Loading...
HomeMy WebLinkAboutRes No 224PLANNING COMMISSION RESOLUTION NO. 224 A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF PALM DESERT, CALIFORNIA, ANNOUNCING FINDINGS AND APPROVING THE DESIGN REVIEW BOARD ACTIONS OF MARCH 8, 1977. WHEREAS, the Planning Commission of the City of Palm Desert, California, did review the Design Review Board actions of March 8, 1977, approving: Case No. 45C - Parking lot layout, drainage, signs, and parking lot lighting for the BANK OF AMERICA at El Paseo and San Luis Rey; WHEREAS, at this time, upon considering and receiving all testimony and arguments, if any, of all interested persons desiring to be heard, said Planning Commission did find sufficient facts and reasons to exist to approve the Design Review Board actions of March 8, 1977. NOW, THEREFORE, BE IT RESOLVED by the Planning Commission of the City of Palm Desert, California, as follows: 1) that the above recitations are true and correct and constitute the findings of the Commission in this case; 2) that it does hereby approve the Design Review Board actions of March 8, 1977. PASSED, APPROVED, and ADOPTED at a regular meeting of the Palm Desert Planning Commission, held on this 15th day of March, 1977, by the following vote, to wit: AYES: BERKEY, KELLY, MILLS, READING, WILSON NOES: NONE ABSENT: NONE ABSTAIN: NONE ATTEST: PAUL A. WILLIAMS, SECRETARY PALM DESERT PLANNING COMMISSION OY WILSCHAIRMAN MARCH 8, 1977 CONDITIONS OF APPROVAL CASE NO. 45C BANK OF AMERICA SIGN PLAN 1. The development of this project shall conform to all plans submitted in behalf of this case, Exhibits I and J, and as revised according to Plan- ning Commission action. Any minor changes require approval by the Direc- tor of Environmental Services. Any substantial change requires approval by the Design Review Board and Planning Commission. 2. All requirements of any law, ordinance, or regulation of the State, City, and any other applicable government entity shall be complied with as a part of the development process. 3. Drainage and revised parking lot layout plan are approved. 4. Traffic signs shall be provided as required by the City Engineer. 5. The following signage is approved: a) Delete all "A" and "B" signs and the ground plaque. b) Chains shall be permitted at both ends of the window teller access aisle. c) One (1) "hours of operation" sign shall be permitted at the entrance to the window teller access aisle. d) "C", "D", and "F" signs are approved, white letters on gold back- ground, with a maximum sign height of 4.5 feet, with landscaping around the base. e) One (1) non -illuminated monument sign as detailed on Exhibit J is approved with white letters, gold background, and black trim at the northeast corner of El Paseo and San Luis Rey. f) One (1) logo sign (gold letters on black background) is approved for the north face of the building - not to exceed a maximum height on the wall of twenty (20) feet. g) Delete "Bank of America" wall signs from west and east elevations. 6. Approve light standard WTC, Kim Lighting Inc., for use in parking lot. AGREEMENT I accept and agree, prior to use of this permit or approval, to comply with all the conditions set forth, and understand that the Department of Building and Safety will not issue a building permit or allow occupancy on the use permitted until this signed confirmation has been received by the Department of Environmental Services. (Date) (Applicant's Signature)