HomeMy WebLinkAboutC24350 Amendent 1 Curb, Gutter, and Cross Gutter Repair Program 753-06CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: Approve Contract Amendment No. 1 to Contract No. C24350 with
Contreras Construction Company for Additional Curb, Gutter, and
Sidewalk Work (Project Number 753-06).
SUBMITTED BY: Mark Greenwood, P.E.
CONTRACTOR: Contreras Construction Company
P.O. Box 1808
Indio, California 92201
DATE: April 13, 2006
CONTENTS: Amendment No. 1 to Contract No. C24350
Contractors Quotation
Location Photos
Recommendation:
By minute motion, approve Contract Amendment No. 1 to Contract No.
C24350 with Contreras Construction Company to include four additional
locations in the 2006 Citywide Curb, Gutter, and Sidewalk Program (Project
No. 753-06), in the amount of $77,122.00.
Discussion:
In November 2005, the City advertised for contractors to bid on the 2006 Citywide Curb,
Gutter, and Sidewalk Program. On January 12, 2006, the contract was awarded to
Contreras Construction Company.
Staff has identified additional locations where work of the same nature needs to be done.
Instead of waiting for next year's program, staff requests approval of a contract amendment
to include the additional locations. Below is a list of the locations with brief descriptions:
AD-2 Desert Crossing at Fairfield Inn — Recent construction at this location caused an
unforeseen condition where vehicles have been hitting the curb when making a right turn
into the hotel parking lot from Highway 111. Delineators have been installed as a temporary
measure to make the curb more apparent. The proposed permanent solution is to pull back
the curb to eliminate the problem.
Staff Report — Contract Amendment #1 to Contract C24350 Contreras Construction
April 13, 2006
Page 2of2
AD-3 Elephant Bar ADA ramps — The wheelchair ramps near the Elephant Bar are not in
compliance with the Americans with Disabilities Act. The proposed solution is to remove
the existing ramps and replace them with ramps meeting the grade requirements.
AD-4 Fred Waring median west of Highway 111 — This median prohibits left turns from the
Desert Crossing driveway to Fred Waring Drive. Staff has observed drivers on various
occasions making the left turn anyway and driving down the wrong side of the divided road
to get back to Painters Path. Staff has determined that there is no compelling reason to
prohibit this left turn movement. The proposed solution is to remove the median and
replace it with a striped median which would allow the left turn movement.
AD-5 Magnesia Falls median west of Portola Avenue — Originally, this median was
designed to only allow egress from Portola Palms Mobile Home Park (PPMHP). Since that
time, the City authorized egress and ingress from the PPMHP gate only as right turn in or
out. The proposed solution is to remove the asphalt pavement and extend the curb to
connect the two median islands. Then median will then be landscaped to match the
existing landscape.
Funds are available for this Contract Amendment in account 400-4616-433-4001.
Therefore, staff recommends that City Council approve Contract Amendment No. 1 to
Contract No. C24350 with Contreras Construction Company to include the additional
locations in the Curb, Gutter, and Sidewalk Program (Project No. 753-06).
Submitted By: Department Head:
Ryan Gayler Mark Greenwood, P.E.
Project Administrator Director of Public Works
Approval:
ACM for Development Services Finance Director
City Manager
W lAgenda Items12006-Apr 131Contract amendment Contreras C24350 753-061Approve Contreras amendment 1 C24350 campes nos 753-06 doc
CITY OF PALM DESERT
CONTRACT AMENDMENT
Project Description:
P.O.# 12937
Contract
# C24350
2006 Citywide Curb, Gutter, and Sidewalk Project # 753-06
Program
Contractor Name Contreras Construction Company Contractor
Street Address P.O. Box 1808 Vendor # 166
City, State, Zip Indio, CA 92201
Contract Amendment # 1
Pursuant to the terms of the original contract Agreement, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract. Unless
otherwise stated, all work shall conform to the terms, general conditions, and special provisions of the original contract.
DESCRIPTION OF CHANGE
Add locations for median removal, repair, ADA retrofit, curb realignment
Contingency used? (yes / no)
If yes, amount moved to base:
no
Increase/Decrease in Amount
$77,122.00
Contract Amount (include past amendments)
242,415.00
Plus/Minus Current Amendments
77,122.00
Revised Total Contract Amount
$ 319,537.00
1. ORDERED BY:
Department Head
3. APPROVED BY:
City Manager
Date
Increase/Decrease in Days
20
Contract Date of Completion
5/27/06
Plus/Minus Current Amendment
20
Revised Date of Completion
6/16/06
2. CERTIFIED FUNDS AVAILABLE
Director of Finance
4. APPROVED BY:
Date
City Council
Date
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will
provide all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and
hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses fort any delays.
ACCEPTED BY:
Contractor/Vendor
Date
Contreras Construction Co.
General Contractor
P.O. Box 1808
Indio, Ca 92202
Phone (760) 347-6070 Fax (760) 347-5591
Ship To:
City of Palm Desert
Attn: Ryan Gayler
73-510 Fred Waring Dr.
Palm Desert, Ca 92260
DATE March 30, 2006
Quotation # 1369
Customer #
Quotation valid until:
Prepared by: Lupe Perez
Project Name : Curb, Gutter & Sidewalk
Repair , Project # 753-06
Comments or special instructions: Price includes removals, disposals, grading, compacting, and traffic control.
Additional Work:
Description
1. AD-2 Desert crossing at Hwy 111 - remove curb and reconstruct with curb and gutter,
concrete slab to be 8" thick. 1 LS =
$
2,918.00
2. AD-3 Elephant Bar ADA Ramps - Saw cut, remove 20 If of curb and gutter, & 17 If of
curb, eliminate one ramp, and reconstruct new ramp. 1 LS =
$
6,516.00
3. AD-4 Fred Waring, West of Hwy 111 - Remove & dispose of concrete curb (@1024 If),
and stamp concrete (@ 1380 sf). Place 4" of AC over 7" base @ 4620 sf. 1 LS =
$
49,887.00
4.AD-5 Magnesia Falls, West of Portola Ave next to the median islands - remove @ 126
If of curb and @ 1150 sf of median rock, ac, and base. Construct 6" curb for median
island, (@ 175 If ). Place 4" of ac next to curb over 7" of base. 1 LS =
$
17,801.00
$
77,122.00
ACCEPTED FOR BUYER
BY:
Title
Date
CONTRERAS CONSTRUCTION CO.
ACCEPTANCE OF PROPOSAL
The above price, specification and condition are
satisfactory and are hereby accepted. You are
authorized to do work as specified. Payment will
be made as outline above.
CONTRERAS CONSTRUCTION CO.
Approve By:
Henry Contreras
Title President Date
All material guaranteed to be as specified. All work to be completed
in a substantial workmanlike manner according to specification
submitted per standard practices. Any alteration or deviation from
above specification involving extra cost will execute only upon
written orders, and will become an extra charge over and above
the estimate. All agreements contingent upon strike, accidents, or
delays beyond our control. Owner to carry fire, tornado and other
necessary insurance. Our workers are fully covered by Workers
Compensation Insurance.
When signed by the Buyer and approved by Managing Officer cf this Company, this will constitute a firm contract between both parties, hereto, for all labor and for aft materials
herein referred to, according to terms and condition.
AD-2 Desert Crossing: at Highway 111 AD-3 Elephant bar ADA ramps
AD-3 Elephant bar ADA ramps
AD-4 Fred Waring: West of Hwy 111 AD-5 Magnesia Falls: West of Portola Avenue