REIMBURSEMENT AGREEMENT
FOR CONSTRUCTION OF
DRAINAGE IMPROVEMENTS ON GERALD FORD DRIVE
AND UNIVERSITY CENTER PROFESSIONAL PARK
THIS AGREEMENT is made and entered into this day of
2006, by and between the City of Palm Desert ("Palm Desert") and J.W. Design
and Construction, Inc. ("JWDC"), and is made with reference to the following
background facts and circumstances:
RECITALS
Palm Desert and JWDC desire to proceed with the Drainaqe Improvements on
Gerald Ford Drive, throuqh the Universitv Center Professional Park, and in the
Mid-Vallev Channel ("Proiect"). The "Project" will provide inlet structures on
Gerald Ford Drive and within University Center Professional Park, reinforced
concrete pipe storm drain, flap gate and outlet structures, grading within the mid-
valley channel, and installation of hardened weirs within the mid-valley channel.
NOW THEREFORE, in consideration of mutual covenants and subject to the
conditions contained herein, the parties do agree as follows:
(1) The "Project" shall consist of the construction of drainage improvements as
described above.
(2) The estimated cost of the "Project" is $340,480.00 (See Exhibit 1). Palm
Desert's share of the ProjecYs cost is estimated to be $262,810.00 based on
the percentage of the work physically located within Palm Desert's area of
responsibility.
(3) JWDC shall serve as the lead agency for the construction of the "Project".
Upon acceptance of the improvements built within the jurisdiction of Palm
Desert under the agreement, Palm Desert shall assume all responsibilities for
maintaining such improvements.
(4) Upon completion of the "Project", JWDC shall present to Palm Desert a
statement certifying its costs incurred in completing the work, and shall include
copies of the contractor's invoices, evidence of payment, and such other
information and records necessary to verify the payment for the work.
(5) Within thirty days of the receipt of the information provided pursuant to section
(4) above, Palm Desert shall pay to JWDC Palm Desert's share of the
"Project" construction costs.
(6) JWDC agrees to keep all project contracts and records for a period of not less
than three years from the date of the completion of the "Project". JWDC also
agrees that all such files and records shall be made available to Palm Desert
upon its reasonable request.
(7) JWDC agrees to include in the contract specifications and bid documents
prepared under this agreement a requirement that all prime contractors shall
name Palm Desert as "also insured" on all liability insurance coverage
required, and any notice of cancellation. JWDC agrees to provide a copy of
the insurance certificate within 30 days of the signing of the construction
contract.
(8) All notices or other communications required or permitted hereunder shall be
in writing and shall be either personally delivered (which shall include delivery
by means of professional overnight courier service which confirms receipt in
writing (such as FedEx or UPS)), sent by telecopier or facsimile ("FAX")
machine capable of confirming transmission and receipt, or sent by certified or
registered mail, return receipt requested, postage prepaid to the following
parties at the following addresses or numbers:
If to "Palm Desert": Public Works Director
City of Palm Desert
73-510 Fred Waring Drive
Palm Desert, CA 92260
Telephone: (760) 346-0611
FAX: (760) 341-7098
If to "JWDC": Jerry Williams
J.W. Design and Construction, Inc.
P.O. Box 1154
San Luis Obispo, CA 93406
Telephone: (805) 544-3130
FAX: (805) 781-3970
Notices sent in accordance with this paragraph shall be deemed delivered
upon the next business day following the: (1) date of delivery as indicated on
the written confirmation of delivery (if sent by overnight courier services); (2)
the date of the actual receipt (if personally delivered by other means); (3) date
of transmission (if sent by telecopier or facsimile machine), or; (4) the date of
delivery as indicated on the return receipt (if sent by certified or registered
mail, return receipt requested). Notice of change of address shall be given by
written notice in the manner detailed in this paragraph.
(9) This Agreement contains the entire agreement between the parties, and is
intended by the parties to completely state the agreement in full. Any
agreement or representation respecting the matters dealt with herein or the
duties of any party in relation thereto, not expressly set forth in this agreement,
is null and void.
(10) If any term, provision, condition, or covenant of this agreement, or the
application thereof to any party or circumstance, shall to any extent be held
invalid or unenforceable, the remainder of the instrument, or the application of
such term, provision, condition, or covenant to persons or circumstances other
than those as to whom it is held invalid or unenforceable, shall not be affected
thereby and each term and provision of this agreement shall be valid and
enforceable to the fullest extent permitted by law.
(11) This Agreement may be executed in one or more counterparts and when a
counterpart shall have been signed by each party hereto, each shall be
deemed an original, but all of which constitute one and the same instrument.
(12) Palm Desert and JWDC do hereby mutually agree to indemnify, defend, save,
and hold harmless the other and their respective officers, agents, servants,
and employees, of and from any and all liabilities, claims, demands, debts,
damages, suits, actions and causes of action of whatsoever kind, nature, or
sort, including, but not by way of limitation, for wrongful death, and for the
expenses of the defense of said parties, and each of them, and the payment
of attorneys fees in any such action, arising out of, or in any manner
connected with any act or omission of such indemnifying party, done or
performed in connection with such parties duties and obligations hereunder.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed by their duly authorized representatives on this date:
ATTEST:
By:
Rachelle D. Klassen, City Clerk
APPROVED AS TO FORM:
By:
David J. Erwin, City Attorney
ATTEST:
By:
Secretary
APPROVED AS TO FORM:
By:
PALM DESERT
By:
Richard S. Kelley, Mayor
JWDC
By:
Jerry Williams, President
EXHIBIT 1
CITY OF PALM DESERT PARTICIPATION IN STORM DRAIN @ UCPP
ITEM QUANTITY NOMENCLATURE UNIT VALUE COPD participation
% $
1. 510 If 36" RCP CI 1500 D 178.00/If $90,780.00 1�� $9�,780.00
2. 1 ea 7' x 4' x 9' junction
structure I. s. $18,000.00 50 $9,000.00
3. 140 If 24" RCP CI 1500 D 100.00/If $14,000.00 100 $14,000.00
4. 1 ea combination catch-basin
underwalk drain I. s. $45,000.00 100 $45,000.00
5. 1 ea H.S. flapped hydro- I. s.
gate assembly $33,360.00 100 $33,360.00
6. 1 ea conc. structure $42,000.00 50 $21,000.00
w. end ret. basin I. s.
7. 1 ea re-size -reconfigure
North retention basin I. s. $33,600.00 50 $16,800.00
8. 1 ea Additional weir @
east property line I. s. $5,000.00 JWD g 50 $2,500.00
9. 1 ea Gunnite @ weirs
10. 1 ea grade next easterly
weir to CVE supplied
new elevation
Sub Total
I. s. $56,740.00
I. s. $2,000.00 JWD g
$340,480.00
50 $28,370.00
100 $2,000.00
$262,810.00
Difference COPD/Development costs �$77,670.00 �
Vicinity Map
Gerald Ford Drainage and Mid-Valley Channel
The mid-valley channel travels adjacent to the southern boundary of the Union Pacific Railroad