HomeMy WebLinkAboutC25570 CO2 - Sec 29 AD Swr InstallationB
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: Approve Change Order No. 2 to Contract C25570 for the
Section 29 Assessment District 2004-02 Sewer Installation
Phase I
SUBMITTED BY: Mark Greenwood, P.E.
APPLICANT: Jones Bros Construction Company
P.O. Box 905
Coachella, CA 92236
DATE: April 12, 2007
CONTENTS: Change Order No. 2
Vicinity Map
Recommendation:
That City Council, by Minute Motion:
1. Approve Change Order No. 2 to Contract No. C25570 for
the construction of the Section 29 Assessment District
2004-02 Phase I Sewer Installation with Jones Bros
Construction Company in the amount of $2,563.13;
2. Move $14.09 from contingency to base;
3. Appropriate $2,549.04 from unobligated Fund 400 to the
project account; and
4. Authorize the Mayor to execute the same.
Discussion:
On October 12, 2006, City Council approved Contract No. C25570 for the Phase
I Sewer Improvements of Assessment District 29 2004-02, in the amount of
$634,220.00 plus a 10% contingency. On January 11, 2007, City Council
approved Change Order No. 1 in the amount of $63,407.91 for the removal of
excessive earth material over the proposed pipe alignment.
Phase I Sewer Installation was the first part of a cooperative effort for
construction of improvements in the Section 29 Assessment District 2004-02.
Staff Report
Approve Change Order No. 2 to Contract C25570-Jones Bros (Project 627-S-05)
Page 2 of 2
April 12, 2007
When the sewer portion was separated from the overall project and bid
separately, the plans were modified accordingly. Those modifications failed to
address the amount of excess dirt removal. This material would have been
removed as part of the overall Assessment District construction project; however,
to construct the sewer project the removal of the overburden was necessary.
When the overburden was removed it left two manholes perched above the final
street grade. These manholes will be at grade once the street improvements are
constructed; however, the Coachella Valley Water District would not approve the
sewer improvements to go on-line until the perched manholes had earthen
material constructed around them.
Therefore, staff recommends that City Council approve Change Order No. 2 to
Contract No. C25570 for the construction of the Section 29 Assessment District
2004-02 Phase I Sewer Installation with Jones Bros Construction Company in
the amount of $2,563.13, move $14.09 from contingency to base, appropriate
$2,549.04 from unobligated Fund 400 to the project account, and authorize the
Mayor to execute the same.
Department Hepn'd:
Mark Greenwood, P.E.
Director of Public Works
Approval:
Homer Croy
ACM for Development Services
Carlos L. Ortega
City Manager
Icls
s
Paul Gibson
Finance Director
AYES 1e/1SCXlokaiU61xlf-
iFinPfyi p'`
• rm e_ AlJJ /j
ABSENT: Aj olio
ABSTAIN: f -\ tv1P_
VERIFIED BY:�f9
Original on File withjcity Clerk's Office
CITY COUNCIL ACTION:
APPROVED V DENIED
RECEIVED OTHER
MEETING DATE y -1 a- D' I
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose
Consultant's Name
Address:
Section 29 Assessment District Phase I Sewer
Jones Bros Construction
P.O. Box 905, Coachella, CA 92236
Contract # / P.O. #
Change Order No.
Contingency:
Account No.
Project No.
Vendor No.
C25570/13581
YES k NO�
46494350433460
627-S-05
2763
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES
(Supplemental Plans, Specifications, and Directives dated Attached)
Construct embankment material around perched manholes No. 3 and 4.
DECREASE
In Contract Price
INCREASE
In Contract Price
$2,563.13
TOTALS: - 2,563.13
NET CHANGE IN CONTRACT PRICE: 2,563.13
JUSTIFICATION:
Phase I Sewer Installation was the first part of a cooperative effort for construction of improvements in the
Section 29 Assessment District 2004-02. When the sewer portion was separated from the overall project
and bid separately, the plans were modified accordingly. Removal of excess soil was necessary due to the
separation of the project. The overburden was removed to final grade on the sewer project. Prior to CVWD
90% approval it was required to construct earthen material around Manholes No. 3 and 4 that were perched
above final street grade. These manholes will be finalized as part of the overall Assessment District
construction project; however, due to the time between Phase I and Phase II of the Assessment District the
manholes could not be left perched above the street grade.
Less: Expend. & Enarrb. To Date:
Less: This Change Order Arrant:
BALANCE OF BIDET
REMA N NG FOR PROJECT:
636,797.22
63,407.91
0.00
Arrant Approved by Council:
Less: Prior change Order(s):
Less: This Change Order:
Balance Rerrniring of Contingency:
63,422.00
63,407.91
2,563.13
(z549.04)1
The amount of the Contract will be Increased by the Sum of: Two Thousand Five Hundred Sixtv-three 13
Dollars ($ 2,563.13).
Contract C25570 Change Order No. 2 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension -0- Days
Revised Contract Total 75 Days
The undersigned Contractor approves the foregoing Change Order # 2 as to the changes, if any, in the contract price
specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in
work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change
Order # 2 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of
that directly or indirectly related to the approved time extension, required to complete the Change Order items. This
document will become a supplement of the contract and all provisions will apply hereto. It is understood that the
Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
3. CERTIFIED
FUNDS AVAILABLE:
DEPARTMENT HEAD
FINANCE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
CONTRACTOR Date Accepted
4. APPROVED BY:
RICHARD S. KELLY, MAYOR Date Approved
CITY MANAGER Date Approved
MONTEREY AVE
VICINTIY MAP
ASSESSMENT DISTRICT 29
Project 627-05
1 ERALD FORD DFF ,
Ffill..