HomeMy WebLinkAboutClosure of Monterey Avenue for CVWD ID 53 Trunk Sewer ProjectCITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: Report Regarding the Proposed Closure of Monterey Avenue for the CVWD Improvement District 53 Trunk Sewer Project SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works DATE: September 13, 2007 CONTENTS: Vicinity Map Recommendation: Receive and file. Discussion: At the August 9, 2007 City Council meeting, staff presented a verbal report regarding the traffic control options for the CVWD Improvement District 53 Trunk Sewer project. Staff indicated that the preferred alternative was to allow the complete closure of northbound Monterey Avenue as a means to expedite the construction. The anticipated benefit was that the work could be completed and the road reopened to full traffic prior to the Thanksgiving holiday, thereby preventing impact to peak holiday season traffic. City Council indicated agreement with staffs recommendation and made it clear that Monterey Avenue was to be opened to traffic prior to the Thanksgiving weekend. Since that time, staff has received a number of complaints from residents and businesses about the performance of the District's contractor and the condition of the work zone on this project. Complaints include blocked access to residences, unkempt construction zones, inadequate traffic control, rude behavior by the contractor, etc. Staffs requests to the contractor to correct these issues have been repeatedly disregarded. As a result, staff has lost confidence in the contractor's ability to complete the work by Thanksgiving while meeting the standards of the City of Palm Desert. Having gained additional information about conditions in and around the construction zone, staff no longer supports the proposal to close Monterey Avenue prior to the peak season and instead believes that this work may be more appropriately performed during the summer months. Informational Report: Proposed Monterey Avenue Closure Page 2 of 2 September 13, 2007 Alternatively, it has been suggested that the project be allowed to continue with the requirement that at least one northbound lane remain open to traffic at all times and the project be completed prior to the Thanksgiving holiday weekend. Staff is continuing to coordinate with CVWD to determine if this is feasible, with at least one meeting scheduled to occur after the filing of this report and before the City Council meeting of September 13. Therefore, the results of this coordination effort will be provided at the City Council meeting. Department Held: Approvals: ro,„ Mark Greerkood, P.E. Homer Croy ACM for Development Services Director of Public Works Carlos L. Orte City Manager ITY COU[..:IL ACTION: APPROVED DENIED RECEIVED OTHER MEET IN- D:i`iE CO-C) AYES NOES ::{ ABSEN i ABSTAIN v'ERI Pi ED BY : 7j-?,xinal on /dhl 116..11•sumx+mss�...wow..�y:a..�,*.,.+......a.Mua..+a..ANI+..wVOWN. b City <.ern ,, F W:IAgenda Items12007-Sept 131Monterey Ave Closure for CVWD Sewer ProjectlMonterey Ave closure for CVWD sewer projectc doc • Co f Ce..;•