HomeMy WebLinkAboutC25570 CO1 Sec 29 AD No. 2004-02 Sewer Installation Phase IREQUEST:
SUBMITTED BY:
APPLICANT:
DATE:
CONTENTS:
Recommendation:
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
Approve Change Order No. 1 to Contract C25570 for the
Section 29 Assessment District 2004-02 Sewer Installation
Phase I
Mark Greenwood, P.E.
Jones Bros Construction Company
P.O. Box 905
Coachella, CA 92236
January 11, 2007
Change Order No. 1
Vicinity Map
By Minute Motion:
1. Approve Change Order No. 1 to Contract No. C25570 for
the construction of the Section 29 Assessment District
2004-02 Phase I Sewer Installation with Jones Bros
Construction Company in the amount of $63,407.91.
2. Move $63,407.91 from contingency to base.
3. Authorize the Mayor to execute the same.
Discussion:
On October 12, 2006, City Council approved Contract No. C25570 for the Phase
I Sewer Improvements of Assessment District 29 2004-02, in the amount of
$634,220.00 plus a 10% contingency.
Phase I Sewer Installation was the first part of a cooperative effort for
construction of improvements in the Section 29 Assessment District 2004-02.
When the sewer portion was separated from the overall project and bid
separately, the plans were modified accordingly. Those modifications failed to
address the amount of removal of excessive earth material over the proposed
pipe alignment. This material would have been removed as part of the overall
Staff Report
Approve Change Order No. 1 to Contract C25570-Jones Bros (Project 627-S-05)
Page 2 of 2
January 11, 2007
Assessment District construction project; however, to construct the sewer project
the removal of the overburden was necessary.
Funds are available for this in account number 469-4350-433-4001.
Therefore, staff recommends that City Council approve Change Order No. 1 to
Contract No. C25570 for the construction of Section 29 Assessment District
2004-02 Phase I Sewer Installation with Jones Bros Construction Company in
the amount of $63,407.91, move $63,407.91 from contingency to base, and
authorize the Mayor to execute the same.
Prepared By:
Greenwood,
Director of Public Wo s
Approval:
AC for Dev opment Services
City t/lanbger
P.E
/cls
Department Head:
c Greenwood, P.K.
erector of Public Works
Finance Director
=TY COUNCIL ACTION:
APPROVED V DENIED
RECEIVED OTHER.
MEETING DAT
AYES -
NOES: k
ABSENT: N(SY
ABSTAIN:
VERIFIED BY:_.WIW yt
7riginal on File with City Clerk's Office
i1.e(ttk►P id f PILL/
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose
Consultant's Name
Address:
Jones Bros Construction
P.O. Box 905, Coachella, CA 92236
Contract # / P.O. # C25570/13581
Change Order No. 7— 1
Contingency: YES) I NO
Account No. 46943504334001
Project No. 627-S-05
Vendor No. 1 2763
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES
(Supplemental Plans, Specifications, and Directives dated
Removal of soil overburden at Sewer Installation site
Attached)
DECREASE INCREASE
In Contract Price In Contract Price
$63,407.91
TOTALS: - 63,407.91
NET CHANGE IN CONTRACT PRICE: 63,407.91
JUSTIFICATION:
Phase I Sewer Installation was the first part of a cooperative effort for construction of improvements in the
Section 29 Assessment District 2004-02. When the sewer portion was separated from the overall project
and bid separately, the plans were modified accordingly. Those modifications failed to address the amount
of removal of excessive earth material over the proposed pipe alignment. This material would have been
removed as part of the overall Assessment District construction project; however, to construct the sewer
project the removal of the overburden was necessary.
TOTAL BUDGET FOR PROJECT:
Less: Expend. & Enarrb. To Date:
Less: This change Order Amount:
BALANCE OF BUDGET
REMAJ N NG FOR PROJECT:
+ 697,642.00
- 634,234.09
- 63,407.91
0.00
CONTINGENCY:
Arna.nt Approved by Cancil:
Less: Prior Change Order(s):
Less: This Change Order:
Balance Remaining of Contingency:
63,422001
+ 63,42200
- 63,407.91
14.09
The amount of the Contract will be Increased by the Sum of: Sixtv-three thousand four hundred seven and
91/00 Dollars ($ 63,407.91).
Contract C25570 Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension -0- Days
Revised Contract Total 75 Days
The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price
specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in
work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change
Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of
that directly or indirectly related to the approved time extension, required to complete the Change Order items. This
document will become a supplement of the contract and all provisions will apply hereto. It is understood that the
Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
3. CERTIFIED
FUNDS AVAILABLE:
DEPARTMENT HEAD
FINANCE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
CONTRACTOR Date Accepted
4. APPROVED BY:
RICHARD S. KELLY, MAYOR Date Approved
CITY MANAGER Date Approved
MONTEREY AVE
VICINTIY MAP
ASSESSMENT DISTRICT 29
Project 627-05
1 ERALD FORD DFF ,