one non-inverter-integrated DC combiner is utilized per inverter
X For central inverter systems: No more than two inverters are utilized.
X The PV system is connected to the load side of the utility distribution equipment.
A Solar PV Standard Plan and supporting documentation is completed and attached.
4. Structural Requirements
A completed Structural Criteria and supporting documentation is attached Wind and Seismic(if required).
5. Fire Safety Requirements
X Clear access pathways provided.
X Fire classification photovoltaic system is provided.
X All required marking and labels are provided.
A diagram of the roof layout of electrical panels, modules, clear access pathways and approximate locations
of electrical disconnecting means and roof access points are completed and attached.
I understand and affirm that the above information regarding the solar photovoltaic is true and accurate. If during the inspection
process any deviation in this scope will result in stop work and full plan review. In the event a project requires supplemental plan
reviews,a plan review fee of$168.00 per hour(with one-half hour minimum)will be collected from the applicant.
Applicant Signature: �� G�eurt.� Date:05/04/2023
Project Address:45720 Abronia Trail,Palm D ert.Califo nia 92260
Updated June 2021
CITY OF PALM DESERT
DEPARTMENT OF DEVELOPMENT SERVICES
Building &Safety Division •73510 Fred Waring Drive, Palm Desert, California 92260
Phone(760) 776-6435• Fax(760)776-6392• permitcenter@cityofpaImdesert.org
BUILDING PERMIT APPLICATION
Project Address: 45720 Abronia Trail, Palm Desert, California 92260
Total Value of Work$: 8117.25
Project Description (Describe the Specific Nature of Approval Requested):
REROOF CRRC: HVAC SEER: WATER HEATER ENERGY:
OTHER:To install a 5.925kW PV array roof mounted 15 panel system
Contractor Business Name:
Skyline Smart Energy Phone: 8552561507
Mailing Address: 10642 Downey Ave Unit 205 Fax:
City: Downey State: CA Zip: 90241 Email: capermitting@skylinesmartenergy.com
License No. 1028741
Property Owner Name:
Daniel Olfert Phone: 8552561507
Mailing Address: 45720 Abronia Trail Fax:
City: Palm Desert, State: CA Zip: 92260 Email: janellenixoncasting@gmail.com
Architect/Designer Name:
Phone:
Mailing Address: Fax:
City: State: Zip: Email:
License No.
Engineer Name:
Phone:
Mailing Address: Fax:
City: State: Zip: Email:
License No.
Applicant Name:
Phone:
Mailing Address: Fax:
City: State: Zip: Email:
Applicant/Representative Signature: By signing this application, I certify that the information provided is accurate. I
understand that the City might not approve what I am applying for and/or might require conditions of approval.
Print Name: Amanda Young Signature: .4t-rt.G72� G,�eu41q_ Date: 05/04/2023
*THE REVERSE SIDE MUST BE COMPLETED FOR RESIDENTIAL REMODELS AND TENANT IMPROVEMENTS
CITY OF PALM DESERT
BUILDING PERMIT APPLICATION
Structure Information:
Roof Type (circle one): Occupancy Group (circle one):
Shingles❑ Built Up❑ Concrete❑ Foam❑ Metal❑ R2❑ R3❑ A.2❑ U❑ R3-U❑ A2❑
Tile type:Comp Shingle B❑ M❑ MIXED
Construction Type (circle one): Fire Sprinklers: YES ❑ NO 0
IA El IB❑IIA❑ IIB❑ IIIA❑ IIIB❑ IV HT❑ VA❑VB❑
All applicable information must be completed below
Commercial Remodel Sq. Ft. Addition Sq. Ft. Residential Remodel Sq. Ft. Addition Sq. Ft.
Assembly Area Accessory Cover
Office
Garage Area
Retail
Living Area
Warehouse/Storage No. of Bedrooms
Total Building
No. of Baths
Accessory Cover No. of Dwelling Units
Multi-family, some Residential, and Commercial Projects plans must be submitted to the Fire Department.
Fire requires one (1) complete set of plans. Please call Fire at(760) 346-1870 for further information.
THE FOLLOWING ITEMS ARE BEING SUBMITTED:
(Please check all that you have provided)
❑2 COMPLETE SETS OF PLANS, including the following supporting documents if applicable:
❑Structural Calculations ❑Title 24—Energy Calculations
❑Truss Calculations ❑Soils report
❑CF-R Forms ❑Manufacturer's Specifications
❑ Electrical El Mechanical ❑Plumbing ❑HOA Letter of Approval(required by Planning Dept.)
❑Assessor:
Please submit the following for new construction, square footage addition to an existing structure, photovoltaic and
swimming pool permits
✓ Commercial projects-1 title page, 1 site plan, 1 elevation, 1 floor plan
✓ Residential projects-1 site plan, 1 dimensioned floor plan,at least 1 elevation plan
FEES
Plan Check Hourly: $168.00 (Plan Review Fees may be adjusted after Plan Review)
Inspection Hourly: $159.00
Archive Fee:
8.5xl 1 up to 11x17 $.07 per page
Plans $.80 per page
Do not base your permit fees off of the fees stated above. For Reference Only.
OFFICE USE ONLY
Permit No. Plan Location:
APN: Received By: