HomeMy WebLinkAbout1980-08-28 MINUTES
DESIGN REVIEW BOARD MEETING
THURSDAY - AUGUST 28, 1980
CITY HALL COUNCIL CHAMBERS
I . The meeting was called to order at 12:20 p.m. A 11-2 hour study session was
held on Tuesday, August 26, 1980.
MEMBERS PRESENT: Vern Barton
Al Cook (present during portion of meeting)
Bernie Leung
Charles Martin
Eric Johnson (present during portion of meeting)
MEMBERS ABSENT: Phyllis Jackson
Rick Holden
STAFF PRESENT: Stan Sawa
On a motion by Leung, seconded by Barton, the Board approved the minutes of
the meeting of August 12, 1980, as written.
Carried 3-0-1 (Barton, Leung, Martin, with Cook Abstaining)
II. Minutes Motion approving cases found acceptable at the study session: None.
III . CASES
Case No. 164 MF - SILVER SPUR ASSOCIATES AND WOODWARD DIKE - Final Approval of
landscaping plan for area C of Ironwood Country Club, on the north side of
Portola Avenue, just west of Mesa View Drive; Larry Spicer was present.
The Board reviewed the final landscaping and irrigation plans for area C. The
applicant briefly reviewed the plan and indicated the general concept. The
Board felt certain changes to the desert landscaping utilized should be incor-
porated. It was noted that the median in Mesa View Drive would be provided also
in the Cove Construction tract and as such landscaping within the median
should match the landscaping proposed by the applicant.
On a motion by Leung, seconded by Barton, the Board moved to approve final
landscaping plans subject to the following revisions:
1. Increase Desert Willows to 5 gallon size.
2. Delete D-2 and replace with 1 gallon Creosote Larrea and Encelia Farinosa.
3. Provide desert mix wild flowers in desert shrub areas.
Carried 4-0 (Barton, Cook, Leung, Martin) .
Case No. 200 MF - MAYER GROUP - Final approval of working drawings for 264
unit condominium project at the northeast corner of Monterey Avenue and
Country Club Drive; Patty Martin was present. Additionally, John Wilbanks,
Bob Muting, Michael Weidman and Dave Guiterrez were present during the informal
discussion on August 26, 1980.
Final working drawings were reviewed with the 13 items on the staff report
reviewed individually. With regard to the 13 items, it was noted that there
would be access to the park from the project. Landscaping changes were dis-
cussed pertaining to blowsand protection and adjacent to Country Club Drive.
It was determined that the sidewalk meandering was acceptable. The applicant
noted that there was suppose to be some variation to the straight walls along
Monterey Avenue and Country Club Drive.
The applicant explained that the trash container storage room, behind the
garages, would be utilized for trash cans. The applicant explained some of
the elevation changes and the reasons for them. It was noted that a lands-
caping plan for the center median would have to be submitted prior to the
construction of the median. Shading of the windows was discussed along with
provisiions for additional insulation. The Board indicated they would like
MINUTES
DESIGN REVIEW BOARD
AUGUST 28, 1980 Page Two
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
III. CASES (Cont. )
to review a evaluation of what affect increasing the insulation to R-30
would have on heat gain.
Other items of discussion pertain to landscaping and entry design.
On a motion by Johnson, seconded by Martin, the Board moved to grant approval
of final working drawings, subject to the following revisions:
1. Design of fountain at entry on Country Club Drive to be reviewed by
Design Review Board prior to its construction.
2. Entrances on both streets to be revised to provide 20' of width for
egress so that one lane can be provided for left turns and one lane
for right turns; Additionally, center median to be cut back approxi-
mately 10' to facilitate easier ingress and egress.
3. Working drawings to be revised to show undulation in straight wall
along Country Club Drive.
4. Along each side of entry to project on Monterey Avenue and Country Club
Drive, delete T-3 and use T-1 (Bottle Tree) .
5. Along Country Club Drive and Monterey Avenue, delete tree type T-3 and
replace with 24" box size Rhus Lancea.
6. Change tree type T-13 to Pinaus Eldarica.
7. Modify working drawings to indicate access to park.
8. Delete tree type T-3 where used for blowsand protection on north and
west, and replace with 15 gallon Rhus Lancea.
9. At easterly property line along Country Club Drive modify sidewalk so
that it ends adjacent to curb. Prior to construction of center median
submit landscaping and irrigation plans to Design Review Board for
approval .
10. Submit evaluation showing heat gain, which could be expected if
R-30 insulation is utilized.
Carried 4-0 (Barton, Leung, Martin, Johnson).
Note: Al Cook left during discussion of the previous item and Eric Johnson
arrived at beginning of previous item.
Case No. 200 MF - MAYER GROUP AND BALLEW-MCFARLAND - Preliminary review of
plans for 9 acre public park at the northeast corner of Monterey Avenue and
Country Club Drive; Patty Martin was present. Additionally, John Wilbanks,
Bob Muting, Michael Weidman and Dave Guiterrez were present during the in-
formal discussion on August 26, 1980.
The park design was reviewed by the Design Review Board with the Board feeling
that the park design was generally unacceptable for a number of reasons.
The Board felt that additional parking should be provided. Additionally,
landscaping should be compatible with the residential project which borders
the park on the north and east. Additionally, heavy planting and fencing
should be utilized adjacent to the baseball court to protect the parking
facilities from stray balls.
The Board felt that possibly the design of the park should be restudied. They
felt that . the park should be a passive park.
Additionally, additional parking should be provided. The Board also felt that
a study could be made to determine demand, age groups utilizing the parks,
appropriate uses for the park for the present and future. The Board noted
MINUTES
DESIGN REVIEW BOARD
AUGUST 28, 1980 Page Three
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
III. CASES (cont. )
that the feasibility of night lighting the park should be studied now. They
stated that possibly there are too many tennis courts and that additional
parking should be provided instead.
Staff noted that their comments would be forwarded to the Planning Commission
who would review and approve the final park design.
On a motion by Johnson, seconded by Barton, the Board moved to recommend that
their comments, as stated above, be forwarded to the Planning Commission.
Carried 4-0 (Barton, Leung, Martin, Johnson).
Case No. 159 MF - FRANK OLIVER - Approval of modification to final working
drawings for preschool under construction at the northwest corner of Alessandro
Drive and Cabrillo Avenue; Frank Oliver was present during the informal dis-
cussion on August 26, 1980.
The Board reviewed the requested changes submitted by the applicant. After
some discussion, the Board felt that they should review revised elevations
and site plans which show the revised location of the dormers. Additionally,
they requested to see a revised landscaping plan as discussed with the
applicant on August 26, 1980. The also requested to see working drawings of
the second story, which had been added to the building without prior Design
Review Board or City approval .
On a motion by Johnson, seconded by Barton, the Board moved to continue this
item until the above mentioned items are submitted for Design Review Board
approval .
Carried 3-0-1 (Barton, Leung, Johnson, with Martin abstaining) .
IV. DISCUSSION ITEMS
The Board, during their study session on August 26, 1980, reviewed the
preliminary landscaped plan for the Haystack Road drainage Swale and felt
that the plant materials utilized were acceptable. The materials should
be compatible with the landscape plan, which is being developed by Lewis
Homes on Haystack Road.
V. ADJOURNMENT - 1:47 P.M.
A- ht&� LUX,
STAN SAWA, Associate Planner
/lr