INTEROFFICE MEMORANDUM
TO: Honorable Mayor and City Council
FROM: Spencer Knight, Landscape Manager
SUBJECT: INFORMATIONAL ITEM - - COMMUNITY GARDEN COST ESTIMATE
DATE: 3/23/00
Attached are cost estimates for the Community Garden. These costs reflect the
following changes:
1) The shade structure in the Demonstration Garden. This structure is now a
20' x 20', prefabricated metal structure (see Exhibit A). If the City desires
to upgrade this structure at a future date it can be easily removed and
replaced. It will be on a concrete pad.
2) The character and quantity of site furnishings, and the character of the
individual garden storage buildings was changed, creating a minor cost
decrease.
3) The perimeter block wall was modified from that which was used at City
Hall to a more standard type wall construction (like what was used at the
Coachella Valley Water District well site to the south of the garden area).
This change helped to decrease costs.
Please note that the Attached cost sheets include a standard flush, single stall restroom
facility with sink. The Landscape Committee felt a standard flush type restroom facility
was needed. The additional cost will be less than $20,000.
Schedule of Exhibits:
A) Photo of proposed shade structure for the Demonstration Garden.
B) Plot plan of proposed shade structure for the Demonstration Garden.
C) Preliminary cost estimate for the installation of complete Community Garden.
D) Preliminary cost estimate for installation of Community Garden infrastructure,
grading, and Demonstration Garden Phase only.
E) Preliminary cost estimate for installation of Community Garden — Standard
Garden Phase.
F) Engineer's cost estimate for landscaping all Community Garden areas with a
Desert Willow style plant pallet.
G) Preliminary cost estimate for Community Garden infrastructure, grading, wall,
irrigation system, perimeter landscape, and only the Demonstration Garden.
3/23/00-G:\PubWorks\Sonja De La Fuente\My Documents\STAFF REPORTS\Info Item-Community Garden Cost Estimate.doc-sd
•
Memo: Community Gard ost Estimate
' 3/22/00
Page 2 of 2
Exhibit F provides a comparison cost for a conventional landscape installation in garden
areas with a Desert Willow style plant pallet.
Exhibit G provides an estimate of the costs associated with the infrastructure, grading,
wall, irrigation system and perimeter landscape for all of the Community Gardens and
the interior of only the Demonstration Garden. This exhibit defers from Exhibit D by the
inclusion of all the perimeter block wall, irrigation system, and perimeter landscape.
The garden area located between Guadalupe Avenue and the Coachella Valley Water
District well site is half of the Standard Garden and its individual cost would be
approximately half of the Standard Garden costs (Exhibit E).
The Economy of Scale cost factor found in Exhibits D & E reflects the increase in unit
price resulting from the smaller work volumes occurring in the phase form of installation.
This increase, being hard to estimate by individual unit, is represented by a percentage
figure.
H. SPE CER K IGHT ' I-<EVIEWED YND‘..4ce-4. UR
CITY MANAGER
E WED A NCUR RE IEWED AND CONCUR
ACM/PUBLIC ORKS DIRECTOR FINANCE DIRECTOR
HSK/sd CITY COUNCIL/ACTION:
Attachments APPROVED ✓✓ DENIED
RECEIVED OTHER
*By Minute Motion, conceptually MEETINe, fl TE_ 3.02- - C7
approve the project as proposed AYES.
by staff with direction that NOES:
appropriate reporting on the ABSENT: zYur u&
progress of same is made to the ABSTAIN:
VERIFIED BY: I'LD pp
Council. Original on File with City Ojerk's Office
3/23/00-G:\PubWorks\Sonja De La Fuente\My Documents\STAFF REPORTS\Info Item-Community Garden Cost Estimate.doc-sd
EXHIBIT A IP
• The Apache• Shown with optional
6" x 6" legs and cupola.
•
filih
_ .. } 1-4-101:0- ,
\ `
_ Milk*,. ill ..... . 4°.
aasft_ ape -
„........_
_.....
_,., . ::._......
. , •. p.A....
, . .)„. . .lkorAi
. . . .
... tek • ,.. .4,
.1
•
tt. --"E" .. a 7- 7 i
I
1• r
4
Apache �,,,
Style Tubular .' • '�
"Illit.:4°
Standard Sizes —"- oohs, - _
16' x 16' 3" x 3" legs * `'r -
20' x 20' 3" x 3" legs �_ -
24' x 24' 3" x 3" legs -- •::;..K ..
28' x28' 3" x3" legs
36' x 36' 3" x 5" legs * Hexagon Design * Powder Coated Steel Frame
Optional: 6" x 6" legs * Roof: Aluminum , Galvalume, Wood or Cupola
available on all sizes.
14 I
1999 Page 7
N
0
i
m 40
/ 11:\\*-111 S) 0 4to
207 *. 604
‘)
N \ /TO1R
v,�
r�;1 t lea _ — — a
II
1.-1 /" W
incoks-
1 \
\111/ a
1\ fil\%\i\N •
411:: r
•• 4•://r 1 ;.is , t' sl5ii 111
dz
.i.I
PLAN VIEW o .314' DIA. ANCHOR BELTS
`_ a, 12' L.& MINT
DOTTOH OF 'PIB })LOCK I O p V.
W.
O')
f NUTE$ REINFORCE ANDPOUR_ - - CONCRETE ID SATISFY
Liz i
1 , : i l , - LDCAL BUILDING CDDES
t
d , t i ; a SHELTER PRODUCTS
g.
tn..
a ` �' o i . DI . ilF 111NDW1N MFG., 1NC.
Q 1 ( p. o Z o CENTRAL IAA..
o 120' APACHE SHELTER
n -_ t�-tt 1 A-2020
r�, SIDE VIES
H F
.. H
W
• •
PALM DESERT COMMUNITY GARDENS EXHIBIT C
PRELIMINARY COST ESTIMATE
03-21-00
DESCRIPTION QUANTITY UNIT UNIT COST EXTENSION
GRADING
Grading 1 I.s. $20,000.00
$20,000
UTILITIES
Utilities 1 I.s. $25,000.00
$25,000
MOBILIZATION
Mobilization 1 I.s. $3,000.00
$3,000
BUILDING
Shade Structure 1 I.s. $25,000.00
Restroom Faucility(single @ main garden) 1 I.s. $20,000.00
Storage Buildings 4 ea. $1,500.00 $6,000.00
$51,000
PLOTS
Plots 1 I.s. $25,500.00
Path ways 560 c.y. $5.00 $2,800.00
Soil 188 c.y. $15.00 $2,820.00
$31,120
HARDSCAPE
Parking 2800 s.f. $6.50 $18,200.00
Curb 420 I.f. $8.00 $3,360.00
Ornamental wrought iron 790 I.f. $36.00 $28,440.00
Block wall 1500 I.f. $60.00 $90,000.00
Entry Gate side 7 ea. $1,600.00 $11,200.00
Entry Gate main 1 ea. $5,000.00 $5,000.00
$156,200
LANDSCAPE
Trees 24"Box 10 ea. $285.00 $2,850.00
Washingtonia robusta 290 f.t. $40.00 $11,600.00
Shrubs 15 Gal 14 ea. $90.00 $1,260.00
Shrubs 5 Gal 350 ea. $18.50 $6,475.00
Boulders 30 ea. $85.00 $2,550.00
Desert Dust 7125 s.f. $0.75 $5,343.75
$30,079
SITE FURNISHING
Site furnishing 6 ea. $500.00 $3,000.00
Tools I.s. $3,000.00 $3,000.00
$6,000
IRRIGATION
Irrigation 1 I.s. $14,300.00
$14,300
SUBTOTAL $336,698.75
10%CONTINGENCY $33,669.88
TOTAL ESTIMATE* S370,368.63
*FIGURES ARE FOR ESTIMATE PURPOSES ONLY. ACTUAL CONSTRUCTION COST MAY VARY.
• •
PALM DESERT COMMUNITY GARDENS EXHIBIT D
PRELIMINARY COST ESTIMATE BY PHASES
03-21-00
DESCRIPTION QUANTITY UNIT UNIT COST EXTENSION
INFRASTRUCTURE /GRADING
GRADING
Grading 1 I.s. $20,000.00
$20,000
UTILITIES
Utilities 1 I.s. $25,000.00
$25,000
MOBILIZATION
Mobilization 1 I.s. $3,000.00
$3,000
SUBTOTAL INFRASTRUCTURE/GRADING $48,000.00
DEMONSTRATION GARDEN
BUILDING
Restroom Faucility(single @ main garden) 1 I.s. $20,000.00
Storage building 1 ea. $1,500.00 $1,500.00
$21,500
PLOTS
Plots 1 I.s. $7,500.00
Path ways 154 c.y $5.00 $770.00
Soil 62 c.y. $15.00 $930.00
$9,200
HARDSCAPE
Parking 800 s.f. $6.50 $5,200.00
Curb 120 I.f. $8.00 $960.00
Ornamental wrought iron fence 220 I.f. $36.00 $7,920.00
Block wall 162 I.f. $60.00 $9,720.00
Entry Gate side 2 ea. $1,600.00 $3,200.00
$27,000
LANDSCAPE
Trees 24"Box 3 ea. $285.00 $855.00
Washingtonia robusta 80 f.t. $40.00 $3,200.00
Shrubs 15 Gal 4 ea. $90.00 $360.00
Shrubs 5 Gal 90 ea. $18.50 $1,665.00
Boulders 9 ea. $85.00 $765.00
Desert Dust 2053 s.f. $0.75 $1,539.75
$8,385
SITE FURNISHING
Site furnishing 2 ea. $500.00 $1,000.00
$1,000
IRRIGATION
Irrigation 1 I.s. $5,800.00
$5,800
SUBTOTAL DEMONSTRATION GARDEN $120,884.75
20%ECONONMY OF SCALE $24,176.95
10%CONTINGENCY $12,088.48
TOTAL ESTIMATE* $132,973.23
'FIGURES ARE FOR ESTIMATE PURPOSES ONLY. ACTUAL CONSTRUCTION COST MAY VARY.
r
.
• •
.,
PALM DESERT COMMUNITY GARDENS EXHIBIT E
PRELIMINARY COST ESTIMATE BY PHASES
03-21-00
DESCRIPTION QUANTITY UNIT UNIT COST EXTENSION
STANDARD GARDEN*
BUILDING
Storage building 1 ea. $1,500.00 $1,500.00
$1,500
PLOTS
Plots 1 I.s. $7,500.00
Path ways 154 c.y $5.00 $770.00
Soil 62 c.y. $15.00 $930.00
$9,200
HARDSCAPE
Parking 800 s.f. $6.50 $5,200.00
Curb 120 I.f. $8.00 $960.00
Ornamental wrought iron fence 220 I.f. $36.00 $7,920.00
Block wall 162 I.f. $60.00 $9,720.00
Entry Gate side 2 ea. $1,600.00 $3,200.00
$27,000
LANDSCAPE
Trees 24"Box 3 ea. $285.00 $855.00
Washingtonia robusta 80 f.t. $40.00 $3,200.00
Shrubs 15 Gal 4 ea. $90.00 $360.00
Shrubs 5 Gal 90 ea. $18.50 $1,665.00
Boulders 9 ea. $85.00 $765.00
Desert Dust 2053 s.f. $0.75 $1,539.75
$8,385
SITE FURNISHING
Site furnishing 2 ea. $500.00 $1,000.00
$1,000
IRRIGATION
Irrigation 1 I.s. $5,800.00
$5,800
SUBTOTAL DEMONSTRATION GARDEN $52,884.75
20% ECONONMY OF SCALE $10,576.95
10%CONTINGENCY $5,288.48
TOTAL ESTIMATE** $68,750.18
*DOES NOT INCLUDE ANY INFRASTRUCTURE/GRADING(grading,utilities,mobilization)
**FIGURES ARE FOR ESTIMATE PURPOSES ONLY. ACTUAL CONSTRUCTION COST MAY VARY.
• 0 EXHIBIT F
Palm Desert Community Garden
Landscape Cost for Desert Willow Style Landscape
Item Qty. Units Unit Cost Total
Mobilization 27,000 square feet $ 0.30 $ 8,100.00
Clearing & Grubbing 27,000 square feet $ 0.36 $ 9,720.00
Plant Materials 27,000 square feet $ 1.25 $ 33,750.00
Boulders 27,000 square feet $ 0.35 $ 9,450.00
Decomposed Granite 27,000 square feet $ 0.60 $ 16,200.00
Irrigation System 27,000 square feet $ 1.00 $ 27,000.00
Hardscape (cobble) 5,000 square feet $ 7.00 $ 35,000.00
Earthwork 300 cubic yards $ 4.00 $ 1,200.00
Maintenance & Plant Establishment 27,000 square feet $ 0.35 $ 9,450.00
Sub-Total $ 149,870.00
Design Cost 10 % $149,870.00 $ 14,987.00
Project Management 15 % $149,870.00 $ 22,480.50
Contingency 10 % $149,870.00 $ 14,987.00
Sub-Total 35 % $149,870.00 $ 52,454.50
TOTAL $ 202,324.50
S •
PALM DESERT COMMUNITY GARDENS EXHIBIT G
PRELIMINARY COST ESTIMATE
Infrastructure,Grading,Wall,Irrigation System,Perimeter Landscape,
( and Demonstration Garden ONLY
03-21-00
DESCRIPTION QUANTITY UNIT UNIT COST EXTENSION
GRADING
Grading 1 I.s. $20,000.00
$20,000
UTILITIES
Utilities 1 I.s. $25,000.00
$25,000
MOBILIZATION
Mobilization 1 I.s. $3,000.00
$3,000
BUILDING
Shade Structure 1 I.s. $25,000.00
Restroom Faucility(single @ main garden) 1 I.s. $20,000.00
Storage Buildings 1 ea. $1,500.00 $1,500.00
$46,500
PLOTS
Plots 1 I.s. $7,500.00
Path ways 154 c.y. $5.00 $770.00
Soil 62 c.y. $15.00 $930.00
$9,200
HARDSCAPE
Parking 2800 s.f. $6.50 $18,200.00
Curb 420 I.f. $8.00 $3,360.00
Ornamental wrought iron 790 I.f. $36.00 $28,440.00
Block wall 1500 I.f. $60.00 $90,000.00
Entry Gate side 7 ea. $1,600.00 $11,200.00
Entry Gate main 1 ea. $5,000.00 $5,000.00
$156,200
LANDSCAPE
Trees 24"Box 7 ea. $285.00 $1,995.00
Washingtonia robusta 280 f.t. $40.00 $11,200.00
Shrubs 15 Gal 14 ea. $90.00 $1,260.00
Shrubs 5 Gal 350 ea. $18.50 $6,475.00
Boulders 30 ea. $85.00 $2,550.00
Desert Dust 7125 s.f. $0.75 $5,343.75
$28,824
SITE FURNISHING
Site furnishing 1 ea. $500.00 $500.00
Tools I.s. $1,000.00 $3,000.00
$3,500
IRRIGATION
Irrigation 1 I.s. $14,300.00
$14,300
SUBTOTAL $306,523.75
10%CONTINGENCY $30,652.38
TOTAL ESTIMATE` $337,176.13
'FIGURES ARE FOR ESTIMATE PURPOSES ONLY. ACTUAL CONSTRUCTION COST MAY VARY.