HomeMy WebLinkAboutRatify C20580D1 CO3 Commercial Diversified Fire Station No. 67 RenovationContract No. C2058(
CITY OF PALM DESERT
CITY MANAGER
STAFF REPORT
REQUEST: RATIFY CITY MANAGER'S APPROVAL OF CHANGE ORDER NO. 3 IN
THE AMOUNT OF $2,466.24 TO COMMERCIAL DIVERSIFIED, INC.
(TWENTYNINE PALMS, CA), FOR VARIOUS CONSTRUCTION
MODIFICATIONS ASSOCIATED WITH THE FIRE STATION NO. 67
RENOVATION PROJECT.
SUBMITTED BY: Stephen Y. Aryan, Assistant to the City Manager
DATE: December 8, 2005
CONTRACTOR: Commercial Diversified, Inc.
72033 29 Palms Highway
Twentynine Palms, CA 92277
ATTACHMENTS: 1. Contract Change Order No. 3
2. Background Material
RECOMMENDATION
By Minute Motion:
Ratify City Manager's Approval of Change Order No. 3 in the amount of $2,466.24 to
Commercial Diversified, Inc. (Twentynine Palms, CA), for various construction
modifications associated with the Fire Station No. 67 Renovation Project.
BACKGROUND
On March 10, 2005, the City Council awarded the Mesa View Fire Station Renovation Project to
Commercial Diversified, Inc. (Twentynine Palms, CA) in the amount of $1,395,000, plus a 10%
contingency. Please note that the Council previously ratified Change Order No. 1 & 2 for a
combined total of $9,275.81.
Change Order Number 3 is in the amount of $2,466.24. This change order is to accommodate
several modifications and a credit as follows:
Additional TV cable extensions to remove cables from roof and extend to the
dorms (option #2-no conduit)
Additional seismic work needed at the roof area of the Training Room. The
added hold-downs are needed because they were missing from the original
construction.
Raising the existing ducts above the Kitchen ceiling in order to install the new
recessed lights.
Hand chipping concrete for kitchen sink alternate tie-in
Rerouting the waste line to the Kitchen sink (CREDIT)
TOTAL
$1,164.95
$1,438.00
$208.73
$55.06
($400.50)
$2,466.24
G CityMgnStepnen AryankWord Data\Mesa View FS Change Order 3 ooc Page 1 of 2
Change Order No, 3 (Contract #C-20580-D1)
City Council Staff Report
October 27, 2005
Prepared by: Reviewed
Stephen Y. Aryan
Assitant to the City Manager
Approved by:
14a
Carlos L. Ortega
City Manager
k�5
Paul/.1ibsonDireca ce Ct�y_
Treasurer
G �CdyMg6Stephen AryamWord DaWMesa View FS Change Order 3.doc Page 2 of 2
CONSTRUCTION CHANGE ORDER
P.O.# 012324
Contract # C-20580-D 1
Project #
Project Description: Mesa View Fire Station No. 67 Remodel
Contractor Name Commercial Diversified, Inc. Contractor
Street Address 72033 29 Palms Highway Vendor # 8590
City, State, Zip Twentynine Palms, CA 92277
Contract Change Order # 3
Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract. Unless
otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract.
_DESCRIPTION OF CHANGE
Multiple Items Requested: 1) Additional TV cable extensions; 2) Additional seismic work needed at the roof area
of the Training Room; 3) Raising the existing ducts above the Kitchen; 4) Hand chipping concrete for kitchen sink
alternate tie-in. Please note that this change order also reflects a credit for Rerouting the waste line to the Kitchen
sink.
Contingency used? (circle one) I Yes No Increase/Decrease in Amount $
If yes, amount moved to base: 1 $2, 466.24 Increase/Decrease in Days
Contract Amount (include past change orders) $1,404,275.81 I Contract Date of Completion
Plus/Minus Current Change Order $2,466.24 Plus/Minus Current Change Order
Revised Total Contract Amount $1,406,742.05 Revised Date of Completion
1. ORDERED BY: Stephen Y. Aryan
//-.21- 05
Assistant to the City vor
Date
3. APPROVED BY:
City Manager
Date
2. CERTIFI UN AVAILABLE
Directockf(Finan&— Date
4. APPROVED BY:
City Council Date
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we
will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified
work, and hereby accept as full payment the amount shown above, Which includes all direct and indirect overhead expenses fort any delays.
ACCEPTED BY:
Contractor/Vendor Date
Commercial Diversified
INC.
.... I . . 03 November 2005
Attn: Frank Urrutia
Urrutia Architects
166 Luring Drive
Palm Springs, CA 92262
Re. Addition and Remodel Mesa View Fire Station
# 67
CER Additional Cable Drops
SCOPE: '
Additional Cable Drops
Option 1: Encased in Conduit
1. C&S Proposal, see attached
3089.00
Sub Total
3089.00
15%
Mark Up
463.35
Total
3552.35
Option 2: Not Encased In Conduit
1. C&S Proposal, see attached
1013.00
'
Sub Total
1013.00
15%
Mark Up
151.95
Total
1164.95
Per the General Conditions of the Agreement,
the Contractor requests an
executed Change Order for the above referenced additional work.
Respectfully,
�..
�
Richard A. Cobalis
President
r
Commercial Diversified, Inc,
72033 29 Palms HWY, Twentynine Palms, CA 92277
Tel: (760) 367-6104 Fax: (760) 367-6860
License: 518140
info@commercialdiversified.com
http:ltwww.com merclaldiversified. com
NOV-04-2005 FRI 02:37 PM COMMERCIAL DIVERSIFIED FAX NO, 7603676860 P. 01
C & S Electric
7379 Hopi Trail, Yucca V, atley, Ca. 92284
Pit (760) 365-63831,AX (760) 365-6385
Co. lie. C10-399096
Entail cse1gp-1c2,C g - ria,
To: Colzirnceaial Divorsified, Lic.
Soil- !Musa View Fire Station, I'll", I)csc) t
I11d Date: 10/21/05 .
In: all 3-TV outlets, one in each dorm.
1. TV outlets in conduit. - $ 3,089.00
2. 'rV outjt�ts 11,11 as open wiring- $ 1,013.00
• i �31�
x
1'.1/4/2005 2.27 PM
L a ,
Page 1 of 2
Aryan, Steve
From: Frank [frank@urrutiaarchitects.com]
Sent: Thursday, November 03, 2005 4:08 PM
To: 'Commercial Diversified, Inc'
Cc: Aryan, Steve; knappae@aol.com
Subject: CER #9
E-Mail Transmittal
Date: JiNovember 3, 2005
To:
Commercial Diversified
From:
Urrutia Architects
Francisco J. Urrutia, AIA/FARA
Project #: 11 0326.00
Project Name:
Mesa View FS
Ronda: I have reviewed the enclosed CER #9 and need you to confirm the
following is included in the CER.
Remarks:
The intent is for Detail 3/S5.1 to apply to 4 (four) points in the shear walls
where the 4 x 4 wood posts are supposed to be located. This also applies to
the foundation where the posts meet the concrete. At this point we should
have 4 HD 2 hold-downs in place. If they are not there, they will need to be
installed per detail 3/S3.0. In the end we need all four posts to have hold-
down connections per detail 3/S5.1 to carry the shear down from the roof to
the foundation. Please confirm that the proposal sent to me will address this
intent.
Standard
Disclaimer For
Electronic
The electronic data contained in this media is fie copyright of Urrutia Architects and is provided by Urrutia
Media
Architects as an aid to the recipient. The data is believed to be accurate but the recipient is responsible for
taking necessary steps to confirm its accuracy. Unless stated otherwise, Urrutia Architects is not responsible
for any error or omissions, known or unknown that may arise by use of this electronic file. Any alternations to,
and use of this electronic data isat the sole risk of the recipient. It should be noted that the following digital
rile was prepared for the sole purpose of preparing construction drawings by Urrutia Architects. This
Information shall not be used for any other purpose, any other project provided to any other party
without the express permission o/ Urrutia Architects. Any questions regarding the data that may arise
shall be addressed to Urrutia Architects.
11 /22/2005
COMMERCIAL DIVERSIFIED, INC.
72033 Twentynine Palms Hwy.
Twentynine Palms, CA 92277
Tel: (760) 367-6104 Fax: (760) 367-6860
License 5181°40 -- "
Email: comdlvinc@adelphia.net
TRANSMITTAL SHEET
TO: FROM:
Frank Urrutia Richard Cobalis
COMPANY: DATE;
Urrutia Architects 11/4/2005
FAX NUMBER: TOTAL NO. OF PAGES INCLUDING COVER:
327.6813 ' 1
PHONE NUMBER: CC:
327.6800
RE: YOUR REFERENCE:
Sheet S5 Detail 3 Mesa View Fire Station
Verification of HD2 - REVISED
LI URGENT m FOR REVIEW ❑ PLEASE COMMENT ❑ PLEASE REPLY ❑ PREVAILING WAGE
NOTESICOMMENTS:
Mr. Urrutia,
The following revisions have been made to our proposal in order to comply with the direction
in your correspondence.
Cost for these repairs would be:
Material (not Itemized) $150.00
Epoxy Inspections $255.00 $85,00 ea.
Labor, 24 MH $846.00
Sub Total $1251.00
15% Mark Up 1$ 87.00
Total $1438.00
t..
r�
r
. 3
CHANGE ESTIMATE
PROJECT: Mesa View Fire Station
Palm Desert, CA.
OWNER: City of Palm Desert
TO CONTRACTOR:
Commercial Diversified, Inc.
OWNER
® ,
ARCHITECT
CONSULTANT
❑
CONTRACTOR
FIELD
❑
OSHPD
❑
CHANGE ESTIMATE REQUEST NO.: 8
DATE OF ISSUANCE: October 20, 2005
CONTRACT FOR: Mesa View Fire Station
Addition and Remodel
CONTRACT DATED: C2058Di
,
ARCHITECT'S PROJECT NO.: 0326.00
ARCHITECT: Urrutla Architects
OSHPD NO.:
Please submit an Itemized proposal for changes in the Contract Sum and Contract Time for proposed
modifications to the Contract Documents described herein. Submit proposal within 10 days, or notify the
Architect In writing of the date on which you anticipate submitting your proposal,
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH
THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
Description:
1. The existing ceiling and ductwork In the Corridor and Dining area are to low to be able to accept
.the light fixtures specified. A different light fixture was specified which was shallower and would
fit, however, they have a 6-8 week lead time to obtain them. As an alternative, the ductwork will
be raised to allow for the specified lights to be Installed. Provide a cost to raise the a/c ductwork.
x•
10/20/05
t.
I
Attachments:
None.
REQUESTED BY URRUTIA ARCHITECTS:
---------------
(Signature)
Francisco 1. Urrutla. President
(Printed name and title)
t `
t MCI=
Commercial Diversified
INC.
03 November 2005
Attn: Frank Urrutia
Urrutia Architects
165 Luring Drive ;
Palm Springs, CA 92262
Re. Addition and Remodel Mesa View Fire Station # 67
CER #8 Raise the Existing Ductwork
SCOPE: '
Raise the existing a/c ductwork Corridor/DR
Labor Material
Labor 6 HR 181.50
Sub Total 181.50
16% Mark Up 27.23
Total 208.73
Per the General Conditions of the Agreement, the Contractor requests an
executed Change Order for the above referenced additional work.
Respectfully,
Richard A. Cobalis
President
Commercial Diversified, Inc.
72033 29 Palms HWY, Twentynine Palms, CA 92277
Tel: (760) 367-6104 Fax: (760) 367-6860
License: 518140
info@commerclaidiversified.com i
http://www.commercialdiversified.com
CHANGE ESTIMATE
PROJECT: Mesa View Fire Station
Palm Desert, CA.
OWNER: City of Palm Desert
OWNER
❑ ,
ARCHITECT
❑
CONSULTANT
❑
CONTRACTOR
❑
FIELD
❑
OSHPD
❑
TO CONTRACTOR:
Commercial Diversified, Inc.
CHANGE ESTIMATE REQUEST NO,: 3
DATE OF ISSUANCE: July 26, 2005
CONTRACT FOR: Mesa View Fire Station
Addition and Remodel
CONTRACT DATED: C2058D1
ARCHITECT'S PROJECT NO,: 0326.00
ARCHITECT: Urrutla Architects
OSHPD NO,:
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed
modifications to the Contract Documents described herein. Submit proposal within 10 days, or notify the
Architect in writing of the date on which you anticipate submitting your proposal,
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH
THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
Description:
The Contractor would like to revise the Point Of Connection for the 4" waste line from the existing waste
line to the new sink In the Kitchen as presently drawn on sheet P2,1. The new POC shall be'behind the
existing sink under the slab as shown In the attached drawing prepared by the plumbing contractor.
I
07/26/05
Attachments:
See the attached drawing prepared by Kincaid Plumbing (Kin: DWG #1)
REQUESTED BY URRUTIA ARCHITECTS:
(Signature)
e
07/28/06 .
Francisco I. Urrutia. President
(Printed name and title)
JUL-19-2005 TUE 08:24 AM COMKEROIAL DIVERSIFIED FAX NO. 7603676860
eg., 18 FROM'. 760:34:25446
4
P. 01
P. 211E
21
Commercial Diversified
INC. „
03 November 2005
Attn: Frank Urrutia
Urrutla Architects
165 Luring Drive
;
Palm Springs, CA 92262
Re. Addition and Remodel Mesa View Fire Station # 67
CER #3 Revised POC for the Kitchen Sink
SCOPE: '
Credit for the Revised POC for the Kitchen Sink.
Labor
Material
Saw Cut 33'
1 HR
30.25
Demo Concrete 20 SF
2 HR
60.50
Excavate 2.25 CY
1.5 HR
45,38
Backfill & Compact 2.25 CY
2 HR
30.25
Replace Concrete .26 CY
3 HR
90.75 35.00
4x4 Comby 1 HR
6.00
13' x 4" Pipe
.5 HR
15.13 18.00
Sub Total
348.26
15% Mark Up
52.24
Total Credit
400.50
Additional for the Revised POC
for the Kitchen Sink.
Hand chip concrete for alternate
tie in
1.5 HR
45.38
1 ea 2" No Hub Coupling
2.50
Sub Total
47.88
15% Mark Up
7.18
Total Extra
55.06 ,
Per the General Conditions of the Agreement, the Contractor requests an '
executed Change Order for the above referenced additional work,
Respectfully,
Richard A. Cobalis
President
Commercial Diversified, Inc.
72033 29 Palms HWY, Twentynine Palms, CA 92277
Tel: (760) 367-6104 Fax: (760) 367-6860
License: 518140
info@pommerctaldiversified.com }
http://www.commercialdiversified.com '