1 . APPROVAL OF MINUTES OF PREVIOUS MEETING OF NOVEMBER 22, 1977
2. Case No. : 63C (Continued)
Nature of Project: Racquetball/Health Club
Location: Northwest Corner of Painters Path and Highway 111
Zone: C-1 , S.P.
Applicant: PALM DESERT RACQUETBALL/HEALTH CLUB, INC.
Nature of Approval Sought: Preliminary site, floor, elevations
Action: APPROVED
3. Case No. : 96MF
Nature of Project: 9 Condominium Units
Location: West side of Verba Santa, south of Pitahaya
Zone: PR-6
Applicant: CHARLES ROOT
Nature of Approval Sought: Final construction drawings
Action: APPROVED
4. Case No. : 97MF
Nature of Project: 6 single-family residences
Location: Desert Paradise Tract, on Joshua between 44th & Parkview
Zone: R-1
Applicant: W & R DEVELOPERS
Nature of Approval Sought: Final construction drawings
Action: APPROVED
5. Case No. : 100MF
Nature of Project: Duplex
Location: Northwest corner of Alessandro and Santa Anita
Zone: R-3(4)
Applicant: SANTIAGO FERNANDEZ
Nature of Approval Sought: Final construction drawings
Action: CONTINUED TO DECEMBER 20, 1977
6. Case No. : 88MF
Nature of Project: Duplex
Location: West side of Portola, northerly of Fairway
Zone: R-2, S.P.
Applicant: VICTOR JENNINGS
Nature of Approval Sought: Final construction drawings
Action: CONTINUED TO DECEMBER 20, 1977
Nape
DESIGN REVIEW BOARD DATE : Dec. 6, 1977
CASE NO. : 63C
APPLICANT : PALM DESERT RACQUETBALL/HEALTH CLUB , INC.
LOCATION: Northwest corner of Painters Path & Highway 111
ZONING: C-1 , S.P .
STAFF RECOMMENDATION:
Staff has not received the revised set of plans for this
project since the last meeting. Continuance of the case
is recommended until such time as the revised plans are
received.
•
Nave ,4loof
SPECIAL CONDITIONS
•
CASE NO. 63C •
1 . Construction plans shall be submitted for approval to the City
Fire Marshal prior to issuance of building permits . All con-
ditions shall be made a part of construction and no certificate
of occupancy shall be issued-until completed.
2. Any/all utility service and distribution lines on or abutting
the subject property, shall be placed underground prior to oc-
cupancy clearance.
3. Final construction drawings including a final landscaping, grad-
ing, lighting, amenities trash storage, walking layout , and ir-
rigation plan shall be submitted to the Design Review Board. No
final inspection or occupancy permit shall be given by the Dept .
of Environmental Services to this project until the aforementioned
approved plans and construction shall have been completed.
4. Applicant shall comply with all of the requirements of the related
Case CUP 09-77.
5. Final landscaping plan shall include proposed- improvements for
pedestrians, bicycles and landscaping for area along Highway 111
as required by Condition No. 9 of the Conditional Use Permit
CUP 09-77.
6 . Lower northerly 1/3 of building two feet.
7. Mounding shall be provided around southern area, along Painters
Path with wrapping around the south end and integrate the fire
escape. -
8. Wood treatment shall be natural redwood, minimum 1"x8" with tongue
and groove .
9. A handrail and handicap entrance shall be provided.
10. The service entrance shall be refined.
AGREEMENT
I accept and agree, prior to use of this permit or approval , to comply
with all the conditions set forth, and understand the Department of
Building and Safety will not issue a building permit or allow occupancy
on the use permitted until this signed confirmation has been received
by the Department of Environmental Services.
_ (Date) (Applicant ' s Signature)
DESIGN REVIEW BOARD DATE: Dec. 6 , 1977
CASE NO. : 96MF
APPLICANT : CHARLES ROOT
LOCATION: West side of Verba Santa, south of Pitahaya
ZONING: PR-6
STAFF RECOMMENDATION :
Staff is recommending approval of the final construction
drawings. The Board may want to consider alternative trash
enclosure sites to make them more easily accessible to the
residents of the interior units.
SPECIAL CONDITIONS
CASE NO. 96MF
1 . Construction plans shall be submitted for approval to the City
Fire Marshal prior to issuance of building permits. All con-
ditions shall be made a part of construction and no certificate
of occupancy shall be issued until completed .
2 . Final construction drawings including a final landscaping, grading,
lighting, amenities , trash storage , walkway layout , and irrigation
plan shall be submitted to the Design Review Board. No final in-
spection or occupancy permit shall be given by the Dept . of Envi-
ronmental Services to this project until the aforementioned ap-
proved plans and construction shall have been completed.
3. Applicant shall comply with all of the requirements of related
Case No. DP 09-77.
4. " Each unit shall have its own trash enclosure area for easier access.
AGREEMENT
I accept and agree , prior to use of this permit or approval , to
comply with all the conditions set forth, and understand the Dept .
of Building and Safety will not issue a building permit or allow
occupancy on the use permitted until this signed confirmation has
been received by the Department of Environmental Services.
(Date) (Applicant ' s Signature)
DESIGN REVIEW BOARD DATE:Dec . 6, 1977
CASE NO. : 97MF
APPLICANT: W&R DEVELOPERS
LOCATION: Desert Paradise Tract , on Joshua between 44th and Parkview.
ZONING: R-1
STAFF RECOMMENDATION :
The applicant has responded to Special Condition No. 3 by
proposing the use of tile as a roofing material . Special
Condition No. 5 has not been adhered to in the final con-
struction drawings. The following list indicates the ele-
vations proposed by the applicant . Please compare with
the requirements of Special Condition No. 5.
Lot 51 Elevation C
Lot 68 Elevation C
Lot 69 Elevation A
Lot 70 Elevation B
Lot 79 Elevation C
Lot 80 Elevation B
Until Special Condition No. 5 is adhered to, Staff recom-
mends continuance of the case. Additionally, the Staff
recommends the use of shake as a roofing material for
Elevation C as it would appear more compatible with the - -
elevation than tile.
- SPECIAL CONDITIONS
CASE NO. 97MF
1 . Final construction drawings including a final landscaping,
grading and irrigation plan shall be submitted to the Design
Review Board. No final inspection or occupancy permit shall
be given by the Dept . of Environmental Services to this pro-
ject until the aforementioned- approved plans and construction
shall have been completed.
2. Applicant shall dedicate 30 feet from the Centerline of Man-
zanita Court on Lot 51 .
3. Applicant shall use tile , shake , or rock as roofing material .
4. Plant-ons shall be masonry, stucco, or veneer.
5. Elevations labeled A, B, and C are approved. Elevation A may be
- used two times, elevation B may be used three times, and elevation C
may be used one time .
AGREEMENT
I accept and agree , prior to use of this permit or approval , to
comply with all the conditions set forth , and understand the Dept .
of Building and Safety will not issue a building ptsrmit or allow
occupancy on the use permitted until this signed confirmation has
been received by the Department of Environmental Services.
_ (Date) (Applicant ' s Signature)
DESIGN REVIEW BOARD DATE :Dec . 6 , 1977
CASE NO. : 100MF
APPLICANT : SANTIAGO FERNANDEZ
LOCATION : Northwest corner of Alessandro & Santa Anita
ZONING: R-3(4)
STAFF RECOMMENDATION:
Staff is recommending approval of the final construction
drawings.
SPECIAL CONDITIONS FOR
CASE NO. 100MF
1 . Tile tappings shall be deleted and all windows shall be modified
by eliminating wood bars, utilizing stucco plant-ons .
2 . Rock roof shall be beige or tan in color.
3. Perimeter fencing material shall be specified in final construc-
tion drawings.
4. A detailed landscaping and irrigation plan shall be submitted
as a part of the submittal of final construction drawings .
el
AGREEMENT
I accept and agree, prior to use of this permit or approval ,
to comply with all the conditions set forth , and understand
the Department of Building and Safety will not issue a build-
ing permit or allow occupancy on the use permitted until this
signed confirmation has been received by the Department of
Environmental Services.
(Date) (Applicant ' s Signature) -
-
DESIGN REVIEW BOARD DATE: Dec. 6 , 1977
CASE NO. : 88MF (Revised)
APPLICANT : VICTOR JENNINGS
LOCATION : West side of Portola , northerly of Fairway
ZONING: R-2 , S.P.
STAFF RECOMMENDATION:
Approval of final construction drawings.
\ -
SPECIAL CONDITIONS
CASE NO. 88MF
1 . A 6 ft . masonry wall shall be installed along the north
property line or other alternative approved by the Design
Review Board.
2. As a part of the construction drawings include :
- a complete landscape plan
- provide large structure trees such as olives on each side of
entrance drive
- provide some treatment at ends of garages .
Agreement
I accept and agree, prior to use of this permit or approval, to
comply- with all the conditions set forth, and understand that the
Department of Building and Safety will not issue a building permit or
allow occupancy on the use permitted until this signed confirmation
has been received by the Department of Environmental Services.
(Date) (Applicant ' s Signature)