HomeMy WebLinkAbout2006-08-07MINUTES
REGULAR MEETING
RIVERSIDE COUNTY PALM DESERT FINANCING AUTHORITY
MONDAY, AUGUST 7, 2006 — 10:00 A.M.
NORTH WING CONFERENCE ROOM - PALM DESERT CIVIC CENTER
73-510 FRED WARING DRIVE, PALM DESERT, CALIFORNIA 92260
I. CALL TO ORDER
Commissioner Ortega convened the meeting at 10:02 a.m.
II. ROLL CALL
Present: Excused Absences:
Commissioner Carlos L. Ortega Commissioner Larry Parrish
Vice President S. Roy Wilson President Jim Ferguson
Acting President Richard S. Kelly
Also Present:
Paul S. Gibson, Authority Treasurer
Homer Croy, ACM for Development Services
Justin McCarthy, ACM for Redevelopment
Patrick Conlon, Director of the Office of Energy Management
Rachelle D. Klassen, Authority Secretary/City Clerk
III. ORAL COMMUNICATIONS
None
IV. CONSENT CALENDAR
A. MINUTES of the Adjourned Regular Riverside County Palm Desert Financing
Authority Meeting of July 10, 2006.
Rec: Approve as presented.
Upon a motion by Kelly, second by Wilson, and 3-0 vote of the Authority
Commission Board, with Parrish ABSENT, the Consent Calendar was approved as
presented.
V. CONSENT ITEMS HELD OVER
None
VI. NEW BUSINESS
None
MINUTES
REGULAR MEETING OF THE
RIVERSIDE COUNTY PALM DESERT
FINANCING AUTHORITY
VII. CONTINUED BUSINESS
AUGUST 7, 2006
A. REQUEST FOR ACCEPTANCE OF WORK FOR CONSTRUCTION OF THE
COACHELLA VALLEY ANIMAL CAMPUS (CONTRACT
NO. RCPDFA 22130) (Continued from the meetings of March 13, and
July 10, 2006).
Mr. Conlon said the minor items that came up at the last meeting had been
corrected. He further offered that he had a copy of the air balance report
and would be delivering it to the Shelter to Doug Austin's attention. Once the
Notice of Completion is filed, he and Commissioner Ortega would meet with
the contractor to work out the remaining items, including liquidated damages,
and the project would be considered complete.
Vice President Wilson commented that County staff had serious concerns
with improper exit lighting; the architect (WLC) brought it to their attention
that about eight lighted "Exit" signs were not properly placed. It was his
understanding that the contractor was aware but has yet to do anything
about it.
Mr. Conlon responded that staff consulted the plans, and the "Exit" signs
installed by the contractor were done per the plan. He acknowledged that
the architect had previously requested some changes, which he proposed
be done after the subject contract was closed. In further response to
question, he said part of the issue with the "Exit" signs was their being
hardwired into junction boxes in the masonry walls of the structure; for this
reason, it was difficult to change the signs. He noted that both the Fire
Department and County Building & Safety Department signed off on the
project as is; but if there were some "Exit" signs that needed to be changed
or revised, it can be done later. At this point, he said it would be undesirable
to do another Change Order with Wang Milestone Construction.
Commissioner Ortega acknowledged that the County operators of the facility
had several issues, one being the air conditioning and air exchanges/hour,
but he didn't think there was anything else prohibiting the Authority
Commission Board from issuing a Notice of Completion based on the
contractor's compliance with the contract documents and specifications.
Mr. Conlon reiterated that the existing "Exit" signs were installed exactly per
the plans. If necessary, he recommended using a separate contractor to
relocate the signs and offered to assist with the process. In response to
question about claims from subcontractors, he said there were some stop
notices that the contractor had posted bonds to cover. The contractor
2
MINUTES
REGULAR MEETING OF THE
RIVERSIDE COUNTY PALM DESERT
FINANCING AUTHORITY
AUGUST 7, 2006
provided assurance that once the retention funds were released, he would
pay the subcontractors with those funds.
Acting President Kelly moved to, by Minute Motion, accept the project as complete
and authorize the President to sign and the Secretary to file the Notice of Completion with
the Riverside County Recorder's Office. Motion was seconded by Ortega and carried by
a 2-0-1 vote, with Vice President Wilson ABSTAINING due to his concerns about the exit
lighting and Commissioner Parrish ABSENT.
Commissioner Ortega expressed appreciation to Mr. Conlon for the efforts
he expended on this project, which had taken much more time than initially
anticipated.
VIII. OLD BUSINESS
None
XI. REPORTS AND REMARKS
A. PRESIDENT
Responding to Acting President Kelly's question, it was noted that the project
list was still being finalized by the County, particularly the Sheriffs Station.
Vice President Wilson felt the County needed to be closer with actual
designs for the proposed projects before a bond issue could be considered.
He hoped some of the County's pass -through funds with the City could be
utilized to obtain the necessary designs and plans in the meantime,
anticipating that they would be ready for the bond issue in approximately one
year.
Mr. Gibson said it would be necessary for the County to take an action to
authorize the Financing Authority to utilize the pass -through funds for the
aforementioned purposes.
In further response to question, Vice President Wilson said he hoped the
community parks proposed for Bermuda Dunes and the East Valley would
get priority. Acting President Kelly emphasized the need for such parks.
B. VICE PRESIDENT
Vice President Wilson commented that Riverside County would be joining
the Energy Coalition project and would also be collaborating specifically with
the Cities of Palm Desert, Cathedral City, Moreno Valley, and Corona to
3
MINUTES
REGULAR MEETING OF THE
RIVERSIDE COUNTY PALM DESERT
FINANCING AUTHORITY
AUGUST 7, 2006
develop a plan for energy conservation incentives, particularly in the
County's Fourth and Fifth Districts and for the low and moderate income
housing stock.
C. MEMBERS OF THE AUTHORITY
None
D. STAFF
None
X. ADJOURNMENT
With Authority Commission Board concurrence, the meeting was adjourned at
10:36 a.m.
RICHARD S. KaLY, ACTING PR .IDENT
ATTEST:
R • CHEL E D. KLASSE ', SECRETARY
RIVERSIDE COUNTY PALM DESERT
FINANCING AUTHORITY
4