HomeMy WebLinkAboutC23290C1 - CO1 - Carlson SolarCITY OF PALM DESERT CONSTRUCTION CHANGE ORDER Contract Purpose Consultant's Name Address: Contract # / P.O. # 1 C23290C1 I 14017 Change Order No. I 1 Contingency: 1 YES I NO Account No. 1 400-4511-4423-911 Project No. Vendor No. 9976 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE (Supplemental Plans, Specifications, and Directives dated Attached) In Contract Price Install 192 Siemens SM-50 Photovoltaic panels, supplied by City, to Civic Center main parking shade cover Move and replace racking for existing photovoltaic panels on Civic Center main parking shade cover JUSTIFICATION: TOTAL BUDGET FOR PROJECT: Less: Expend. & Encumb. To Date: Less: This Change Order Amount: BALANCE OF BUDGET REMAINING FOR PROJECT: TOTALS: NET CHANGE IN CONTRACT PRICE: + 562,993.00 - 512,879.38 - 96,254.10 (46,140.48) CONTINGENCY: Amount Approved by Council: Less: Prior Change Order(s): Less: This Change Order: Balance Remaining of Contingency: INCREASE In Contract Price 96,254.10 96,254.10 96,254.10 The amount of the Contract will be (Decreased) Increased by the Sum of: Dollars ($ 96,254.10 ). W \City Templates\City Word Templates\Forms\Change Orders and Amendment Forms\City Change Order doc See reverse ... Contract C23290C1 Change Order No. 1 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension Days. Revised Contract Total $560,411.78 The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: DEPARTMENT HEAD 3. CERTIFIED FUNDS AVAILABLE: FINANCE DIRECTOR NOTE: No payments will be made prior to City Manager and Council approval 2. ACCEPTED BY: CONTRACTOR Date Accepted 4. APPROVED BY: RICHARD KELLY, MAYOR Date Approved CITY MANAGER Date Approved W \C,ty Templates\Crty Word Templates \ Forms \Change Orders and Amendment Forms\City Change Order doc See reverse ... r4. Carlson Solar Electric Systems 43430 E. State Hwy 74 #F PMB-221 Hemet, CA 92544 1-877-927-0782 Toll Free Bib To City of Palm Desert 2 73-510 Fred Waring Dnve Palm Desert, CA 92260 (760) 674-3428 Fax (760) 837-0287 Estimate Date Estimate # 6/11/2007 469 Quantity Description Rate 1 Removal of old racking, modules and conduit. 4,600.00 384 installation of 192 + previous 192 SMSO Solar Modules 125.00 384 Module Racking Utilizing anodized aluminum with stainless steel 75.00 hardware 1 Miscellaneous parts such as wire, me connectors, breakers, disconnects, 11,714.25 sub panels and ctc The understanding that the City of Palm Desert will provide any Structural engineering if needed and that performance or payment bonds are not required. This is a not to exceed estimate. Actual cost may be Tess. Total 4,600.00 48,000.00 28,800.00T 1 1,714.25T 0.00T Subtotal S93,114.25 Sales Tax (7.75%) 53,139.85 Total S96,254.10 z0021 21V10S NOS121V0 XVd 65:41 LOOz/81/90