May 19, 2004
Re: Southern California Edison Company Rate
Application; A.04-04-005
To Whom It May Concern:
On April 1, 2004, Southern California Edison Company filed an application for
a rate increase with the California Public Utilities Commission. The substance of the
application is described in the enclosed notice that was included as a bill insert to
Edison's customers. If you wish to comment on, or obtain additional information
concerning this matter, or wish a copy of the application and attachments, please
write either to the Commission Public Advisor or to the Edison Consumer Affairs
Department no later than June 15, 2004 at the address in the enclosed notice.
RBK smb: LW 041030007.doc
Enclosure(s)
P.O. Box 800
Robert B. Keeler
Senior Attorney
COPY TQ
DATE --�
IV 0r:;
.- rt
A rt7 _
c/)
C.,) > VD f?
2244 Walnut Grove Ave. Rosemead, California 91770 (626) 302-4563 Fax (626) 302-1935
THE CPUC WELCOMES YOUR
PARTICIPATION AND COMMENTS
The CPUC will issue its decision after evidentiary hearings on SCE's request.
At the hearings, SCE representatives, interested parties, and the CPUC's staff
will present testimony. The CPUC staff, engineers, accountants, economists,
attorneys and other professionals independently evaluate utility rate increase
proposals and present their analyses and recommendations to the CPUC at
evidentiary hearings. The rates approved may differ from those SCE requests.
If you need advice on how to participate or wish to make comments to the
CPUC, please write to:
The Public Advisor
California Public Utilities Commission
320 West Fourth Street, Suite 500
Los Angeles, CA 90013
Public.advisoda@cDuc.ca.gov
Please state in your letter that you would like a response; otherwise, no reply
will be sent. The Public Advisor will give your letter to the Commissioners and
it will become part of the formal file. Please mention Application No. 04-04-005.
If you have questions or need further information about this matter, or a copy
of the application and attachments, please write to:
Southern California Edison
Consumer Affairs
P.O. Box 800, Quad 1-D
2244 Walnut Grove Avenue
Rosemead. CA 91770
Para solicitar una copia de esta notificacidn en espanoi por favor escriba a
Southern Califomia Edison
Corporate Communications
2244 Walnut Grove Avenue, Quad 4A
Rosemead, CA 91770
o por medio de correo electrOnico
a Jo.Piantedosi@sce.com
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Edison )
Company (U 338-E) for Authorized Capital )
Structure, Rate of Return on Common
Equity, Embedded Cost of Debt and
Preferred Stock, and Overall Rate of )
Return for Utility Operations for 2005. )
NOTICE
A.04-05-021
On May 10, 2004, Southern California Edison Company (SCE) filed
Application 04-05-021 with the California Public Utilities Commission requesting
an authorized cost of capital for 2005. SCE's request, if approved by the
Commission would result in a $28.2 million, or 0.3 percent decrease to SCE's
authorized revenues. The authorized cost of capital determines how much money
SCE is allowed in rates as a return on its invested capital. In this proceeding the
Commission will determine what is a reasonable capital structure and costs of long-
term debt, common equity, and preferred stock for SCE. SCE's request is shown in
the following table.
Percentage of
Component Capital
Long -Term Debt 43.00%
Preferred Stock 9.0%
Common Equity 4g.00%
Total 100.00%
Cost
6.97%
7.01%
11.60%
Weighted Cost
3.00%
0.63%
5.57%
9.20%
SCE's requested cost of capital will fairly compensate those who invest in
SCE and permit SCE to attract capital to meet its obligations to serve its customers.
It will also allow SCE to mitigate the financial effects in 2005 of power purchase
contracts.
SCE is proposing that revenue change resulting from this application be
consolidated with revenue changes from other SCE applications. If the Commission
-1-
were to allocate the revenue change SCE is proposing in this application on a
system average percent basis, the impact by customer group would be as shown
below.
Revenue Change
Customer Group ($ Million) % Change
Domestic (Residential) (8.7) -0.27%
Lighting - Small and
Medium Power (11.9) -0.36%
Large Power (6.6) -0.41%
Agriculture and Pumping (0.9) -0.35%
Street and Area Lighting (0.1) -0.17%
TOTAL (28.2) -0.30%
If the Commission were to change SCE's rates as shown above, an average
residential electric customer using 550 kilowatt-hours per mont in the summer
would see a decrease of $0.20 per month, from $67.90 to $67.70.
The Commission may schedule evidentiary hearings on SCE's request, during
which SCE representatives, interested parties, and the Commission's staff may
present testimony. The Commission staff, engineers, accountants, economists,
attorneys and other professionals independently evaluate utility rate increase
proposals and present their analyses and recommendations to the Commission at
evidentiary hearings. The rates approved by the Commission may differ from those
SCE requests
If you need advice on how to participate or wish to make comments to the
Commission, please write to:
The Public Advisor
California Public Utilities Commission
320 West Fourth Street, Suite 500
Los Angeles, CA 90013
public.advisor.la@cpuc.ca.gov
Please state in your letter if you would like a response; otherwise, no reply
will be sent. The Public Advisor will give your letter to the Commissioners and it
-2-
will become part of the formal file. Please mention Application No. 04-05-021 in
your correspondence.
If you have questions or need further information about this matter, or a copy
of the application and attachments, please write to:
Southern California Edison Company
P.O. Box 800
2244 Walnut Grove Avenue
Rosemead, CA 91770
Attention: Mark R. Bliss
A copy of the application will be mailed upon request.