HomeMy WebLinkAboutC22100A CO1 - Coachella Valley Construction Services - Aztec Road 602-02REQUEST: SUBMITTED BY: APPLICANT: DATE: CONTENTS: CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT Ratify Change Order No. 1 to Contract No. C22100A for the Construction Management of Aztec Road (Project 602-02) Mark Greenwood, P.E., City Engineer Coachella Valley Construction Services P.O. Box 2882 Indio, California 92202 August 26, 2004 Change Order No. 1 Interoffice Memorandum Vicinity Map Recommendation: By Minute Motion, ratify Change Order No. 1 to Contract No. 22100(A) with Coachella Valley Construction Services, in the amount of $17,000. Discussion: One June 10, 2004, City Council awarded Contract No. C 22100(A) to Coachella Valley Construction Services (CVCS), in the amount of $35,000, for the Construction Management of Aztec Road (Project 602-02). During the construction process of Aztec Road, unforeseen conflicts were discovered with existing utilities. It was necessary to mitigate these conflicts in the field, resulting in additional hours being required of the construction manager. Currently CVCS is currently under contract to work twenty-four hours per week. Due to the complexity of the construction environment Public Works staff has determined that the project requires forty hours per week of on -site construction management. Funds are available for this in project account 213-4623-433-4001. G:\PubWorks\PROJECTS\602-02\Staff Reports\STAFF REPORT -CO to CVCS Contract.dot Staff Report -Ratify Change Order No. 1 to Contract C22100A Page 2 of 2 August 26, 2004 The project is approximately eighty-five percent complete. As the job complexity changes and the percent complete increases CVCS will be scaled back down to twenty-four hours per week. The additional cost for these services will be $17,000. Therefore, staff recommends that City Council by minute motion, ratify Change Order No. 1 to Contract No. C22100A, with Coachella Valley Construction Services, in the amount of $17,000.00. Submid,By Mark Gree ood, P. City Engineer Approval: ACM for Develo -,1, Services lcIs Department Head: Michael Errante, P.E. Director of Public Works Finance Director G:1PubWorks\PROJECTS1602-021Staf ReportsISTAFF REPORT -CO to CVCS Confract.dot CITY OF PALM DESERT CONSTRUCTION CHANGE ORDER Project Description: Contractor Name Street Address City, State, Zip Aztec Road at Palm Desert High School Coachella Valley Construction Services P.O. Box 2882 Indio, California 92202 Contractor Vendor # Contract Change Order # 1 P.O. # 11502 Contract # C22100A Project # 602-02 Granite Construction 7672 Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract. DESCRIPTION OF CHANGE Additional hours required on site Contingency used? (circle one) If yes, amount moved to base: Yes No Increase/Decrease in Amount $17,000.00 Contract Amount (include past change orders) $35,000.00 Plus/Minus Current Change Order $17,000.00 Revised Total Contract Amount $52,000.00 1. ORDERED BY: Department Head 3. APPROVED BY: City Manager Date Increase/Decrease in Days Contract Date of Completion Plus/Minus Current Change Order Revised Date of Completion 2. CERTIFIED FUNDS AVAILABLE Director of Finance 4. APPROVED BY: Date City Council Date We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses fort any delays. ACCEPTED BY: ContractorNe Date CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT INTEROFFICE MEMORANDUM To: Carlos L. Ortega, City Manager From: Ryan Gayler, Management Analyst Date: July 30, 2004 Subject: CHANGE ORDER FOR AZTEC ROAD PROJECT (P602-02) Coachella Valley Construction Services has been providing construction management services on the Aztec Road project. They are currently under contract to manage the project twenty-four hours per week. Due to the complexity of the project at this stage, Public Works has determined that the project requires on -site management at a rate of forty hours per week. This increased level of service will be required until the project is approximately eighty-five percent complete. As the job winds down, CVCS will be scaled back down to twenty-four hours per week. The increased cost to the contract for the additional services will be $17,000. Please approve change order #1 to Coachella Valley Construction Services. Public Works will bring this request before Council on the meeting of August 26th for ratification. Rya 'Gayler Management'AYialyst Reviewed and Concur: Carlos L. Ortega City Manager Michael Errante Director of Public Works cc: Homer Croy, ACM for Development Services Paul S. Gibson, Director of Finance G:\PubWorkslRyan Gayler\Word Files\co#1 for CVCS-Aztec Road.doc Page 1 of 1 1 I ..1 I :1 k - • ,44L..nyL___Av 4.. 0 rg____Hr --' I - High School Acces Road Aztec Road — --I :r--7i- 1 '. ! --- i: <• .alti).Desert High :.$g13991:-.--;..„-_,,.,..,:-:,_ iiin •,-EL;:._--..• 7.7::: -.:,,,!•,,(-:..•.•::,::•J;',17-..:.;:. . . -..: ..,': •?,Y.-14,77::::Yli!'•-•V:-;:, ....'.1..::`. III .'1..-.'•• ..f.....1;;:, ..... tn.f',5 , r:". -.,- C7'; --' 1--- 7 ktaLiT151--72#1-L)- i---S , {----7 Ti i ,.. L.:it n i= • ..__, •'. ,1 '.--1---:---t '.7:H:2;:::;.; s "1"--i -•2' C7: i , 5:• v), ,-., IYA-Pittcyz:-.; ----,...--,-- .4-- - 1 \•.':•:1----1 .1d 11'.• 1," -1\..1- --' - FRFD 'WA RI-N-G—D-R • , • . • ; 0:08 (0.1 14Z..ali;1 • 'LLL_ indian Wells