HomeMy WebLinkAboutRes No 248PLANNING COMMISSION RESOLUTION NO. 248
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF PALM
DESERT, CALIFORNIA, ANNOUNCING FINDINGS AND APPROVING A CASE
FROM THE DESIGN REVIEW BOARD MEETING OF MAY 24, 1977
WHEREAS, the Planning Commission of the City of Palm Desert, California,
did review a Case from the Design Review Board Meeting of May 24, 1977, approv-
ing:
CASE NO. 73MF - Preliminary site, floor, and elevation
plans for a 5-unit apartment complex for
Alfred H. Cook;
WHEREAS, at this time, upon considering and receiving all testimony and
arguments, if any, of all interested persons desiring to be heard, said Commission
did find sufficient facts and reasons to exist to approve a case from the Design
Review Board Meeting of May 24, 1977.
NOW, THEREFORE, BE IT RESOLVED by the Planning Commission of the City of
Palm Desert, California, as follows:
1. That the above recitations are true and correct and constitute the
findings of the Commission in this case;
2. That it does hereby approve a case from the Design Review Board Meet-
ing of May 24, 1977.
PASSED, APPROVED, AND ADOPTED at a regular meeting of the Palm Desert Plan-
ning Commission, held on this 31st day of May, 1977, by the following vote, to
wit:
AYES: KRYDER, READING, SNYDER, BERKEY
NOES: NONE
ABSENT: NONE
ABSTAIN: KELLY
GEORGE B KEY, CHAIRMAN
ATTEST:
PAUL A. WILLIAMS, SECRETARY
PALM DESERT PLANNING COMMISSION
May 24, 1977
CONDITIONS OF APPROVAL
CASE NO. 73MF
1. The development of this project shall conform substantially to all develop-
ment plans submitted in behalf of this case (Exhibits A-B), and as revised
according to the Design Review Board process. Any minor changes require
approval by the Director of Environmental Services.
2. All requirements of any law, ordinance, or regulation of the State, City,
and any other applicable government entity shall be complied with as part
of the development process.
3. This approval is applicable, subject to the development of this project, com-
mencing within one year from approval date and being promptly completed.
4. All service lines for utilities shall be placed underground.
5. Curb, gutter, sidewalk, curb cuts, and tie-in paving shall be provided on
Tumbleweed in conformance with City Standards and the requirements of the
City Engineer at the time of construction or by future agreement with the
City Engineer. Improvement location is not approved.
6. Storage facilities shall be provided in all carports.
7. Final construction drawings shall be submitted to the City Fire Marshal
prior to the submittal of plans for Building Plan Check.
8. Final construction plans shall be submitted to the Design Review Board for
approval prior to submittal of plans to the Dept. of Building and Safety
for plan check.
AGREEMENT
I accept and agree, prior to use of this permit or approval, to comply with all the
conditions set forth, and understand that the Department of Building & Safety will
not issue a building permit or allow occupancy on the use permitted until this signed
confirmation has been received by the Department of Environmental Services.
(Date) (Applicant's Signature)