PLANNING COMMISSION RESOLUTION NO. 78
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF PALM DESERT,
CALIFORNIA, ANNOUNCING FINDINGS AND APPROVING A PLOT PLAN TO ALLOW
THE DEVELOPMENT OF A COMMERCIAL OFFICE -RETAIL BUILDING ON PROPERTY
GENERALLY LOCATED AT THE NORTHWEST CORNER OF THE INTERSECTION OF
EL PASEO AND SAGE LANE. CASE NO. 18C.
WHEREAS, the Planning Commission of the City of Palm Desert did receive
a verified application from CURT DUNHAM requesting approval of a Plot Plan on
property located in the C-P-S Zone, and situated at the northwest corner of the
intersection of Sage Lane and El Paseo to allow for the development of a commercial
retail -office building; the property being more particularly described as:
Assessor's Parcel No.s 627-192-024 & 627-192-011
WHEREAS, said application has complied with the requirements of the "City
of Palm Desert Environmental Quality Procedure Resolution Number 74-14", in that
the project is a ministerial action and is exempt under the provisions of the
California Environmental Quality Act of 1970; and
WHEREAS, on September 2, 1975, the Planning Commission did consider this
request for Plot Plan approval; and
WHEREAS, at that time, upon receiving and considering the testimony and
arguments, if any, of all persons who desired to be heard, said Commission did
find the following facts and reasons to exist to approve the Plot Plan:
1. Conformance of the proposed development to all requirements of the
General Plan and Zoning Ordinance.
2. The proposed development does ensure the protection of the public
health, safety and general welfare.
3. Compatibility of the proposed project to the existing and proposed
development in the area.
NOW, THEREFORE, BE IT RESOLVED by the Planning Commission of the City
of Palm Desert as follows:
1. That the above recitations are true and correct and constitute
the findings of the Commission in this case.
2. That it does hereby approve plot plan no. 18C, subject to the
attached conditions.
RESOLUTION NO. 78
PASSED, APPROVED AND ADOPTED at the regular meeting of the Planning
Commission of the City of Palm Desert, California, held on September 2, 1975,
by the following vote to wit:
AYES: BERKEY, MULLINS, SEIDLER, VAN DE MARK, WILSON
NOES:
ABSENT:
ABSTAIN:
ATTEST
ephen A. Fleshman, ASSOCIATE PLANNER
CONDITIONS OF APPROVAL
CASE # 18C
1. The development of this project shall conform substantially to all develop-
ment plans submitted in behalf of this case (Exhibit (s) A-1, B, C) and as
revised according to Planning Commission action. Any minor changes require
approval by the Director of Fnvironmental Services. Any substantial changes
require approval by the Planning Commission.
2. All requirements of any law, ordinance, or regulation of the State, City
and other applicable government entity shall be complied with as part of the
development process.
3. This approval is applicable, subject to the development of this project
commencing within one year from approval date and being promptly completed.
Applicant shall also submit plans approved by Palm Desert Property Owners
Association prior to construction.
4. Curb, gutter, sidewalk, curb cuts, tie-in paving and parking lot improve-
ments shall be provided in conformance with Riverside County Standards and
Palm Desert Zoning Ordinance requirements.
A. The full frontage of both Sage Lane and El Paseo, adjacent to the
parcel shall be improved with sidewalk, curb, gutter and tie-in
paving to standards as specified by the Riverside County Road
Department. The road shall be built to conform to the existing curb
returns.
5. Alley shown along rear of property shall be paved to a minimum of 20 feet
to Riverside County Standards.
6. Traffic control provisions shall be provided as required by the Director
of Environmental Services.
7. Lighting of parking areas and premises shall be approved by the Director
of Environmental Services.
8. Applicant shall submit a drainage plan considering the building site and
adjacent properties to the Director of Environmental Services for approval.
9. A complete and detailed landscaping and irrigation plan shall be provided
to the Director of Environmental Services for approval. Said improvements
shall be made a part of the construction and no permit for final occupancy
shall be approved until installed.
10. A noncombustible trash storage area built to City Standards, location to be
determined by the Director of Environmental Services.
11. All service lines shall be placed underground or a cash bond shall be provided
for the costs of undergrounding distribution lines.
12. Roof mounted exhaust or air conditioning equipment shall be screened from
view.
13. Elevations are approved as shown.
14. Signage shall be provided in accordance with comprehensive signage plan to
be submitted to DRB for final approval.
15. The precise design of the parking lot shall be determined at a later date.
The Director of Environmental Services will work with the Redevelopment
Agency and other commercial groups to develop a workable plan for this
block. Any future design shall not include less than 57 spaces.