CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
Approve Change Order No. 4 to Contract No. C25570A for
Assessment District 2004-02
Mark Greenwood, P.E., Director of Public Works
Skanska Civil USA West (formerly Yeager-Skanska Inc.)
1995 Agua Mansa Road
Riverside, California 92509
January 24, 2008
Change Order No. 4
Vicinity Map
The City Council, by Minute Motion:
1. Approve Change Order No. 4 to Contract No. C25570A with
Skanska Civil USA West for the construction of Section 29
Assessment District 2004-02 in the amount of $59,020.03;
2. Move $59,020.03 from contingency to base; and
3. Authorize the Mayor to execute the same.
Discussion:
On April 26, 2007, City Council awarded the construction contract for the infrastructure
of Assessment District 2004-02 (Section 29) to Yeager-Skanska, Inc., in the amount of
$14,470,270.58. Construction on Assessment District 2004-02 has been underway
since July 25, 2007 and progress has been exceptional.
On July 12, 2007, Change Order No. 1 in the amount of $97,076.80 was approved. The
change was necessary to meet technical requirements of the geo-grid material to be
used on the project.
Contract Change Order No. 2 was approved on September 13, 2007 in the amount of
$88,324.86. This item included modifications to both the storm drain system and water
line design.
Due to a change in conditions encountered during construction and the addition of water
line phasing elements not provided for in the initial project plans it was necessary to
bring Contract Change Order No. 3 to the Council for approval on October 25, 2007, in
the amount of $97,496.60.
Staff Report -Approve CO # 3 to C25570A 627-05
Page 2 of 2
October 25, 2007
Construction Change Order No. 4 consists of a number of different items involving
changes in field conditions, design corrections and material substitutions.
A recap of the items follows:
I1
Relocation of sewer clean -out
2 Installation of 4" irrigation sleeving
3 Concrete protection for existing storm drain
4 Installation of conventional asphalt concrete
paving in lieu of asphalt hot rubber mix paving
5 Catch basin removal and reconstruction
Total
$ 5,402.36
$2,442.64
$6,293.18
$42,040.41
$2,841.44
$59,020.03
Funds are available for these changes in the project account 469-4350-433-4001.
Although construction progress on the project has been excellent we are experiencing
some compliance issues with respect to rubberized asphalt. The issues are nearing
resolution and with the existing Southern California Edison transmission pole
relocations finally complete, steady progress can now resume on the project.
Therefore, staff recommends that City Council approve Change Order No. 4 to Contract
No. C25570A with Skanska Civil USA West (formerly Yeager-Skanska Inc., in the
amount of $59,020.03; move $59,020.03 from contingency to base and authorize the
Mayor to execute the same.
Departpngn.lHead:
Mark Gree'wood, P.E.
Director of Public Works
Approval
Homer Croy
ACM for Dev
Carlos L. Ort
City Manage
pment Services
:• TY COUNCIL)ICTION:
ROVED DENIED
.:.::K:IV.D OTHER
'0i* i4. i
P;upl�.
7' STAIN: Al
VERIFIED BY:
')riginal on File
- r7�
a) _I and balOrl
w h City Clerk's Offirc
Paul Gibson
Finance Director
/cls/dhl
G:1PubWorks\Staff Reports120081January 24103 Approve CCO4 Skanska C25570A 627-051Approve CO 4 C25570A Skanska 627-05 doc
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose Section 29 Assessment District
ConsultanYs Name Skanska Civil USA West
a,ddress: 1995 Agua Mansa Road, Riverside, California 92503
Contract # / P.O. I
#
Change Order I
C25570A/14156
n
�
No.
Contingency: YES I NO
Account No. 4 504334001
Project No. � 62]-Q5
Vendor No. �
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
In Contract Price In Contract Price
Relocation of sewer clean-out
Installation of 4" irrigation sleeving
Concrete protection for existing storm drain
Installation of conventional asphalt concrete paving in lieu of asphalt hot�
rubber mix paving
Catch basin removal and reconstruction
TOTALS:
NET CHANGE IN CONTRACT PRICE:
$5,402.36
$ 2, 442.64
$6,293.18
$42,040.41
$2,841 .44
- 59,020.03
59,020.03
JUSTIFICATION:
Relocation of sewer clean-out, installation of 4" irrigation sleeving, concrete protection for existing storm
drain; installation of conventional asphalt concrete paving in lieu of asphalt hot rubber mix paving and catch
basin removal and reconstruction. .
TOTAL BIAGET FOR PRO�IEGT:
�. •- • : .�"��1""• � �; -
• .- •.a � .
:� � • • : �
'� ' �1i �� y
+ 14,803,436.66
- 14,744,416.63
- 59,020.03
(0.00)
COMI NC�ENCY:
P�rna.nt Appro�ed b�r Couicil :
Less: Rior qiar�ge Order(s):
I..sss: Trrs Chax�e Q�der.
Balar�ce Rerrei r�i rg oF Ca�ti rigency:
� �,a47,o27.os
1,447,027.06
282,898.26
59,02(J.03
1,105,10g.77
e�
The amount of the Contract will be Increased by the Sum of: Fiftv nine thousand twentv and 03/100 Dollars
($59,020.03).
Contract C25570A Change Order No. 4 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension N/A Days
Revised Contract Total N/A Days
The undersigned Contractor approves the foregoing Change Order # 4 as to the changes, if any, in the contract price
specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in
work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change
Order # 4. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of
that directly or indirectly related to the approved time extension, required to complete the Change Order items. This
document will become a supplement of the contract and all provisions will apply hereto. It is understood that the
Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY:
DEPARTMENT HEAD
3
CERTIFIED
FUNDS AVAILABLE:
FINANCE DIRECTOR
NOTE: No payments will be made prior
; to City Manager and Council approval
i
2. ACCEPTED BY:
CONTRACTOR Date Accepted
4. APPROVED BY:
JEAN M. BENSON, MAYOR
CITY MANAGER
Date Approved
Date Approved
VICINITY MAP
ASSESSMENT DISTRICT 29
Project 627-05