HomeMy WebLinkAboutRes OB-101 (2)OVERSIGHT BOARD TO SUCCESSOR AGENCY OF THE PALM
DESERT REDEVELOPMENT AGENCY
STAFF REPORT
OB-101
REQUEST: APPROVE RESOLUTION NO. - A RESOLUTION OF THE
OVERSIGHT BOARD OF THE SUCCESSOR AGENCY TO THE PALM
DESERT REDEVELOPMENT AGENCY APPROVING THE EXECUTION
OF AN AGREEMENT FOR UNIVERSITY SITE WORK AND COSTS
BETWEEN THE SUCCESSOR AGENCY AND THE CITY OF PALM
DESERT
SUBMITTED BY: Mark Greenwood, Director of Public Works
DATE: November 3, 2014
CONTENTS: Resolution No. OB-101
Reimbursement Agreement-C33990
Recommendation
By Minute Motion that the Oversight Board:
OB-101
1. Waive further reading and adopt Resolution No. approving the
execution of a Funding Agreement for University Site work and costs
between the Successor Agency to the Palm Desert Redevelopment
Agency and the City of Palm Desert and taking certain related actions.
Background
The vacant land currently owned by the Successor Agency to the Palm Desert
Redevelopment Agency (Successor Agency), bounded by Cook Street, Frank Sinatra,
and Gerald Ford (commonly referred to as the University Site) has become a Health
and Safety concern over the last 18 months due to the dust that is blown across the
site. Successor Agency staff has received numerous complaints from residents living
downwind from the site about the inconvenience of several inches of sand built up in
their streets and in their yards, as well as complaints of health related problems caused
by the blowing sand.
In May of 2013, the City received two Notices to Comply from the South Coast Air
Quality Management District because of dust and sand blowing off the subject site. The
Successor Agency constructed wind fence and stabilized a small portion of the lot, but
the improvements had very little impact upon the problem because the unstabilized
acreage upwind from the improvements is a constant source of new blowing sand.
G.PubWorks1Ryan Gayler\Word Fues\Staff ReportslOB SR -Soil Stabilization Reimb Agmt docx
Staff Report
University Site Soil Stabilization Project Funding Agreement
Page 2 of 2
November 3, 2014
Pursuant to the Long Range Property Management Plan (LRPMP), most of the Property
will be transferred to California State University, San Bernardino ("the University") for
use for education facilities. The Successor Agency is engaged with the University
regarding details that must be finalized before the transfer can occur. But until such
details are finalized, the Successor Agency's disposition of the Property is pending and
the Successor Agency must continue to maintain the Property.
At the request of the Executive Director of the Successor Agency, the City of Palm
Desert Public Works Department has advertised a project for bid that will seal the
undeveloped land on the University Site. If this agreement is approved, the project will
be presented to the City Council for award November 13, 2014.
The estimated cost for the improvements is included on the 14-15A Recognized
Obligation Payment Schedule (ROPS) and will be immediately transferred to the City
upon approval of the agreement.
Staff recommends that the Oversight Board for the Successor Agency adopt Resolution
No. oB-ioi approving the execution of a Funding Agreement, for University Site Work
and Costs, between the Successor Agency to the Palm Desert Redevelopment Agency
and the City of Palm Desert and taking certain related actions.
Fiscal Analysis
Although the General Fund may initially advance the funds for this work, it is the
intention of the Successor Agency to reimburse the City for the costs from the 14-15A
ROPS, line 43. Only in the event there are no funding sources available from the
Successor Agency would the General Fund have to pay for the work.
Preppred By:
RyaGayler, Project Administrator
Paul S. Gibson, Director of Finance
Approval:
114„,0
M. WohImuth
Manager/Executive Director of the
ccessor Agency of the Palm Desert
edevelopment Agency
Depad:
Mark Gfe
Director o
wood, P.E.
Public Works
(G 0, LQ snr- Alb.SEr•/T.)
rbt BY OVERSIGHT BOARD
ON t�-'�
VERIFIED B
Original on file with City Jerk's Office
G:\PubWorks\Ryan Gayler\Word Files\Staff Reports\OB SR -Soil Stabilization Reimb Agmt.docx
RESOLUTION NO. OB-1°1
A RESOLUTION OF THE OVERSIGHT BOARD OF THE SUCCESSOR
AGENCY TO THE PALM DESERT REDEVELOPMENT AGENCY
APPROVING THE EXECUTION OF AN AGREEMENT FOR UNIVERSITY
SITE WORK AND COSTS BETWEEN THE SUCCESSOR AGENCY AND
THE CITY OF PALM DESERT
RECITALS:
A. Pursuant to AB X1 26 (enacted in June 2011), as modified by the
California Supreme Court's decision in California Redevelopment Association, et al. v.
Ana Matosantos, et al., 53 Cal. 4th 231(2011), the Palm Desert Redevelopment Agency
(the "Former Agency") was dissolved as of February 1, 2012, the Successor Agency
was established and an Oversight Board to the Successor Agency (the "Oversight
Board") was constituted.
B. AB 1484 (enacted in June 2012) amended and supplemented the
provisions of AB X1 26. Together, AB X1 26 and AB 1484 are referred to herein as the
"Dissolution Act."
C. Pursuant to Section 34175(b) of the Califomia Health and Safety Code
("HSC"), all assets of the Former Agency, including that certain real property (the
"Property"), sometimes referred to as the University Site — consisting of undeveloped
land in the City bounded by Frank Sinatra Drive on the south, Cook Street on the west,
and Gerald Ford Drive on the north and east — transferred to the control of the
Successor Agency by operation of law
D. The Property is identified as Property Nos. 10(a) and 10(b) on the
Successor Agency's Long Range Property Management Plan (the "LRPMP"). The
LRPMP has been previously approved by the Oversight Board and the Califomia State
Department of Finance ("DOF"), as indicated in the DOF's related June 2, 2014
approval letter.
E. The Successor Agency is charged with maintaining the Property before
the disposition of the Property in a manner consistent with the LRPMP and the
Dissolution Act.
F. Pursuant to the LRPMP, most of the Property will be transferred to
California State University, San Bernardino ("the University") for use for education
facilities. The Successor Agency is engaged with the University regarding details that
must be finalized before the transfer can occur. Until such details are finalized, the
Successor Agency's disposition of the Property is pending and the Successor Agency
must continue to maintain the Property.
G. The Property has been the subject of complaints from nearby residents
and Notices to Comply from the South Coast Air Quality Management District regarding
12812-0001 \1632317.1 1
RESOLUTION NO. oB-101
high particulate matters (PM-10) from the Property that become airborne from blowing
winds, causing nuisance and potential health hazards.
H. While prior efforts — including the installation of wind fences at strategic
locations and the sealing of certain portions of the Property — had mild successes
against light winds, these measures have been insufficient to overcome the effects of
even moderate wind storms.
I. Additional work (the "Work") is required to address the on -going nuisance
and potential health hazard. Such Work is currently expected to include the sealing of
the entire surface of the Property.
J. Pursuant to HSC Sections 34171(b) and 34171(d)(1)(F), the costs of
maintaining the Property before its disposition constitute enforceable obligations of the
Successor Agency, separate and apart from the Successor Agency's administrative
cost allowance (as defined under HSC Section 34171(b)).
K. Pursuant to HSC Section 34177(1), the Successor Agency is required to
prepare a Recognized Obligation Payment Schedule ("ROPS"), listing the Successor
Agency's enforceable obligations, and the related estimated dollar amounts, to be paid
by the Successor Agency for each six month fiscal period (commencing January 1 and
July 1, respectively) (each, a "ROPS Period"), and submit such ROPS to the Oversight
Board and the DOF for approval.
L. The Successor Agency previously prepared a ROPS ("ROPS 14-15A") for
anticipated payments covering the period from July 1, 2014 through December 31, 2014
(the "ROPS 14-15A Period").
M. Listed as Item No. 43 on ROPS 14-15A is $120,000 for the utilities,
services and other costs expected to be incurred for the maintenance of Successor
Agency -owned properties. Item No. 43 is intended to include the cost of the Work
("Work Costs") relating to the Property to be incurred during the ROPS 14-15A Period.
As indicated on ROPS 14-15A, Item No. 43 is to be paid from moneys disbursed by the
County Auditor -Controller from the Redevelopment Property Tax Trust for ROPS 14-
15A Period payments (the "ROPS 14-15A RPTTF Disbursement").
N. The Oversight Board adopted Resolution No. OB-064, on February 24,
2014, approving ROPS 14-15A.
O. The Successor Agency received the DOF's letter dated May 16, 2014,
indicating the DOF's approval of ROPS 14-15A with certain modifications, which
modifications did not affect Item No. 43.
P. Based on current estimates, the total Work Costs to be incurred during the
ROPS 14-15A Period will be $86,000.
12812-000I\1760669.1
RESOLUTION NO. oB-1OL
Q. As between the City of Palm Desert (the "City") and the Successor
Agency, the City has the resources (with respect to the staffing and established
procedures) to manage contracts and otherwise coordinate with third parties in
connection with the Work.
R. The Successor Agency and the City desire to enter into an Agreement for
University Site Work and Costs (the "Agreement"), substantially in the form attached
hereto as Exhibit A, for the City to perform or cause to be performed all Work required,
with payment therefor to be made from the funds available to the Successor Agency.
S. Pursuant to HSC Sections 34178(a) and 34180(h), the Successor Agency
may enter into agreements with the City with the Oversight Board's approval.
NOW, THEREFORE, THE OVERSIGHT BOARD OF THE SUCCESSOR
AGENCY TO THE PALM DESERT REDEVELOPMENT AGENCY DOES HEREBY
RESOLVE, DETERMINE AND ORDER AS FOLLOWS:
Section 1. Recitals. The above recitals, and each of them, are true and
correct.
Section 2. Aareement for University Site Work and Costs. This Oversight
Board hereby approves the Successor Agency's execution and delivery of the
Agreement, substantially in the form attached hereto as Exhibit A.
Section 3. Other Acts. The members of this Oversight Board and the staff of
the Successor Agency are hereby authorized, jointly and severally, to do all things
which they may deem necessary or proper to effectuate the purposes of this
Resolution and the Agreement.
APPROVED and ADOPTED this day of , 2014.
ROBERT A. SPIEGEL, CHAIR
ATTEST:
RACHELLE D. KLASSEN, SECRETARY
OVERSIGHT BOARD FOR THE SUCCESSOR AGENCY TO THE
PALM DESERT REDEVELOPMENT AGENCY
12812-0001\1760669.1
RESOLUTION NO. OB-101
EXHIBIT A
Agreement for University Site Work and Costs
(in substantial final form)
(see attached)
12812-0001 \I 760669.1
RESOLUTION NO. 0B-101 CONTRACT NO. C33990
AGREEMENT FOR UNIVERSITY SITE WORK AND COSTS
This AGREEMENT FOR UNIVERSITY SITE WORK AND COSTS (this
"Agreement"), dated as of , 2014, is entered into by and between the Successor
Agency to the Palm Desert Redevelopment Agency (the "Successor Agency") and the City of
Palm Desert (the "City", and together with the Successor Agency, the "Parties").
RECITALS:
A. Pursuant to AB X1 26 (enacted in June 2011), as modified by the California
Supreme Court's decision in California Redevelopment Association, et al. v. Ana Matosantos, et
al., 53 Cal. 4th 231(2011), the Palm Desert Redevelopment Agency (the "Former Agency") was
dissolved as of February 1, 2012, the Successor Agency was established and an Oversight Board
to the Successor Agency (the "Oversight Board") was constituted.
B. AB 1484 (enacted in June 2012) amended and supplemented the provisions of AB
X1 26. Together, AB X1 26 and AB 1484 are referred to herein as the "Dissolution Act."
C. Pursuant to Section 34175(b) of the California Health and Safety Code ("HSC"),
all assets of the Former Agency, including that certain real property (the "Property"), sometimes
referred to as the University Site — consisting of undeveloped land in the City bounded by Frank
Sinatra Drive on the south, Cook Street on the west, and Gerald Ford Drive on the north and east
— transferred to the control of the Successor Agency by operation of law.
D. The Property is identified as Property Nos. 10(a) and 10(b) on the Successor
Agency's Long Range Property Management Plan (the "LRPMP"). The LRPMP has been
previously approved by the Oversight Board and the California State Department of Finance
("DOF"), as indicated in the DOF's related June 2, 2014 approval letter.
E. The Successor Agency is charged with maintaining the Property before the
disposition of the Property in a manner consistent with the LRPMP and the Dissolution Act.
F. Pursuant to the LRPMP, most of the Property will be transferred to California
State University, San Bernardino ("the University") for use for education facilities. The
Successor Agency is engaged with the University regarding details that must be finalized before
the transfer can occur. Until such details are finalized, the Successor Agency's disposition of the
Property is pending and the Successor Agency must continue to maintain the Property.
G. The Property has been the subject of complaints from nearby residents and
Notices to Comply from the South Coast Air Quality Management District regarding high
particulate matters (PM-10) from the Property that become airborne from blowing winds,
causing nuisance and potential health hazards.
H. While prior efforts — including the installation of wind fences at strategic
locations and the sealing of certain portions of the Property — had mild successes against light
winds, these measures have been insufficient to overcome the effects of even moderate wind
storms.
-1-
12812.000I \ 1764I 1.2
RESOLUTION NO. OB-101 CONTRACT NO. C33990
I. Additional work (the "Work") is required to address the on -going nuisance and
potential health hazard. Such Work is currently expected to include the sealing of the entire
surface of the Property.
J. Pursuant to HSC Sections 34171(b) and 34171(d)(1)(F), the costs of maintaining
the Property before its disposition constitute enforceable obligations of the Successor Agency,
separate and apart from the Successor Agency's administrative cost allowance (as defined under
HSC Section 34171(b)).
K. Pursuant to HSC Section 34177(1), the Successor Agency is required to prepare a
Recognized Obligation Payment Schedule ("ROPS"), listing the Successor Agency's enforceable
obligations, and the related estimated dollar amounts, to be paid by the Successor Agency for
each six month fiscal period (commencing January 1 and July 1, respectively) (each, a "ROPS
Period"), and submit such ROPS to the Oversight Board and the DOF for approval.
L. The Successor Agency previously prepared a ROPS ("ROPS 14-15A") for
anticipated payments covering the period from July 1, 2014 through December 31, 2014 (the
"ROPS 14-15A Period").
M. Listed as Item No. 43 on ROPS 14-15A is $120,000 for the utilities, services and
other costs expected to be incurred for the maintenance of Successor Agency -owned properties.
Item No. 43 is intended to include the cost of the Work ("Work Costs") relating to the Property
to be incurred during the ROPS 14-15A Period. As indicated on ROPS 14-15A, Item No. 43 is
to be paid from moneys disbursed by the County Auditor -Controller from the Redevelopment
Property Tax Trust for ROPS 14-15A Period payments (the "ROPS 14-15A RPTTF
Disbursement").
N. The Oversight Board adopted Resolution No. OB-064, on February 24, 2014,
approving ROPS 14-15A.
O. The Successor Agency received the DOF's letter dated May 16, 2014, indicating
the DOF's approval of ROPS 14-15A with certain modifications, which modifications did not
affect Item No. 43.
P. Based on current estimates, the total Work Costs to be incurred during the ROPS
14-15A Period will be $86,000.
Q. As between the City and the Successor Agency, the City has the resources (with
respect to the staffing and established procedures) to manage contracts and otherwise coordinate
with third parties in connection with the Work.
R. The Successor Agency and the City desire to enter into this Agreement, for the
City to perform or cause to be performed all Work required, with payment therefor to be made
from the funds available to the Successor Agency.
S. Pursuant to HSC Sections 34178(a) and 34180(h), the Successor Agency may
enter into agreements with the City with the Oversight Board's approval.
-2-
128 12.000I \ 1764 11.2
RESOLUTION NO. OB-101 CONTRACT NO. C33990
T. The Oversight Board adopted its Resolution No. on , 2014
(the "Oversight Board Resolution"), approving the Successor Agency's execution and delivery
of this Agreement.
U. The Oversight Board Resolution was [approved] [deemed approved] by the DOF
pursuant to HSC Section 34179(h) on , 2014.
NOW, THEREFORE, THE PARTIES DO HEREBY AGREE AS FOLLOWS:
Section 1. Subject to the provisions of this Agreement and with the funding provided
pursuant to this Agreement, the City agrees to perform or cause to be performed all Work
required to mitigate the on -going nuisance and potential health hazard, including but not limited
to the plans and specifications thereof and all actual work related thereto. The City shall perform
the Work (or cause the performance thereof) in accordance with all applicable federal, state and
local laws, and rules and regulations. Subject to the provisions set forth herein, the City shall
have the sole discretion with respect to the planning, specification and the timing with respect to
all components of the Work.
Section 2. As soon as practical upon the execution of this Agreement by the Parties
(and in any case before the end of ROPS 14-15A Period), the Successor Agency shall transfer an
amount equal to $86,000 from the portion of the ROPS 14-15A RPTTF Disbursement allocable
to Item 43.
Section 3. At any time, if the City determines that the amount previously transferred
by the Successor Agency pursuant to this Agreement is insufficient for the completion of the
Work, the City's Finance Director shall notify the Successor Agency, specifying the estimated
dollar amount necessary for thc completion of the Work (thc "Additional Costs"). The
Successor Agency shall list the Additional Costs on the ROPS for the next available ROPS
Period. Subject to the Oversight Board's and the DOF's approval (and any modification) of such
ROPS item(s), the Successor Agency shall transfer or caused to be transferred to the City the
Additional Costs as soon as practicable upon the commencement of the applicable ROPS Period.
Section 4. Before each transfer of moneys by the Successor Agency pursuant to this
Agreement, the City may, but is not obligated to, advance funds from sources available to City
for the work necessary for the Work (cach such advance being a "City Advance"). Any such
City Advance made pursuant to this Agreement shall constitute a loan under HSC Section
34173(h) and the repayment of the City Advance pursuant to this Agreement shall constitute an
enforceable obligation of the Successor Agency. Any amount transferred by the Successor
Agency pursuant to this Agreement shall first be used to reimburse the City for outstanding City
Advances, and then to pay for other expenditures of the Work.
Section 5. The Parties agree that the City's obligation with respect to the work for the
Work under this Agreement shall be limited to the extent that funding therefor is available from
the Successor Agency pursuant to this Agreement.
Section 6. To the extent the City still holds moneys (the "Excess") transferred by the
Successor Agency pursuant to this Agreement after the payment of all of the Work Costs
-3-
128I2.0001 \176411.2
RESOLUTION NO. OB-101 CONTRACT NO. C33990
incurred (including the reimbursement to City Advances therefor), the City shall return such
Excess to the Successor Agency within a reasonable time.
Section 7. The City shall maintain records of all of the advances made by the City for
the Work Costs and all of the receipts of repayments made by the Successor Agency pursuant to
this Agreement. Such records shall be available for inspection by the Successor Agency at all
reasonable times.
Section 8. The Successor Agency's obligation to pay for all Work Costs incurred
(including the reimbursement to the City for all City Advances) under this Agreement shall
survive the Successor Agency's disposition of the Property and shall terminate only when the
payment of all Work Costs incurred (including the reimbursement to the City for all City
Advances) has been made in full by the Successor Agency.
Section 9. The Parties agree to take all appropriate steps and execute any documents
which may reasonably be necessary or convenient to implement the intent of this Agreement.
Section 10. This Agreement may be amended at any time, and from time to time, by
an agreement executed by both parties to this Agreement in writing.
Section 11. If any provision of this Agreement or application thereof to any person or
circumstance is held invalid, such invalidity shall not affect other provisions or applications of
this Agreement which can be given effect without the invalid provision or application, and to this
end the provisions of this Agreement are severable.
Section 12. No official, agent, or employee of the Successor Agency or the City, or
members of the City Council, or members of the Successor Agency Board of Directors or
Oversight Board shall be individually or personally liable for any payment hereunder in the event
of any default or breach by the Parties, or for any amount which may otherwise become due
under the terms of this Agreement.
Section 13. This Agreement is made in the State of California under the Constitution
and laws of the State of California, and is to be so construed.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK:
SIGNATURES TO FOLLOW}
-4-
128I2.0001\176411.2
RESOLUTION NO. OB-101 CONTRACT NO. C33990
IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by
their duly authorized officers.
SUCCESSOR AGENCY TO THE PALM
DESERT REDEVELOPMENT AGENCY
By
Attest:
Secretary
Executive Director
CITY OF PALM DESERT
By
Mayor
Attest:
City Clerk
APPROVED:
OVERSIGHT BOARD OF THE
SUCCESSOR AGENCY TO THE PALM
DESERT REDEVELOPMENT AGENCY
By Date:
Chair
-5-
12812.0001\176411.2