HomeMy WebLinkAboutRes No 206PLANNING COMMISSION RESOLUTION NO. 206
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
PALM DESERT, CALIFORNIA, ANNOUNCING FINDINGS AND APPROVING
THE DESIGN REVIEW BOARD ACTIONS OF DECEMBER 21, 1977.
WHEREAS, the Planning Commission of the City of Palm Desert, California,
did review the Design Review Board actions of December 21, 1977, approving:
Case No. 39C - Final construction drawings for a 12,500 square foot
commercial building for J & R Enterprises;
Case No. 45C - Preliminary drawings for a new 11,000 square foot
bank building for BANK OF AMERICA.
WHEREAS, at this time, upon receiving and considering all testimony
and arguments, if any, of all interested persons desiring to be heard, said
Planning Commission did find sufficient facts and reasons to exist to approve
the Design Review Board actions of December 21, 1976.
NOW, THEREFORE, BE IT RESOLVED by the Planning Commission of the City
of Palm Desert, California, as follows:
1) That the above recitations are true and correct and constitute the
findings of the Commission in this case;
2) That it does hereby approve the Design Review Board actions of
December 21, 1976; with a modification to Condition of Approval No. 17 for Case
No. 45C as follows:
17. All existing signs on Lot 1 shall be removed within
five (5) working days of occupancy of the new building,
to include removal of the structural elements and poles
for said signs.
PASSED, APPROVED, and ADOPTED at a regularly scheduled meeting of the
Palm Desert Planning Commission, held on this 4th day of January, 1977, by the
following vote, to wit:
AYES: BERKEY, KELLY, READING, WILSON
NOES: NONE
ABSENT: MILLS
ABSTAIN: NONE
ATTEST:
PAUL A. WILLIAMS, SECRETARY
PALM DESERT PLANNING COMMISSION
December 21, 1976
CONDITIONS OF APPROVAL
CASE NO. 45C
1. The development of this project shall conform substantially to all
development plans submitted in behalf of this case (Exhibits A-G),
and as revised according to the Design Review Board process. Any
minor changes require approval by the Director of Environmental
Services. Any substantial change requires approval by the Planning
Commission.
2. All requirements of any law, ordinance, or regulation of the State,
City, and any other applicable government entity shall be complied
with as part of the development process.
3. This approval is applicable, subject to the development of this pro-
ject, commencing within one year from approval date and being promptly
completed.
4. Any roof mounted, exhaust, or air conditioning equipment shall be fully
concealed from view from any public rights -of -way and adjoining proper-
ties by architecturally integrated means as shown.
5. All utility service and distribution lines shall be placed underground.
6. Curb, gutter, sidewalk or approved pathways, curb cuts, and tie-in
paving shall be provided in conformance with City Standards for the
following:
a) The applicant shall install curb, gutter, and sidewalk along the
full frontage of San Luis Rey.
7. Final landscaping (with irrigation system) plans indicating plant sizes
and heights shall be provided to the Design Review Board for approval
prior to issuance of a building permit.
8. Lighting of parking areas and premises shall be provided as approved by
the Director of Environmental Services.
9. Signage shall be provided in accordance with signage plan to be submitted
to the Design Review Board and the Planning Commission for final approval.
10. Traffic control provisions shall be provided as required by the Traffic
Engineer.
11. Elevations are approved as shown.
12. Construction plans shall be submitted for approval to the City Fire
Marshall prior to issuance of building permits. All conditions shall
be made a part of construction and no certificate of occupancy shall
be issued until completed.
13. A detailed grading plan shall be submitted to the City Engineer for
approval.
14. The applicant shall agree to join any assessment district formed that
includes the subject property within its boundaries.
15. The applicant shall grant to the City of Palm Desert, easement rights
over the parking lot area of the project site.
16. Parking lot improvements shall include Lots 1, 30, 31, and 32 and com-
plete plans for this total site shall be submitted to the Design Review
Board process for approval.
17. All existing signs on Lot 1 shall be removed within five (5) working
days of occupancy of the new building, to include removal of the struc-
tural elements and poles for said signs.
-1-
18. The landscape plan shall provide for a minimum of 20" box trees throughout
the entire project.
AGREEMENT
I accept and agree, to use of this permit or approval, to comply with all the
conditions set forth, and understand that the Department of Building & Safety
will not issue a permit or allow occupancy on the use permitted until this
signed confirmation has been received by the Department of Environmental
Services.
(Date) (Applicant's Signature)