CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
Approve Change Order #1 to C22360, Landscape Installation on
Portola Avenue and the Hovely Lane East Median Island
H. Spencer Knight, Landscape Manager
Hort Tech Landscape, Inc.
80420 Avenue 50
La Quinta, CA 92253
August 26, 2004
Change Order No. 1
Recommendation:
By Minute Motion;
1. Allocate from un-obligated funds $11,183.22 from account 400-
4614-453-40.01.
2. Approve Change Order #1 with Hort Tech Landscape, Inc., La
Quinta CA) in the amount of $11,183.22 including contingency
for the Landscape Installation on Portola Avenue and the
Hovely Lane East Median Island Projects (Project 915-04).
Discussion:
The landscapes on several private properties were within the construction area of
Capital Improvement Project 630-99, Widening of Portola Avenue Northbound from San
Marino Circle to El Cortez. These properties are located on the west side of Portola
between Alessandro and El Cortez. The landscapes on these properties were impacted
by the construction process and required replacement.
On June 10, 2004, City Council awarded Contract No.C22360 to Hort Tech Landscape,
Inc. for Capitol Improvement Project 915-04, Landscape Installation on Portola Avenue
and the Hovely Lane East Median Island Project, in the amount of $103,515.00. The
G:\PubWorks\Staff Reports\2004\August 26\Change Order No. 1 Hort Tech.doc
Staff Report — Change Order No. 1 to Contract No. C22380
Page 2of2
August 26, 2004
scope of this project did not include the above -mentioned properties. Since Hort Tech
was on site; their services were used to replace the needed landscapes.
Funds are currently available in account 400-4614-453-40.01.
Therefore, the staff recommends that City Council approve Change Order #1 to
Contract No. C22360 for $11,183.22
Submitted By:
H Sp nc. K ig t
Lape Manager
Approval:
AC for Deve o•.112a, t Services
City Manager
/jI
Department Head:
Michael Errante, P.E.
Director of Public Works
Director of Finance
G:\PubWorks\Staff Reports120041August 261Change Order No. 1 Hort Tech.doc
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Project Description:
Contractor Name
Street Address
City, State, Zip
P.O. #
Contract # C22360
Landscape Installation/Portola Ave. & the Project # 915-04
Hovley Lane East Median Island
Hort Tech, Inc.
P.O. Box 3284
Palm Desert, CA 92261-3284
Contractor Jack Kerns
Vendor # 5799
Contract Change Order # 1
Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract. Unless
otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract.
DESCRIPTION OF CHANGE
Installed additional landscaping not with in scope of contract but requested by staff.
Contingency used? (circle one)
If yes, amount moved to base:
Yes No
Increase/Decrease in Amount
$11,183.22
Contract Amount (include past change orders)
$ 103,515.00
Plus/Minus Current Change Order
$ 11,183.22
Revised Total Contract Amount
$114,698.22
1. ORDERED BY: H. Spencer Knight
Department Head
3. APPROVED BY:
City Manager
Date
Increase/Decrease in Days
Contract Date of Completion
Plus/Minus Current Change Order
Revised Date of Completion
2. CERTIFIED FUNDS AVAILABLE
Director of Finance
4. APPROVED BY:
Date
City Council
Date
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we
will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified
work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses fort any delays.
ACCEPTED BY: