HomeMy WebLinkAboutC22360 CO1 Hort Tech - Portola Avenue & Hovley Lane 915-04REQUEST: SUBMITTED BY: APPLICANT: DATE: CONTENTS: CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT Approve Change Order #1 to C22360, Landscape Installation on Portola Avenue and the Hovely Lane East Median Island H. Spencer Knight, Landscape Manager Hort Tech Landscape, Inc. 80420 Avenue 50 La Quinta, CA 92253 August 26, 2004 Change Order No. 1 Recommendation: By Minute Motion; 1. Allocate from un-obligated funds $11,183.22 from account 400- 4614-453-40.01. 2. Approve Change Order #1 with Hort Tech Landscape, Inc., La Quinta CA) in the amount of $11,183.22 including contingency for the Landscape Installation on Portola Avenue and the Hovely Lane East Median Island Projects (Project 915-04). Discussion: The landscapes on several private properties were within the construction area of Capital Improvement Project 630-99, Widening of Portola Avenue Northbound from San Marino Circle to El Cortez. These properties are located on the west side of Portola between Alessandro and El Cortez. The landscapes on these properties were impacted by the construction process and required replacement. On June 10, 2004, City Council awarded Contract No.C22360 to Hort Tech Landscape, Inc. for Capitol Improvement Project 915-04, Landscape Installation on Portola Avenue and the Hovely Lane East Median Island Project, in the amount of $103,515.00. The G:\PubWorks\Staff Reports\2004\August 26\Change Order No. 1 Hort Tech.doc Staff Report — Change Order No. 1 to Contract No. C22380 Page 2of2 August 26, 2004 scope of this project did not include the above -mentioned properties. Since Hort Tech was on site; their services were used to replace the needed landscapes. Funds are currently available in account 400-4614-453-40.01. Therefore, the staff recommends that City Council approve Change Order #1 to Contract No. C22360 for $11,183.22 Submitted By: H Sp nc. K ig t Lape Manager Approval: AC for Deve o•.112a, t Services City Manager /jI Department Head: Michael Errante, P.E. Director of Public Works Director of Finance G:\PubWorks\Staff Reports120041August 261Change Order No. 1 Hort Tech.doc CITY OF PALM DESERT CONSTRUCTION CHANGE ORDER Project Description: Contractor Name Street Address City, State, Zip P.O. # Contract # C22360 Landscape Installation/Portola Ave. & the Project # 915-04 Hovley Lane East Median Island Hort Tech, Inc. P.O. Box 3284 Palm Desert, CA 92261-3284 Contractor Jack Kerns Vendor # 5799 Contract Change Order # 1 Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract. DESCRIPTION OF CHANGE Installed additional landscaping not with in scope of contract but requested by staff. Contingency used? (circle one) If yes, amount moved to base: Yes No Increase/Decrease in Amount $11,183.22 Contract Amount (include past change orders) $ 103,515.00 Plus/Minus Current Change Order $ 11,183.22 Revised Total Contract Amount $114,698.22 1. ORDERED BY: H. Spencer Knight Department Head 3. APPROVED BY: City Manager Date Increase/Decrease in Days Contract Date of Completion Plus/Minus Current Change Order Revised Date of Completion 2. CERTIFIED FUNDS AVAILABLE Director of Finance 4. APPROVED BY: Date City Council Date We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses fort any delays. ACCEPTED BY: ContractorNendor Date