HomeMy WebLinkAboutRatify C20580D1 CO3 Commercial Diversified Fire Station No. 67 RenovationContract No. C2058( CITY OF PALM DESERT CITY MANAGER STAFF REPORT REQUEST: RATIFY CITY MANAGER'S APPROVAL OF CHANGE ORDER NO. 3 IN THE AMOUNT OF $2,466.24 TO COMMERCIAL DIVERSIFIED, INC. (TWENTYNINE PALMS, CA), FOR VARIOUS CONSTRUCTION MODIFICATIONS ASSOCIATED WITH THE FIRE STATION NO. 67 RENOVATION PROJECT. SUBMITTED BY: Stephen Y. Aryan, Assistant to the City Manager DATE: December 8, 2005 CONTRACTOR: Commercial Diversified, Inc. 72033 29 Palms Highway Twentynine Palms, CA 92277 ATTACHMENTS: 1. Contract Change Order No. 3 2. Background Material RECOMMENDATION By Minute Motion: Ratify City Manager's Approval of Change Order No. 3 in the amount of $2,466.24 to Commercial Diversified, Inc. (Twentynine Palms, CA), for various construction modifications associated with the Fire Station No. 67 Renovation Project. BACKGROUND On March 10, 2005, the City Council awarded the Mesa View Fire Station Renovation Project to Commercial Diversified, Inc. (Twentynine Palms, CA) in the amount of $1,395,000, plus a 10% contingency. Please note that the Council previously ratified Change Order No. 1 & 2 for a combined total of $9,275.81. Change Order Number 3 is in the amount of $2,466.24. This change order is to accommodate several modifications and a credit as follows: Additional TV cable extensions to remove cables from roof and extend to the dorms (option #2-no conduit) Additional seismic work needed at the roof area of the Training Room. The added hold-downs are needed because they were missing from the original construction. Raising the existing ducts above the Kitchen ceiling in order to install the new recessed lights. Hand chipping concrete for kitchen sink alternate tie-in Rerouting the waste line to the Kitchen sink (CREDIT) TOTAL $1,164.95 $1,438.00 $208.73 $55.06 ($400.50) $2,466.24 G CityMgnStepnen AryankWord Data\Mesa View FS Change Order 3 ooc Page 1 of 2 Change Order No, 3 (Contract #C-20580-D1) City Council Staff Report October 27, 2005 Prepared by: Reviewed Stephen Y. Aryan Assitant to the City Manager Approved by: 14a Carlos L. Ortega City Manager k�5 Paul/.1ibsonDireca ce Ct�y_ Treasurer G �CdyMg6Stephen AryamWord DaWMesa View FS Change Order 3.doc Page 2 of 2 CONSTRUCTION CHANGE ORDER P.O.# 012324 Contract # C-20580-D 1 Project # Project Description: Mesa View Fire Station No. 67 Remodel Contractor Name Commercial Diversified, Inc. Contractor Street Address 72033 29 Palms Highway Vendor # 8590 City, State, Zip Twentynine Palms, CA 92277 Contract Change Order # 3 Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract. _DESCRIPTION OF CHANGE Multiple Items Requested: 1) Additional TV cable extensions; 2) Additional seismic work needed at the roof area of the Training Room; 3) Raising the existing ducts above the Kitchen; 4) Hand chipping concrete for kitchen sink alternate tie-in. Please note that this change order also reflects a credit for Rerouting the waste line to the Kitchen sink. Contingency used? (circle one) I Yes No Increase/Decrease in Amount $ If yes, amount moved to base: 1 $2, 466.24 Increase/Decrease in Days Contract Amount (include past change orders) $1,404,275.81 I Contract Date of Completion Plus/Minus Current Change Order $2,466.24 Plus/Minus Current Change Order Revised Total Contract Amount $1,406,742.05 Revised Date of Completion 1. ORDERED BY: Stephen Y. Aryan //-.21- 05 Assistant to the City vor Date 3. APPROVED BY: City Manager Date 2. CERTIFI UN AVAILABLE Directockf(Finan&— Date 4. APPROVED BY: City Council Date We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, Which includes all direct and indirect overhead expenses fort any delays. ACCEPTED BY: Contractor/Vendor Date Commercial Diversified INC. .... I . . 03 November 2005 Attn: Frank Urrutia Urrutia Architects 166 Luring Drive Palm Springs, CA 92262 Re. Addition and Remodel Mesa View Fire Station # 67 CER Additional Cable Drops SCOPE: ' Additional Cable Drops Option 1: Encased in Conduit 1. C&S Proposal, see attached 3089.00 Sub Total 3089.00 15% Mark Up 463.35 Total 3552.35 Option 2: Not Encased In Conduit 1. C&S Proposal, see attached 1013.00 ' Sub Total 1013.00 15% Mark Up 151.95 Total 1164.95 Per the General Conditions of the Agreement, the Contractor requests an executed Change Order for the above referenced additional work. Respectfully, �.. � Richard A. Cobalis President r Commercial Diversified, Inc, 72033 29 Palms HWY, Twentynine Palms, CA 92277 Tel: (760) 367-6104 Fax: (760) 367-6860 License: 518140 info@commercialdiversified.com http:ltwww.com merclaldiversified. com NOV-04-2005 FRI 02:37 PM COMMERCIAL DIVERSIFIED FAX NO, 7603676860 P. 01 C & S Electric 7379 Hopi Trail, Yucca V, atley, Ca. 92284 Pit (760) 365-63831,AX (760) 365-6385 Co. lie. C10-399096 Entail cse1gp-1c2,C g - ria, To: Colzirnceaial Divorsified, Lic. Soil- !Musa View Fire Station, I'll", I)csc) t I11d Date: 10/21/05 . In: all 3-TV outlets, one in each dorm. 1. TV outlets in conduit. - $ 3,089.00 2. 'rV outjt�ts 11,11 as open wiring- $ 1,013.00 • i �31� x 1'.1/4/2005 2.27 PM L a , Page 1 of 2 Aryan, Steve From: Frank [frank@urrutiaarchitects.com] Sent: Thursday, November 03, 2005 4:08 PM To: 'Commercial Diversified, Inc' Cc: Aryan, Steve; knappae@aol.com Subject: CER #9 E-Mail Transmittal Date: JiNovember 3, 2005 To: Commercial Diversified From: Urrutia Architects Francisco J. Urrutia, AIA/FARA Project #: 11 0326.00 Project Name: Mesa View FS Ronda: I have reviewed the enclosed CER #9 and need you to confirm the following is included in the CER. Remarks: The intent is for Detail 3/S5.1 to apply to 4 (four) points in the shear walls where the 4 x 4 wood posts are supposed to be located. This also applies to the foundation where the posts meet the concrete. At this point we should have 4 HD 2 hold-downs in place. If they are not there, they will need to be installed per detail 3/S3.0. In the end we need all four posts to have hold- down connections per detail 3/S5.1 to carry the shear down from the roof to the foundation. Please confirm that the proposal sent to me will address this intent. Standard Disclaimer For Electronic The electronic data contained in this media is fie copyright of Urrutia Architects and is provided by Urrutia Media Architects as an aid to the recipient. The data is believed to be accurate but the recipient is responsible for taking necessary steps to confirm its accuracy. Unless stated otherwise, Urrutia Architects is not responsible for any error or omissions, known or unknown that may arise by use of this electronic file. Any alternations to, and use of this electronic data isat the sole risk of the recipient. It should be noted that the following digital rile was prepared for the sole purpose of preparing construction drawings by Urrutia Architects. This Information shall not be used for any other purpose, any other project provided to any other party without the express permission o/ Urrutia Architects. Any questions regarding the data that may arise shall be addressed to Urrutia Architects. 11 /22/2005 COMMERCIAL DIVERSIFIED, INC. 72033 Twentynine Palms Hwy. Twentynine Palms, CA 92277 Tel: (760) 367-6104 Fax: (760) 367-6860 License 5181°40 -- " Email: comdlvinc@adelphia.net TRANSMITTAL SHEET TO: FROM: Frank Urrutia Richard Cobalis COMPANY: DATE; Urrutia Architects 11/4/2005 FAX NUMBER: TOTAL NO. OF PAGES INCLUDING COVER: 327.6813 ' 1 PHONE NUMBER: CC: 327.6800 RE: YOUR REFERENCE: Sheet S5 Detail 3 Mesa View Fire Station Verification of HD2 - REVISED LI URGENT m FOR REVIEW ❑ PLEASE COMMENT ❑ PLEASE REPLY ❑ PREVAILING WAGE NOTESICOMMENTS: Mr. Urrutia, The following revisions have been made to our proposal in order to comply with the direction in your correspondence. Cost for these repairs would be: Material (not Itemized) $150.00 Epoxy Inspections $255.00 $85,00 ea. Labor, 24 MH $846.00 Sub Total $1251.00 15% Mark Up 1$ 87.00 Total $1438.00 t.. r� r . 3 CHANGE ESTIMATE PROJECT: Mesa View Fire Station Palm Desert, CA. OWNER: City of Palm Desert TO CONTRACTOR: Commercial Diversified, Inc. OWNER ® , ARCHITECT CONSULTANT ❑ CONTRACTOR FIELD ❑ OSHPD ❑ CHANGE ESTIMATE REQUEST NO.: 8 DATE OF ISSUANCE: October 20, 2005 CONTRACT FOR: Mesa View Fire Station Addition and Remodel CONTRACT DATED: C2058Di , ARCHITECT'S PROJECT NO.: 0326.00 ARCHITECT: Urrutla Architects OSHPD NO.: Please submit an Itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. Submit proposal within 10 days, or notify the Architect In writing of the date on which you anticipate submitting your proposal, THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. Description: 1. The existing ceiling and ductwork In the Corridor and Dining area are to low to be able to accept .the light fixtures specified. A different light fixture was specified which was shallower and would fit, however, they have a 6-8 week lead time to obtain them. As an alternative, the ductwork will be raised to allow for the specified lights to be Installed. Provide a cost to raise the a/c ductwork. x• 10/20/05 t. I Attachments: None. REQUESTED BY URRUTIA ARCHITECTS: --------------- (Signature) Francisco 1. Urrutla. President (Printed name and title) t ` t MCI= Commercial Diversified INC. 03 November 2005 Attn: Frank Urrutia Urrutia Architects 165 Luring Drive ; Palm Springs, CA 92262 Re. Addition and Remodel Mesa View Fire Station # 67 CER #8 Raise the Existing Ductwork SCOPE: ' Raise the existing a/c ductwork Corridor/DR Labor Material Labor 6 HR 181.50 Sub Total 181.50 16% Mark Up 27.23 Total 208.73 Per the General Conditions of the Agreement, the Contractor requests an executed Change Order for the above referenced additional work. Respectfully, Richard A. Cobalis President Commercial Diversified, Inc. 72033 29 Palms HWY, Twentynine Palms, CA 92277 Tel: (760) 367-6104 Fax: (760) 367-6860 License: 518140 info@commerclaidiversified.com i http://www.commercialdiversified.com CHANGE ESTIMATE PROJECT: Mesa View Fire Station Palm Desert, CA. OWNER: City of Palm Desert OWNER ❑ , ARCHITECT ❑ CONSULTANT ❑ CONTRACTOR ❑ FIELD ❑ OSHPD ❑ TO CONTRACTOR: Commercial Diversified, Inc. CHANGE ESTIMATE REQUEST NO,: 3 DATE OF ISSUANCE: July 26, 2005 CONTRACT FOR: Mesa View Fire Station Addition and Remodel CONTRACT DATED: C2058D1 ARCHITECT'S PROJECT NO,: 0326.00 ARCHITECT: Urrutla Architects OSHPD NO,: Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to the Contract Documents described herein. Submit proposal within 10 days, or notify the Architect in writing of the date on which you anticipate submitting your proposal, THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS. Description: The Contractor would like to revise the Point Of Connection for the 4" waste line from the existing waste line to the new sink In the Kitchen as presently drawn on sheet P2,1. The new POC shall be'behind the existing sink under the slab as shown In the attached drawing prepared by the plumbing contractor. I 07/26/05 Attachments: See the attached drawing prepared by Kincaid Plumbing (Kin: DWG #1) REQUESTED BY URRUTIA ARCHITECTS: (Signature) e 07/28/06 . Francisco I. Urrutia. President (Printed name and title) JUL-19-2005 TUE 08:24 AM COMKEROIAL DIVERSIFIED FAX NO. 7603676860 eg., 18 FROM'. 760:34:25446 4 P. 01 P. 211E 21 Commercial Diversified INC. „ 03 November 2005 Attn: Frank Urrutia Urrutla Architects 165 Luring Drive ; Palm Springs, CA 92262 Re. Addition and Remodel Mesa View Fire Station # 67 CER #3 Revised POC for the Kitchen Sink SCOPE: ' Credit for the Revised POC for the Kitchen Sink. Labor Material Saw Cut 33' 1 HR 30.25 Demo Concrete 20 SF 2 HR 60.50 Excavate 2.25 CY 1.5 HR 45,38 Backfill & Compact 2.25 CY 2 HR 30.25 Replace Concrete .26 CY 3 HR 90.75 35.00 4x4 Comby 1 HR 6.00 13' x 4" Pipe .5 HR 15.13 18.00 Sub Total 348.26 15% Mark Up 52.24 Total Credit 400.50 Additional for the Revised POC for the Kitchen Sink. Hand chip concrete for alternate tie in 1.5 HR 45.38 1 ea 2" No Hub Coupling 2.50 Sub Total 47.88 15% Mark Up 7.18 Total Extra 55.06 , Per the General Conditions of the Agreement, the Contractor requests an ' executed Change Order for the above referenced additional work, Respectfully, Richard A. Cobalis President Commercial Diversified, Inc. 72033 29 Palms HWY, Twentynine Palms, CA 92277 Tel: (760) 367-6104 Fax: (760) 367-6860 License: 518140 info@pommerctaldiversified.com } http://www.commercialdiversified.com '