HomeMy WebLinkAboutC23290C1 CO1 N.Carports Photovoltaic SystmCITY OF PALM DESERT
OFFICE OF ENERGY MANAGEMENT
STAFF REPORT
TO: Honorable Mayor and City Council Members
SUBJECT: CHANGE ORDER #1 CIVIC CENTER SOLAR PHOTOVOLTAIC
SYSTEM
SUBMITTED BY: Pat Conlon, Director of Office of Energy Management
DATE: June 28, 2007
CONTRACT No. C23290-C1
CONTRACTOR: Carlson Solar Electric Systems
43430 E. Highway 74, Suite F PMB 211
Hemet, CA 92544
ATTACHMENT: Change Order #1
Staff Recommendation:
By Minute Motion
1) Approve Change Order #1 on the above contract for an amount Not To Exceed
$96,254.10 for the installation of a new rack system and 192 additional solar
panels, supplied by the City, on the Civic Center main parking shade cover.
2) Authorize the use of $46,415.77 project contingency funds for the above
contract.
3) Authorize the transfer of $49,838.33 from account No. 400-4511-4423-911 to the
base contract for this expenditure.
Discussion:
The City currently has 192 solar panels in storage left over from the 2001 purchase of
600 solar panels as part of the Palm Desert Solar Assistance Program. The Siemens
SM-50 solar panels we have in storage are the same solar panels we installed on the
Civic Center main parking shade cover in 2003, so there is no need to change or modify
Change Order #1 Civic Center Solar Photovoltaic System
June 28, 2007
Page 2 of 2
the existing photovoltaic system's wiring or equipment to accommodate the additional
panels.
What we would like to take advantage of when we do this work is to revise the existing
rack system when the new rack system is installed. The rack system is the frame which
supports the solar panels. We would like to remove the existing rack system and
incorporate the existing solar panels into the new rack system, which holds the added
solar panels. We want to locate the new rack system a further distance from the existing
date palm trees so we can get more solar exposure on both the existing photovoltaic
solar panels and the 192 new panels that we will be adding to the system.
By relocating the rack system away from the shade of the date palms coupled with
adding the additional panels to the system, there will be a 130% increase to the output
of the system. As you are aware, the shading of the date palms on the existing system
reduces the potential output by 50%. The new calculated annual output of the
photovoltaic system with the revised racks and the additional 192 panels is
approximately 29,862 kilowatt hours, which at our existing time -of -use Southern
California Edison rates, will result in an annual savings of $5,249.16.
The 192 added solar panels are eligible for a Southern California Edison rebate of
approximately $29,250.00.
No additional appropriation is required for this Change Order. Funds are available in the
project contingency and the project account no. 400-4511-4423-911.
Any questions, please feel free to contact me.
Submitted by: Approved by:
Pat onlon Carlos Orte(g
Director, Office of Energy Management City Manager
Reviewed by:
Paul Gibson
Finance Director
dITY COUNCIL,ACTION:
APPROVED ✓ DENIED
RECEIVED OTHER
t€ETIN DATE /n '?ZSS U /
AYES: i/'(Ibtizne"fr/� ji(1yd one' Kaki
NOES:
ABSENT:
ABSTAIN:
VERIFIED BY: / //n
)riginal on File `i/ith City Clerk's Offic
G'\Energy Management\Pat Conlon\Staff Reports\CO#1 Civic Center PV System June 28 2007.doc
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose
Consultant's Name
Address:
Contract # / P.O. # 1 C23290C1 I 14017
Change Order No. I 1
Contingency: 1 YES I NO
Account No. 1 400-4511-4423-911
Project No.
Vendor No.
9976
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE
(Supplemental Plans, Specifications, and Directives dated Attached) In Contract Price
Install 192 Siemens SM-50 Photovoltaic panels, supplied by City, to Civic
Center main parking shade cover
Move and replace racking for existing photovoltaic panels on Civic Center
main parking shade cover
JUSTIFICATION:
TOTAL BUDGET FOR PROJECT:
Less: Expend. & Encumb. To Date:
Less: This Change Order Amount:
BALANCE OF BUDGET
REMAINING FOR PROJECT:
TOTALS:
NET CHANGE IN CONTRACT PRICE:
+ 562,993.00
- 512,879.38
- 96,254.10
(46,140.48)
CONTINGENCY:
Amount Approved by Council:
Less: Prior Change Order(s):
Less: This Change Order:
Balance Remaining of Contingency:
INCREASE
In Contract Price
96,254.10
96,254.10
96,254.10
The amount of the Contract will be (Decreased) Increased by the Sum of: Dollars ($ 96,254.10 ).
W \City Templates\City Word Templates\Forms\Change Orders and Amendment Forms\City Change Order doc
See reverse ...
Contract C23290C1
Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension Days.
Revised Contract Total $560,411.78
The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY:
DEPARTMENT HEAD
3. CERTIFIED
FUNDS AVAILABLE:
FINANCE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
2. ACCEPTED BY:
CONTRACTOR Date Accepted
4. APPROVED BY:
RICHARD KELLY, MAYOR Date Approved
CITY MANAGER Date Approved
W \C,ty Templates\Crty Word Templates \ Forms \Change Orders and Amendment Forms\City Change Order doc
See reverse ...
r4. Carlson Solar Electric Systems
43430 E. State Hwy 74 #F PMB-221
Hemet, CA 92544
1-877-927-0782 Toll Free
Bib To
City of Palm Desert 2
73-510 Fred Waring Dnve
Palm Desert, CA 92260
(760) 674-3428 Fax
(760) 837-0287
Estimate
Date Estimate #
6/11/2007 469
Quantity Description Rate
1 Removal of old racking, modules and conduit. 4,600.00
384 installation of 192 + previous 192 SMSO Solar Modules 125.00
384 Module Racking Utilizing anodized aluminum with stainless steel 75.00
hardware
1 Miscellaneous parts such as wire, me connectors, breakers, disconnects, 11,714.25
sub panels and ctc
The understanding that the City of Palm Desert will provide any
Structural engineering if needed and that performance or payment bonds
are not required.
This is a not to exceed estimate. Actual cost may be Tess.
Total
4,600.00
48,000.00
28,800.00T
1 1,714.25T
0.00T
Subtotal S93,114.25
Sales Tax (7.75%) 53,139.85
Total S96,254.10