REQUEST: Award Contract C24120 to Pacific Asphalt Services, Ontario,
California, for the Presidents' Plaza III Parking Lot Slurry
Seal and Repair.
SUBMITTED BY:
CONTRACTOR
DATE:
CONTENTS:
Recommendation:
Martin Alvarez, Senior Management Analyst
Pacific Asphalt Services
P.O. Box 1547
Ontario, CA 91762
September 22, 2005
Vicinity Map Attached
Contract Agreement
By Minute Motion:
1. Award Contract C24120 to Pacific Asphalt Services of
Ontario, California, in the amount of $51,500.00, plus a 10%
contingency to slurry seal and repair the Presidents' Plaza
parking lot.
2. Appropriate $29,567 from the Presidents' Plaza III Parking
Lot Reserve Fund,
Discussion:
The Presidents' Plaza III Business Improvement District was established in 2001 for a
5-year term and budget. The District is in its fifth and final year of the term. The
renewal process for the district will begin in November of 2005. The District includes
properties located on the south side of Highway 111 and on the north side of El Paseo,
between Highway 74 and Sage Lane.
The City collects an annual assessment from each property owner to pay for
maintenance services such as landscaping, lighting and street sweeping. Included in
each year's budget is a parking lot maintenance reserve of $5,000, and to date, the
parking lot reserve fund balance is $29,567. These funds are sufficient to cover the
required slurry seal and re -striping of the parking lot. An additional $21,933 is required
Staff Report
Parking Lot Slurry Seal/Repair C24120
Page 2 of 2
September 22, 2005
to complete a capital improvement to repair an 8,500 square foot area of the parking lot
located south of the Palomino's building. These funds are available in the City's
Parking Lot Resurfacing Account No. 110-4313-433.33-20.
On August 12, 2005, staff advertised for sealed bids for this project. The bids included
slurry sealing the entire parking lot and repairing an 8,500 square foot section of parking
lot located south of the former Palomino's parking lot (see attached map). This section
of parking lot has deteriorated to a point that replacement is necessary.
On September 9, 2005, bids were opened. The following were the responders:
Pacific Asphalt Services Ontario, California $51,500.00
S-2 Sealing and Striping, Inc. Palm Desert, California $56,717.00
Nelson Paving & Sealing, Inc. Beaumont, California $71,225.00
Therefore, staff recommends that City Council, by minute motion, authorize the Mayor
to award Contract C24120 to Pacific Asphalt Service of Ontario, California, in the
amount of $51,500.00, plus a 10% contingency.
Submitted By:
artin C.Alvarez
Senior Management Analyst
Approval:
City Manager
oa-111�
Director of Finance
/ma
Department Head:
9444. ee
Homer Croy
ACM for Development Services
G'VDevServicesV0artin AlvarezWord FilestPresPlazallf Parking Lot Re SeaMward to Pacific Asphalt doc
CONTRACT NO. C24120
AGREEMENT
PRESIDENTS' PLAZA III PARKING LOT SLURRY SEAL / REPAIR
CONTRACT C24120
FISCAL YEAR 2005/2006
THIS AGREEMENT is made and entered into this 22nd day of September,
2005, by and between City of Palm Desert, California, hereafter called "Owner'
and Pacific Asphalt Services hereinafter called "Contractor".
WITNESSETH
RECITALS:
Contractor has submitted to Owner its Contractor's Proposal for the
construction of Owner Project,
PARKING LOT SEAL COAT / REPAIR FOR PRESIDENT'S PLAZA III,
BUSINESS IMPROVEMENT DISTRICT, CONTRACT NO. C24120, in
strict accordance with the Contract Documents identified below, Owner
has accepted said Proposal.
2. Contractor states that it has re-examined its Contractor's Proposal and
found it to be correct, has ascertained that its Subcontractors are properly
licensed and possess the requisite skill and forces, has examined the site
and Contract in accordance with the Contract Documents for the money
set forth in its Proposal to be paid as provided in the Contract Documents.
AGREEMENT:
IT IS AGREED BY THE PARTIES AS FOLLOWS:
1. Contract Documents: The entire contract consists of the following: (a) The
Agreement; (b) The Notice Inviting Bids; (c) The Instruction to Bidders;
(d) The Contractor's Proposal; (e) The Bidder's Bond; (f) The
Performance Bond; (g) The Payment Bond; (h) The General Conditions;
(i) The Special Provisions; 0) The Standard Specifications as modified in
other portions of the Contract Documents; (k) The Plans; (1) Addenda
Nos. ; (m) The Determination of Prevailing Wage Rates for Public
Work; (n) Any Change Orders issued; (o) Any additional or supplemental
specifications, notices, instructions and drawings issued in accordance
with the provisions of the Contract Documents. All of said Documents
presently in existence are by this reference incorporated herein as if here
set forth in full and upon the proper issuance of their documents they shall
likewise be deemed incorporated.
CONTRACT NO. C24120
2. Contractor shall commence the work within ten calendar days after the
date of the Notice to Proceed and will do all things necessary to construct
the work generally described in Recital No. 1 in accordance with the
Contract Documents and will complete said work within forty-five (45)
calendar days from the Notice to Proceed date to the satisfaction of the
Engineer.
3. Contractor agrees to indemnify, defend and save Owner and its
officers, agents and employees, and the Engineer harmless from:
a. Any and all liability, claims, damages, losses or injuries to any person
or other entity, including injury to Contractor's employees, and all
claims which arise from or are connected with the negligent
performance of or failure to perform the work or other obligations of
this Agreement, or which are caused or which are claimed to be
caused by the negligent or intentional acts or omissions of Contractor,
its subcontractors, its agents or employees, and, all expenses of
investigating and defending against same,
b. Any and all liability, claims, damages, losses or injuries to any and all
contractors, subcontractors, material -men, laborers, or any other
person, firm or corporation furnishing or supplying work, services,
materials or supplies in connection with the performance of the
Agreement.
Attention is directed to the General Specifications pages 25-26 and 33-37,
which specifications are made part of this Agreement as set forth in
Agreement paragraph 1, above.
Attention is directed to Section 6-9, "Liquidated Damages" of the Standard
Specifications and is hereby amended to the substitute the "City of Palm
Desert" in place of "Agency." Liquidated damages shall be $1000 dollars
per calendar day of delay.
4. Should any litigation or arbitration be commenced between the parties
concerning the works of improvements as referenced herein, the
prevailing party in any such litigation, being the Owner or the Contractor,
should be entitled to a reasonable sum for attorney's fees incurred in any
such litigation relating to this Contract.
5. This Agreement shall be binding upon all parties hereto and their
respective heirs, executors, administrators, successors, and assigns.
6. Contractor shall be paid in the manner set forth in the Contract Documents
the amount of its Proposal as accepted by Owner, subject to such
additions and deductions as may be made pursuant to the Contact
Documents and applicable law.
CONTRACT NO. C24120
Satisfactory Performance
The prime Contractor agrees to pay each Subcontractor under this prime
contract for satisfactory performance of its contract no later than 10 days
from the receipt of each payment the prime Contractor receives from City
of Palm Desert. Any delay or postponement of payment from the above
referenced time frame may occur only for good cause following written
approval of the City of Palm Desert.
Release of Retention
The prime Contractor agrees further to release retention payments to each
Subcontractor within 30 days after the Subcontractor's work is
satisfactorily completed. Any delay or postponement of payment from the
above referenced time frame may occur only for good cause following
written approval of the City of Palm Desert.
7. Execution of the Agreement by the parties constitutes their agreement to
abide by all applicable provisions of the California Labor Code; constitutes
Contractor's certification that he is aware of the provisions of said Code
and will comply with them; and further constitutes Contractor's certification
as follows:
"I am aware of the provisions of Section 3700 of the California
Labor Code which requires every employer to be insured against
liability for worker's compensation or to undertake self insurance
in accordance with the provisions of that Code, and I will comply
with such provisions before commencing the performance of the
work of this contract."
IN WITNESS WHEREOF the parties hereto have executed or caused to
be executed by their duly authorized officials, this Agreement which shall be
deemed an original on the date first above written.
[Remainder of this page has intentionally been left blank.
Signature blocks are contained on the next page]
CONTRACTOR:
BY:
Signature to be notarized
TITLE:
OWNER:
BY:
Signature to be notarized
TITLE: Mavor of Palm Desert, CA
CA
APPROVED AS TO CONTENT:
HOMER CROY
ASSISTANT CITY MANAGER
FOR DEVELOPMENT SERVICES
CONTRACT NO. C24120
ATTEST BY:
TITLE:
ATTEST BY:
TITLE: Citv Clerk of Palm Desert„
APPROVED AS TO FORM:
DAVID J. ERWIN,
CITY ATTORNEY