REQUEST: Approve Change Order #2 to C20210
SUBMITTED BY: Mark Greenwood, P.E., City Engineer
APPLICANT: PSOMAS
11444 West Olympic Boulevard
Los Angeles, California 90064
DATE: July 8, 2004
CONTENTS: Change Order No. 2
Vicinity Map
Recommendation:
By Minute Motion;
Approve Change Order #2 with Psomas (Los Angeles, CA) in the
amount of $19,500 including contingency for the Highway 111 at
Desert Crossings project (Project 615-02).
Discussion:
On June 13, 2002, City Council awarded the engineering contract for the design of the
Desert Crossing Intersection Improvements to Psomas for the amount of $79,102.00,
with a 10% contingency in the amount of $7,910.20. On April 10, 2003, Change Order
#1 was approved in the amount of $11,000.00. This change order addresses the need
for additional title, appraisal, and acquisition services in conjunction with the right-of-way
necessary to complete the improvements.
Change Order #2 to the Psomas Engineering contract will enable the engineers to
modify the existing design plans for better traffic circulation on Highway 111.
Modifications will include an extension of the left turn lanes on Northbound Highway 111
to allow greater stacking, and to accommodate more traffic entering Desert Crossings
shopping center. Also, a dedicated right turn pocket into the Toys "R" Us parking lot will
be added on Northbound Highway 111 at the same intersection. This will decrease the
Staff Report —
Change Order No. 2 to Contract No. C20210
Page 2 of 2
July 8, 2004
hindrance for through traffic on Highway 111 and improve overall circulation at the
intersection.
These changes need to be made within this fiscal year to allow proper time for
advertisement and the bidding process to occur in support of a May 2005 construction
schedule.
Funds are currently available in the Measure "A" project account: 213-4347-433-4001.
Therefore, the staff recommends that City Council approve Change Order #2 to
Contract No. C20210 for $19,500.
City Engineer
Approval:
ACM for De - = • en t Services
City Manager
Icls
Department Head:
Michael Errante, P.E.
Director of Public Works
irect of Finance
G:\PubWorks\PROJECTS\615-02\Staff Reports\Change Order No. 2.doc
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
P.O. # 9681
Contract # C20210
Intersection Improvements Highway 111 at Project # 615-02
Project Description: Desert Crossings
Contractor Name Psomas
Street Address
City, State, Zip
11444 West Olympic Boulevard.
Los Angeles, California 90064
Contractor
Vendor # 6983
Contract Change Order # 2
Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract. Unless
otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract.
DESCRIPTION OF CHANGE
Revise approved street improvement plans based upon City's comments, revise approved traffic improvement
plans based upon City's comments, reestablish survey control, obtain additional survey
Contingency used? (circle one)
If yes, amount moved to base:
Yes No
Increase/Decrease in Amount
19,500.00
Contract Amount (include past change orders)
90,102.00
Plus/Minus Current Change Order
19,500.00
Revised Total Contract Amount
$109,602.00
1. ORDERED BY:
Department Head
3. APPROVED BY:
City Manager
Date
Increase/Decrease in Days
Contract Date of Completion
Plus/Minus Current Change Order
Revised Date of Completion
2. CERTIFIED FUNDS AVAILABLE
Director of Finance
4. APPROVED BY:
Date
City Council
Date
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we
will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified
work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses fort any delays.
ACCEPTED BY:
ContractorNendor
Date