Loading...
HomeMy WebLinkAboutC22310 CA3 Ramp Modifications @ the Monterey Ave Interchange CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: Approve Amendment No. 3 to Contract with RBF Consulting for Additional Consultant Services to Complete Project Approval Reports and Environmental Documentation for Ramp Modifications at the Monterey Avenue Interchange on Interstate 10 (Project 669-02) SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works APPLICANT: RBF Consulting, Inc. 3300 Guasti Road, Suite 100 Ontario, CA 91761 DATE: September 11, 2008 CONTENTS: Contract Amendment No. 3 Request for Additional Services with Fee Proposal Project Cost Worksheet Vicinity Map Recommendation: By Minute Motion, Approve Amendment No. 3 to Contract C22310 with RBF Consulting, Inc. in the amount of $278,362.00 for additional consultant services to complete Project Approval Reports and Environmental Documentation for the Ramp Modifications at the Monterey Avenue Interchange on Interstate 10, with funds available in Account No. 213-4389- 433-4001. Background: On February 12, 2004, City Council approved Contract C22310 with RBF Consulting, Inc. in the amount of $199,030.00 for engineering services to complete the project approval and environmental documentation (PA/ED) phase for the proposed westbound on- and off-ramp modifications at the Monterey Interchange on Interstate 10 (I-10). The ramp modifications consist of realigning the westbound I-10 off-ramp to Varner Road and inserting a loop on- ramp from northbound Monterey Avenue to westbound I-10. This will eliminate the congestion and queuing experienced on northbound Monterey Avenue for vehicles entering the westbound I-10 on-ramp. Amendment 3 to C22310 with RBF-Monterey I-10 Interchange PA/ED Page 2 of 4 September 11, 2008 On October 28, 2004, City Council approved Amendment 1 to Contract C22310 in the amount of $50,070.00 for additional services to meet Caltrans and FHWA requirements including CEQA compliance, a Natural Environmental Study, Biological Assessment, Acoustical Study, and other direct costs. On June 22, 2006, City Council approved Amendment 2 in the amount of $135,990.00 for additional traffic analysis, changes to project report requirements, preparation of a Modified Access Report, retaining wall advance planning studies, noise study update, milk vetch survey, cooperative agreement report, additional topographic mapping, and other costs due to extending the project duration. The contract between the City and RBF was originally negotiated with the aim of gaining project and environmental approval on a more simplified and fast-track basis. However, this has not transpired due to the delays in the review and approval of the PA/ED document and changes in Caltrans and FHWA requirements. Generally, a Project Study Report (PSR) is prepared and approved as a programming document that is then followed by the preparation and approval of a project report (PR) and environmental document. The scope of work and associated fee was based upon a combined PR and PSR. However, the fast- track scenario has not been achieved because of the following reasons: � Previous changes to the consultant, Caltrans, and City project managers caused discontinuity and loss of time for new project managers to establish a more realistic schedule, to become familiar with the project, and to deal with issues. • Caltrans has taken more time to perform multiple reviews of documents than originally scheduled. • Changes in Caltrans and FHWA requirements for preparation and processing of reports and environmental studies. � The combined PR/PSR has precipitated Caltrans' procedural hurdles that have delayed its approval. • The geometry of the interchange was modified, after approval of the draft environmental document, so that the loop ramp would connect to the existing auxiliary lane to Ramon Road. This required the revision of the preliminary plans, and the engineering and environmental studies which further delayed the issuance of the draft environmental document for public review. The above changes have had a significant impact upon the completion of this phase. What was originally planned to be a 22-month process will take approximately 48 months to complete. The draft Project Report, Environmental Document and related studies including air quality assessment, biological assessment, visual impact assessment, initial site assessment, noise impact analysis, natural environmental study, historic property study, and traffic study were finally distributed on July 3, 2008 for a 30-day public review period. Minimal comments were received and RBF is now in the process of preparing the final documents. Key remaining and important milestones will be the approval of the Modified Access Report and the Final Project Report and Environmental Document by FHWA. Once the Modified Access Report is approved by FHWA by October 2008, risk design and preparation of the plans, specifications and estimate (PS&E) can proceed. Amendment 3 to C22310 with RBF-Monterey I-10 Interchange PA/ED Page 3 of 4 September 11, 2008 The following is the current schedule for completion of project: Milestone Date Complete PA/ED Phase January 2009 Complete Right-of-Way Acquisition May 2009 Complete PS&E June 2009 Advertise for Bids October 2009 Award Construction Contract December 2009 Begin Construction January 2010 Complete Construction December 2010 Staff and the consultant have been aggressively communicating and meeting with Caltrans to obtain their commitment to 1) adhere to the agreed document and plan review times and 2) strategize and establish a schedule to complete the environmental process and PS&E. The federal funding on the project requires that we award the construction contract no later than December 2009. The City having already acquired the majority of the right-of-way needed for the project, the major milestone of completing the PA/ED phase is eminent. Discussion: Staff has prepared Amendment 3 to Contract C22310 in the amount of $278,362.00 resulting from negotiations with RBF for the additional services to complete the project approval and environmental process. The additional services include the following: • Revisions to Environmental Document and related studies • Revision to draft Project Report • Revisions to Traffic Analysis Study • Revision to preliminary design � Provide conceptual staging and level of service analysis and costs for Traffic Management Plan • Update Right-of-Way Data Sheet • Revisions to Modified Access Report • Additional and extended Project meetings and other direct cost including substantial printing of documents � Additional Quality Control • New tasks including Noise Abatement Decision Report and Air Quality Conformity Documentation Staff has determined that the negotiated cost for these additional services is equitable and recommends that City Council, by Minute Motion, approve Amendment 3 to Contract C22310 with RBF, Inc. in the amount of $278,362.00. The contract amount, including this amendment, will be in the amount of $663,452.00, or approximately 12.4% of the estimated construction cost. Amendment 3 to C22310 with RBF-Monterey I-10 Interchange PA/ED Page 4 of 4 September 11, 2008 Fiscal Impact: The total project cost has increased from an estimated $8.1 million to $10.3 million due to the additional consultant fees, construction inflation, and geometric changes. Staff has recently requested an amendment to the funding agreement with CVAG to fund 50% of the increase in project cost (see attached Project Cost Worksheet for details). Funds for Amendment 3 are available in Project Account No. 213-4389-433-4001. Prepared By: Departm n He�'�ad: � ��� W I� Joh A. Garcia, P.E. Mark Green ood, P.E. En ineering Manager Director of ublic Works Approval: /'.t�---� G����%' Homer Cr Paul Gibson ACM for D e ment Services Finance Director CiTY COUNCIL ACTIOTV: APPROVED ✓ DENTED RECTIVSD OTHER Carlos Ortega ��g��N DATE - -C� City Manager pn�,��: ,�� �V�C1�S: A��EY�`�': JG/dhl A�g��IN; v����a�D sY: � original on ile wi City C7.erk's �ffice CI� ����M DESElI�' Contract#/P.O.# 11404 Pi\Vl'L' A7SIV�L�i:J SE��LJJ Al�ii'y��NT AmendmenU 3 Change Order No. Contingency: YES NO Contract Purpose Monterey/I-10 Ramp Modification-PA/ED Phase Account No. 213-4389-433.40-01 ConsultanYs Name RBF COtlsulting Project No. 669-02 Add�ess: 3300 East Guasti Road, Suite 100 vendor No. 4619 Ontario, CA 91761 You are hereby requested to comply with the following changes from the contract plans and specifications: DECREASE INCREASE DESCRIPTION OF CHANGES In Contract Price In Contract Price Additional professional services to complete the Project Approval and $278,362.00 Environmental Documentation Phase including: 15 month delay in review and approval of Draft Project Report, Environ. Document and related studies including preliminary design, Initial Study, traffic impact analysis, traffic management plan, right of way data sheets, Modified Access Report, project management, meetings, and printing of documents, travel and other expenses. Additional requirements including: pavement life cycle cost analysis, soundwall noise abatement decision record, and airquality conformity a n a lys is. TOTALS: - $ 278,362.00 NET CHANGE IN CONTRACT PRICE: $ 278,362.00 JUSTIFICATION: Substantial consultant services were required due to the fifteen month delay in completion of the Draft Project Report/Study Report and Environmental Document and related studies/reports caused by the numerous revisions and delay in Caltrans review and approval and to address additional requirements noted above. TOTAL BUDGET FOR PROJECT: + 9,988,504.20 CONTINGENCY: Less: Expend. & Encumb. To Date: - 5,392,032.52 AmountApproved by Council: + $19,903.00 Less: This Change Order Amount: - $278,362.00 Less: Prior Amendment(s): - $19,903.00 BALANCE OF BUDGET Less: This Amendment: - REMAINING FOR PROJECT: 4,318,109.68 Balance Remaining of Contingency: - The amount of the Contract will be increased by the sum of: Two Hundred and Seventy Eight Thousand, Three hundred and Sixty-Two Dollars ($278,362). G:\PubWorks\Staff Reports�2008\September 11\04 Amendment 3 C11404 RBF for Monterey I-10 Ramp Modification 669-02\Contract Amendment 3 RBF 669-02.doc Continued on reverse ... Contract C22310 Amendment No. 3 Continued from front This Professional Service Amendment covers changes to the subject contract as described herein. The Consultant shall perform all work as necessary or required to complete the Professional Service Amendment items for a lump sum price agreed upon between the Consultant and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension N/A Days. Revised Contract Total $663,452.00 The undersigned Consultant approves the foregoing Professional Service Amendment# 3 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Professional Service Amendment # 3. The Consultant agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Professional Service Amendment items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Professional Service Amendment shall be effective when approved by the Owner. Execution of this Professional Service Amendment by the Consultant constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Professional Service Amendment, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, and loss of productivity, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONSULTANT Date Accepted 3. CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR JEAN M. BENSON, MAYOR Date Approved NOTE: No payments will be made prior to City Manager and Council approval CITY MANAGER Date Approved G:\PubWorks\Staff Reports�2008\September 11\04 Amendment 3 C11404 RBF for Monterey I-10 Ramp Modification 669-02\Contracl Amendment 3 RBF 669-02.doc Continued on reverse ... � ■ ■ CONSULTINC9 August 26, 2008 Mr. John Garcia JN 65-100103.001 City of Palm Desert 73-510 Fred Waring Drive Palm Desert, CA 92260-2570 Re: Monterey Avenue Interchange at Interstate 10 — Additional Work Request for PA/ED Phase Dear Mr. Garcia: RBF is submitting this additional work request for the Monterey Avenue and I-10 interchange Improvement project. As the project progresses through the Environmental Approval Phase of work, additional work effort, document format, environmental studies, and tasks have been added to the project work items. The project experienced a delay in Public Circulation of the environmental document of 15 months due to changes in Caltrans personnel, Caltrans policy, and NEPA delegation of the environmental document. By June of 2006, significant project milestones were completed (approval of preferred ' alternative, approval of environmental technical studies, and approval of traffic study) of which a project schedule was prepared, submitted, and approved by Caltrans. The following major milestones were scheduled: 1} Circulation of Draft Environmental Document— March 2007 2) Approval of Final Project Report— December 2007 3) Completion of PS&E—June 2008 4) Right-of-way acquisitions—August 2008 5) Complete construction —November 2009 Due to changes in Caltrans staff in the environmental oversight group, between June 2006 and April 2007, RBF was required to rewrite and resubmit the Initial Study several times. In order to : facilitate personal preferences by Caltrans reviewers, RBF staff spent over 10 days working at Caltrans with environmental oversight to wordsmith the entire Initial Study document. In May 2007, the Initial Study was approved and signed by Caltrans. The Draft PR/PSR was submitted for final signatures on 5/2/07, and RBF was completing the environmental public notice for ' circulalation. Public circulation was scheduled for June 2007. PLANNING ■ DE51GN ■ CONSTRLlCTION 3300 East Guasti Road,Suite 100,Ontario,CA 91761 ■ 909.974.4900 ■ Fax 909.974.4004 Offices located throughout California,Arizona&Nevada ■ www.RBF.com printetl an recycletl paper ' 8/26/2008 Mr.John Garcia Page 2 of 8 ' In June, 2007 the District Director instituted a policy of removing unfunded mainline capacity , increasing projects from traffic analysis. Along the I-10 through Coachella Valley, there are ' programmed projects to widen I-10 from 3 lanes to 4 lanes in each direction; however the projects are currently unfunded. Standard traffic modeling practice is to include RTIP programmed projects in traffic impact studies. This change resulted in a new analysis of the proposed westbound ramps on the westbound mainline I-10 lanes, which resulted in ' reconfigured alternatives to have westbound loop on ramp add the fourth auxiliary lane. At the same time, the existing westbound on ramp and loop on-ramp were modified to include ramp metering. These changes required an environmental reevaluation. Based on these changes, RBF was required to spend time to rewrite, revise, and modify the Draft Project Report/ Project Study Report, The Modified Access Report, the Initial Study, the traffic report, the environmental technical studies and project fact sheets. Several new tasks have been added to the work plan by Caltrans. These include the life cycle cost analysis for pavement, the noise abatement decision record, and the air quality conformity report. With the completion of the public circulation of the Draft Environmental Document in July 2008, the following are the current milestone dates: 1)Approve Final Project Report and Final Environmental — December 2008 2) Complete PS&E—September 2009 3) Right-of-way acquisitions— December 2009 4) Complete construction— December 2010 The following tasks are related to our Phase I work plan for the PR/PSR and Environmental Document processing: Task 1.4: Traffic Impact Analvsis Based on District directive to remove unfunded projects from the traffic model, the following traffic analysis tasks were required after the Traffic Impact Analysis report was approved in July, 2006. Additionally, analysis of ramp metering and re-configuration of the westbound loop on ramp to the mainline were added based on Caltrans comments to the Draft PR/PSR. • Modified merge/diverge analysis for loop on-ramp. • Modified mainline analysis without fourth lane west of the interchange. • Analyzed intersection of Monterey and Varner Road based on Caltrans comments, ' specifically the north Monterey to eastbound Varner Road free-right turn. ', • Analysis of mainline to insert V/C ratios in place of OVERFLOW values from Synchro software. • Analysis of ADT traffic numbers over a year after approval Traffic Impact Report for the Draft PR/PSR and MAR. • Analyzed ramp meter queuing for both on-ramps. . . . CONSULTING PLANNING / DESIGN ■ CON9TRUCTION � � 8/26/2008 Mr.John Garcia Page 3 of 8 , These tasks were completed between June 2007 and May 2008. Task 1.5: Preliminary Desiqn Based on results of the revised traffic analysis and addition of ramp metering the following additional design tasks were required: • Reconfigured alternatives to have westbound loop on ramp add the fourth auxiliary lane. Existing westbound direct on ramp merged into the auxiliary lane. Adjusted existing westbound on ramp and loop on-ramp to include ramp metering including 20:1 taper for merge on loop on-ramp. • Additional supplement fact sheet for 20:1 taper for loop on ramp. • Addition of ramp metering and maintenance vehicle pullouts from to southbound Monterey Avenue to I-10 westbound on ramp. • Revised geometric approval drawing and design checklist to reflect the above. • Several iterations, discussions, and meetings with Caltrans staff and Headquarters Design Reviewer to obtain approval of design. Task 1.6: Traffic Manaqement Plan New Caltrans requirements for Final Project Reports include a Traffic Management Plan and TMP worksheets. The TMP will include conceptual stage construction exhibits and cost estimates. In addition, an intersection level of service (LOS)analysis of project construction stages and detour routes will be developed. The purpose of the traffic analysis is to determine any traffic mitigation measures required for project construction. Task 1.7: Riqht of Wav Determination In the past, Caltrans has prepared the Right-of-Way Data Sheets for local projects that are located on the State Highway System. Effective October 23, 2006, Caltrans will no longer prepare the Right-of-Way Data Sheets for local projects and must be prepared by a qualified consultant. RBF will update the Right-of-Way Data Sheets for three (3) project alternatives in accordance with Caltrans standards. The Right-of-Way Data Sheets will be prepared as referenced in appendix L of the Project Development Procedures Manual to support the Right- of-Way Data Sheets. Per discussions with Caltrans, it has been verified a qualified ROW consultant will be required. In order to have the Draft Project Report/ Project Study Report signed in March, 2008, RBF made a commitment to Caltrans Chief of right-of-Way to update the right-of-way data sheets in the final Project Report document • Update ROW data sheets based on open market transaction of the required ROW for the project by the City. ; ■ .:: GON9lJLTING �� PLANNING � �ESIGN ■ CONSTRLJCTION � 8/26/2008 Mr.John Garcia Page 4 of 8 • Update ROW data sheets for required easement along Varner Road, opposite the ramp termini. • City of Palm Desert will use a qualified ROW consultant to update the ROW data sheets based on discussion with Caltrans on 8/08/08. Task 1.10: Proiect Report/ Project Studv Report Based on revised traffic analysis and geometric changes to the configuration of the on-ramps, the following tasks were required: • Attended several workshops to edit the PR/PSR with Caltrans planning and environmental staff. In addition, significant coordination was involved via phone/email to review and respond to comments electronically. • Revised the PR/PSR text to be consistent with changes in the Initial Study(IS). • Modified PR/PSR based on design and traffic comments from Caltrans Deputies and District Director. Revised the following: • Purpose and need • Project history and background • Alternative descriptions • Ramp metering discussion perpetuated throughout document. • Revised alternative exhibits • Revised traffic section of the document. • Included ramp meter queuing analysis The Draft PR/PSR was submitted for final signatures on 5l2/07. At this point the Draft IS was already signed, and RBF was completing the environmental circulation documents. Public circulation was scheduled for June 2007. Based on the changes in District policy, 12 months delay was experienced. The IS was circulated in July 2008. Task 1.11: Modified Access Report RBF prepared the Draft MAR in conjunction with the Draft PR/PSR in 2007. Based on Caltrans policy changes, revised geometry for the ramps, traffic analysis of the I-10 mainline, and for consistency beiween the PR/PSR, Initial Study, and MAR the following additional tasks were performed: • Revised MAR based on changes from Draft PR/PSR • Revised figures and exhibits , • Revised ADT tables and text. • Prepared category determination request � .:: CONSULTING �. PLANNING i OES�GN ■ CONBTRIJCTlON � 8/26/2008 Mr.John Garcia Page 5 of 8 Task 1.12 Life Cvcle Cost Analvsis for Pavement(new taskt Per Caltrans Memorandum dated March 7, 2007, Life-Cycle Cost Analysis for pavement shall be performed and documents for all projects that have a project approval date of July 1, 2007, or later. RBF will utilize the Interim Life Cycle Cost Analysis Procedures Manual, Project Development Procedures Manual (PDPM), and the Highway Design Manual, Sixth to prepare and document life cycle costs for pavement. RBF will develop three (3) pavement alternatives and determine the pavement design life of the alternatives. Each alternative will be analyzed using Real Cost software provided by Caltrans to determine the initial construction costs, project support costs, future maintenance, rehabilitation costs, total agency costs, user costs, and total life cycle costs. Each alternative will be documented and attached to the Project Report per Appendix 00 of the PDPM. Task 2.6.1 Noise Abatement Decision Report(new task) Effective August 2006, per the revised Caltrans Traffic Noise Analysis Protocol, a Noise Impact Analysis, a Noise Abatement Decision Report (NADR) will be required during the PA/ED phase. The report will summarize the preliminary reasonableness determination from the noise study report; present the engineer's cost estimate for the evaluated abatement, evaluation of nonacoustical feasibility issues, preliminary noise abatement decision, and secondary effects of abatement(impacts on cultural resources, scenic view, hazardous materials, and biology). The NADR will be prepared for the proposed soundwall along the north of Varner Road, ' adjacent to the mobile home park. Task 2.7.1: Air Qualitv Conformitv(new task) ' Based on (SAFETEA-LU) Memorandum of Understanding to streamline the NEPA review process, in 2006, NEPA delegation was provided to Caltrans except for air quality provisions. FWHA developed separate stand alone reports to be filed for NEPA environmental documents. Air quality conformity determinations, both regional conformity and project-level conformity, will remain the responsibility of FHWA California Division for all projects assumed under the NEPA Delegation Pilot Program. The Department will send FHWA, separate from the environmental review process, a request for conformity determinations. In this regard, FHWA will be treated much like other federal resource agencies. FHWA's requirement is that the air quality conformity documentation submitted to FHWA be a stand-alone report using the Conformity Analysis Documentation Checklist. The air quality conformity documentation must include adequate summary information such that conformity determinations can be made on the preferred alternative without having to refer to the environmental document. A copy of the FHWA conformity determination letter must also be included in the final environmental document. The stand-alone report and Conformity Analysis Documentation Checklist was not required prior to NEPA Delegation, and was not anticipated in our original scope of work. . . . CONSULTING � PLANNING ■ DESIGN ■ CONSTRl1CTION 8/26/2008 Mr.John Garcia ; Page 6 of 8 Task 2.9: Environmental Documentation RBF had completed the Draft Initial Study in summer of 2006. Two review period submittals of the IS were performed between July 2006 and January 2007 as was expected for a typical ' environmental document for similar projects. A schedule was established based on approval of ; the Initial Study to have public circulation in April, 2007. Due to changes in Caltrans personnel and reorganization of the environmental oversight group in District 08, the following additional tasks were perFormed for the environmental work program: . Attended numerous workshops to edit the Draft Environmental Document (DED) with Caltrans planning and environmental staff. For a 5 month period from January 2007 to May 2007, RBF staff spent over 60 hours at Caltrans working hand in hand with Caltrans reviewers to rewrite the document to meet Caltrans preferences. This is not normal procedure, and is not the role of Caltrans oversight projects, but was performed in an effort to maintain progress. • Coordinated electronic revisions with Caltrans reviewers. • Prepared and approved the public noticing in June 2007. ' • Approved the DED for public circulation on 6/29/07. • Revised the approved DED based on changes of the PR/PSR between ' September 2007 and April 2008. Caltrans performed environmental revaluation of : the document. • Revised approved public noticing in May 2008. • Revised all technical studies in April 2008, including the Air Quality Assessment, Initial Site Assessment, Noise Report, and Visual Impact Assessment based on changes on the PR/PSR • Prepared and approved Errata sheets for the Biological Assessment (BA) and Natural Environment Study(NES) in April 2008. • The environmental document has completed public circulation per CEQA requirements. RBF is currently responding to comments on the Initial Study, this will lead to a CEQA Mitigated Negative Declaration (MND). The NEPA approval process has yet to be accomplished. Since FHWA approval of the MAR is required before the NEPA document can be reviewed, it was determined by the PDT in 2006 to split the process for separate CEQA and NEPA approvals. Since 2006, NEPA delegation has been granted to Caltrans. Several additional reviews per the NEPA delegation process will be required for this project. The schedule for these activities is between September 2008 and January 2009. It is assumed during NEPA delegation reviews and process the approved environmental technical studies will not be revised and are sufficient for approval of the NEPA environmental documentation. . . . CONSLJLTING � PLANNING ■ DESIGN ■ CONSTRLJCTION 8/26/2008 Mr.John Garcia Page 7 of 8 Task 9.0: Proiect Manaqement/ Proiect Meetings 1) Project Management In 2004, RBF originally scoped this phase of the project to have duration of 15 months. In 2006, AWR No 2 extended the project an additional 15 months. The completion date of the PA/ED phase was scheduled for December, 2006. Due to the change of the document format, changes in Caltrans personnel and policy, the schedule has extended an additional 24 months. Based on current schedule, the PA/ED phase will be completed in February 2009. This requires additional 24 months of project management activities. 2) Project Meetings Caltrans, the City, and RBF have attended unanticipated focus meetings outside the regular ' scheduled PDT meetings to discuss specific topics to move this project through the Caltrans process more effectively and efficiently. To date we have attended approximately twelve (12) out of scope focus meetings, in addition to the 24 additional PDT meetings due to schedule delays. We anticipate attending 9 additional meetings in the future. These additional meetings have supported the momentum to keep this project moving forward with Caltrans staff. Task 9.5: Qualitv Control RBF will continue to perform quality control on documents being submitted to Caltrans. RBF utilizes independent in-house reviewers for third party checks of documents. RBF will perform additional quality control checks on the Draft and Final Modified Access Report, Draft and Final Project Report, and Final Environmental Document for the 24 month schedule extension. Reimbursables The original contract budget for reimbursables was $7,200. Amendment No. 2 added $6,000. For each submittal to Caltrans of the PR/PSR, 20 copies were required. The PR/PSR was submitted 4 times between 2006 and 2008. For each submittal of the MAR, 5 copies were required. For each submittal of the IS, 12 copies were required. The IS was submitted 5 times between 2006 and 2008. To date, RBF has experienced a total cost of $35,000. We anticipate an additional $10,000 to complete the final document distributions. We are requesting an additional $30,000 for ` reimbursables. � .:: ' coNsu�nNo PLANiJING ■ DESIGN ■ C�NSTRl1CTION 8/26/2008 Mr.John Garcia Page 8 of 8 Fee In summary, RBF Consulting is requesting a net increase to our contract in the amount of $248,362 for labor and $30,000 for reimbursables. This adjustment is necessary for completion of work tasks associated with the Final Project Report and Final Environmental Document certification through the NEPA process. Should you have any questions please contact me at (909) 974-4935. We look forward to continuing our efforts on this project and its successful completion. Sincerely, /� '' ��������`�.� � G Jeffrey Fromhertz, P.E. ' Project Manager Transportation / Public Works Attachments cc: Brad Mielke Steve Huff H:\Pdata\651001031Admin\contractlammendments\PAED_Am mendment_003.doc . . . coNsu�TiN� PLANNING ■ �ESIGN ■ C�NSTRIJCTION � � X N N � O O O O O O � O O O O O O O O O O O N O O O CO O O O O N O N ti O OJ � M N 00 N � � N (O M CO t0 O �O c� � OO � 00 � CO � M V^ V' tt I� 00 M O M p N O O � � (fl � O � OJ M � OO O �0 Z N E� M � 'V' � M � N EA N � � a <R 4H � E F a O m H � � O O O � `N � � O O �N � � O O O O O O � O O M N � O O O � � � = T -� C N O O O O � 0 0 o E � O O O y m L!) � Ln U � 69 fR (a (I) C 0 U C O O O O O O tt O O O O O O O O O O O N O O O CO O O O O N N �� � Cfl N N a0 00 � I� � N M N � � � M O 'cY (O O � lf� 1(� tn � � t(') Ln � O f� � M tn f� f� n m W cfl N ao ao � � o Z o G� � � � W � � � O � N � 00 (�O C�O � N � � N � � a M S GO <O � L � Z � 0 � 0 � � � � � � � � � � � � � � � 0 � � � 0 � 0 � � � O O d� CO O 00 � aO (O O O N c0 c0 � � O a0 � N u") N � N (D M a0 N !� CO t0 Z � � � `t N oJ N � V N � M (O � CO � � W W W W � � �N � y � Z O � Z L � a a W O � �N CO � � a�O M � N N N o�0 d�' N aN- � � W = �n �n — W � � N Q o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 =� w a ao co 0 o ao v o 0 o c� ao 00 Q � � � � M V N N M N I� O> O) W � j � W � N �t C'� � N � CO � (D M 69 VT Z Q � � O Z > tL Y W C9 y WO � y W = � � M N � CO � � �t (O � N M M W V m � � = o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Z a0 N I� O 00 V 'V' � �t O � � � t(') V N M I� V I� h I� 'd� a0 V � e- � _ � � � � N M r- �t � � M M Y W � � tR fR � H � a L n' � � o ao N c� � w v �r � v o v rn rn = N N o� N � c � � o C N � � f0 O O O � V C � (6 y �a �, � � C �1 � � Q p C tvi� o � c � � y in 'a N c � N N � p UO N a j Q � f0 (0 -p � � .� � f9 f/� �<n � H c � c �� � � � y a >, •o � � 'c� c � y -o � c�o �. � � E v� � � � a � c � o E E � a�i c p c� a� a� a� � � 'co � c :: c� Q c •� E a� .S u`�i v� Q °� c : � � o v`�i � � p R � � .E Q � a� o � Q m y � � � � c m Q � � N L7 >. � m a� � � � >, � � � c� o Q � o � > � � v�'i E m � � a� co m a � U �c w � U c � J � W L � d a Z' � �0 a � c� m U U1 Q o c � @ W � Z o a�'i ° °� E c � � °� _ � � c�i Y c�i � a � � ,� � V � U a�i :a N � �' 2 � � � — o � � d a� >. � � �t3 . Q � � c � � o � J -� � � .� � r � � ;,_, U a�i a�0i � °' � �n � � o � •� H � Q � � o � '� � cLo � c`a o� � a�i � o ,� o � w o � � .o d �o •� o = o ; .� O � � N � Q (n H � f- �' Q U LL � J � Q' d CD = Q Z Q .� W d C� U fA Q' F- � � N M � � (O I� N 6� � T � � N M V' t17 t� � � a0 6� O � � � N N N N N N N N N N � � a o C €O 0 � °f O � p0 i c � .� � `-' « u'i :',. O �y N . 00 N z a ; c Gi o N `o : O C -p ��i 'U N � c .i:'�O Q �' . . E ' v vy 'ti � °' � ' � d a '' � �, ro � E a`, v c o d y - m � c V U � �''.. � � VI 41 y� d p m Z E ,a � a � .' � c > ^ O —O. O m' � � � ���� C C � `w ,� c O- « � ;�:..L � d y a ''�. O U1 ` '�. a NL � lLd �o cnn , c v � d L d � � ° o ;F- Q d Q g �---�-g—_r_ ..� ....�.....p�� �_. o .'�0 .•003 ' oI ( � �� :o � � � ; � � � o€ � ooi � � � . o 'o �o ; � .n .03 0 .o � �0 1 � � o( �; o o � fo �o (o3y E — i � O � � � .p ; �O O r .O -�[p r z s k �O •t ; � ` �1� I� . k � a�� ll ��fC M O � v1 ;�"� ��i � . � N � � � I ;o �: O I � O�� s O � � � � � i O i� w � ; € J I � f" € �� ��(� ; F � � I� � '' i 1 ? � ', ' E E� � 3 � i j ' � � E u� tn t Fn€er �r w:s�r�ur ut Fn'w v� �r r�r'�sr i vr w w w�, �w; �sr ef'�w vr rr vs�v�j vs�; � ,...._.,..j,.......;<....... � , ; � � i � � (( ' � � ' � � � � 3 ";'i'--. , �._�.._. � ��(I � ,.� ��........ _�..�t; a 'f�1 � � �.M. � jI M � � � v :.N � � ] � � i 3 N � I � � l N � � ! � u ..� � � �� � ��� � '�.lL � I.LL� � I II �LL s ( � �� E ? j � ;_ vs vs;v>�v� ��w rn es w _v��w _ vs v�r eR vr vr rn � w� v1(� ���`j3 � __.,...�_... ._, � � _ .. W: _ _�3 . �i . _ e . �q .y. 3 Q � � � ; � � � � i � 3 � � � i�i � � � 1€[ E�.. � � � � � � o , _ , e e � � � ; : 9 . 7 � ��� € : i :N ; � ;. j � ,. � 1 mm ( . " � �€ ; O _ - � £ � N ' €� 3 3; 'N � � € ii � t � _ � � � � � _! ° ! � � j� _ � � ' ! ,; � � j , � , � � � � � � � ���.LL s�LL ? � f# 1. :LL � � � w � ; � a � �� �� � 1 i . � � �IfJ�H�:ff}�IH H! fi},Hi�ffY ffl�ffl�N�� N� tFT�fR I W�V} (fJ �N �� W� ffl ffl�Nl 69 fR'H!.Vf-�; � ._........._...... ....,....�. ....._...._._ . ......--e �_.w..:� mm�..� fN � � � � � , � � � i � � �! � � � � � �� � ��� r O — � � � 1 � 1 ' ' y�.............. _ 3 � '�� 3� — �� �_ ' � � ' � ( i � : 3: � ar.. �..� { � � � �I ! �.p' j �E, �:.O � l { � � . � [ i t � i �� ; E ' — ; � � N � � � r j i € ;j ,� I y Q" LL ° � I � � LL � . � �{L � � ? `o � i € a vs rn�vs e� vi ss�vs;re �rr rn�w bs vs �i s4 u4 vs vr w ��w��'. v� w�l» rr� v► w f s�r w � � � � ' � � ; E i � i � � � E � :� i � � � 3 ¢ � � 1 1 . 3 � E , O O O j O �; Q � ,�� ' � 3 :0 , � ! € �� O O � � O O p�; � 0 � ; O�' � � ij j ; � ' [ � �( � � � N � •�O 3 ( . � � ...0 I � 1 YE 3 :, `0 N �� I � M 00� i � .'„ I , E 3 ;} � �E I �' ` �i � i i � � s � � � � 't i .. LL . � s = i ' ' � '" w er I�rr �rr vs en vr rn ar`vs:w vt w ar:ar vr ef vi wE� �v►�� vf v►� `� vi ._� ' .....,. L r . � i fR < � — �, __ ..... ,,._ Vf Hi fA;tA .. a �� .� , o E , �� , , �o �� , , ;��E , , , ��o�� o o ; , , , , . �O �O � O 3. ,i.O 1 p { O O O 3_.__-�O-r! � ..O� �p — t � �,D i :O�� : € ,€O� ��.� O Ow� t I O i o � � 3 � � 3 �n jo o i IoE� ' E� � � � � Emj'> � � N 7 ! �— 3! iM ;CO . 'Me 'pp N N 3 (((V' �+ �� — � { �� �� ; 0 3 '� N N � ; [� i i £ � � £ O + LL I i LL f � •- ;LL ; ' j � ° � � � ;: fn -rr vs uq vs v>,a► w ss s9 vr u� Fn v� ug ss vs vr� w w, w:� __ _._ � �_ t � � _ �__ � ���.._; _ _� _ _.� �_ m .. � � __.._.._._.....__._. m � � � � � � �' , 3 l . �O (�: � p i in:� � _ ._�.m. ...y.. �� : .... ... . ..._�. H � � ;.LL I � � I "jF" .�y � F�� °V �V�i �{L j 3 (� _ � �I.......,. ._:,,_......,... . ..� � .,,.. � ._< � --....___._.. �.................... _ ��� �.......,..,,� J(k �� � t � �� �.. t � � Q � � 3 4 � � .�._;0......... � ;O � ` �i, � :� ' j(E � "3 E y I 3 ! 3 € £ 3 ���� � � � � � , ' E E� ,� ^3 N� � E i � � � N € !E, �a. � ' � ( � € 3 �.. Q 2 � � � C �' ( � H GI� � 9 LL � :3 � Yl 6 N N � �^ O y U C a+ � N � � '' �p� � : u�'i�. � { p V i �: �1 O � LL � I � �_ � .U`( � 1 e � i 1 Cj U c U � � �� � � � '� = ( Qa� � ( i o w �+ c-> s . � � � � 9 ' � _ �'� N E �. C LL � � 9 C � y � L i�[ C L C d �s a+ a+ � ti �i0�I 3 c C C �. o� � d �'a,( d O j '� � � � � � clj � Q o °' �i '" '� � r U; � 47 1 C Gl . y i W ii � C °�' d � a '� i�'a�'+ c a�+' �' ,�y •�� L c � , �� c ; ' � N > � a i o a �.. ; � i c � � �._ o ; a a+ i i; W E O Q 9 �! O L as+. ��td y y�G U y i! . � y y� 1 9 H f I W �� d d I LL'U W Q i U U O; ': E � Q � O � �.�.:! ��, U f !�. Q U 3 F- :i L��: �_. .�°#; ' � � i �Sn �,4 � ' �'���`' t�6��'���?.., k." ��� E c H', ' � 4,t; r�.e .e '. .. � .� ���. � •� ' ,rxa.'�v ,; ,v f '� �. ',:. . . .. , ..�. ��'3 ..: .. .. ��^^� �' � ,j�: ��.n ry � ��.. . �$ �� .. .. .... g � � ��, �. _ i _ ��`�i.��i�.'.. �a � q. �. • . ,.,�;, �: :u ��.; �.� [ y9 �. t � . „ $ ,.:. , '.'.� ' � t? � t � c"- r.� �x:*�-x'. y��'.. `�. �'�.`"��:{ � �� , � �y �';�� i' � ., r�r s� ' ' �'�i.. ;; �'�; ,�,,., �1�� � o P*. �,� ^�s�=r`"�. o- : {� '�,;:. : .+ � �.,� ��,�,�� � e'§+.",. � �� ,... �' �u � " `_'�'��, . �;,. - �a���., •R ■� �, ��#�`�s� ��`k ` '' . r �� �r�a'fi{@Nh `�ka } ...� .- _+". � * ^�i', � . ,... b�, � � � �,�„�- . 'b . ..:;�n . .��1 u '; � ..� t. ��n.. i ... . � f+lr{�, ,' :, U S� * �r ��*�n �r�vt � �'�'�„�, �v��-.�'ie�' ffi ..�� ..p. II�IIII� II,. .rF.�� �-� �r4.2yT�� 'o��. ��: �. ��. ' .. u { g , .. - � �.�,� .� � ' ,� g .,; .. ,� . �: � .�.._ .. } ,.. .. y � 3� �""'�' va. v�s�* '.r � �,�i.,.. ,'a�'' ��' �' �� "`�,' � . ` �i �f�'` � s: s ��3 y�#i �.� z ��.t.�z�� yp ���f:{ � �, �� y � ��';�x n� '` ��`5' � t ��'�:'3.` d�'' � �#�F«. � �:'� $ *��"`��:: � +�� �� P C '.. '�� t. .. 5 £�y���y , ,`' .t y' . !V`.i � �'W',�ti`1� 'kr^, �'?- � s".�''� { ir y �.���. R i ,�� ! _ �,j��� :�F��� �� �`�"� s � . � ,A � � ,�ai�qi �w '�� ,� ��� r : r Ad�d�uwo ��.�. �, }�" �; K.�q �� kc� �� r F�' .�.` �B�' ''�.-,a`s, � ;�A.��� � : , ��., s�.X-� a ���. � .. :. . ' r4.'; , �` . p '�' ' � . f.n.= ,� e �.< t.` �. � , _ ` ,: � m a. � " � �� .�� �� � ,.m.` ,,7 ��, . , r �' . �uc�., � '�' � ' � m��� '� ��,r" ' + ,. ����. � ��. � �����, �'���`'�.�. �. � € � ����'�� ,� �" � ��:: 1 ��;'?:;. �. �� d� e� � � � ,-. mndS,t �s ..t�. ���' � . k �, _„ ql �'_,.., 'Y�, ' �.� a: � �a �fi���� ,� "�, , , ,.y ;� W r,� ,�.. , ., � r � ���� u��� � ��' � v � \�'' �� { t-�-,-�r s' y�z.�� , � u � .. ,� �� �:�; �-"' >�� � � � ° ��m �', a ial ��: 1 Y'n�, �. u 9YE67C..w,: �� c P �" � „ +'�"�*�? �'S. ,�+ J� i, k � r' i� � ..w, t� �� 1 I �1 �. I�li7� r„ M� �� k� �� r" �.���, .: . . ���� � ' �r ,�� �� �� . ������ � � � .. �%"'� � U *��� �� J��/� � y� � �`� :{ {)RiJ R� � ' �t �;,� k. . �py l� �yer +�tir m �e i� � 4. "�'�' 'S'� S' 'f.+Jf. �iks,. � � f . � i ".�'. r, ;�� ����'�i � ��. �I J Y�4�. I a �F I� s t. vY'J Po�I < � i{{ �, • � ��� � ..� , . < �1�Cal g�� � .,.; l�� �H � . . .. 1 1{� �� �5 W� �i,{ � y " E �l!8t16� �.� �� 2 Y �� ,� ���f'' I' M, �': xn�a�.� '���� �c�t �:. ,r�, �,I��'� I��� ��`:� � �� ��f � : � y � ' . �u � �� � �,� ��. . q ., , �'�� � � >s'' t�, qr Y-� �,'� � � �.;� � c�c���� � ,��� �� � "� II � r2� � r,.t' F� "° l� 7�Ad4fi1 '�"k""?`k L�' � �� �-��,�'a�,..- �� � �k tlI��& �` xc ,� � � . e� � �a �.. ,;..;- -8 c �� i3Jt��:LE �f��.,� �„ �, �..w� � �°.,�;�- tw'� '� � v..#�f �� � �.�v � �`� �.,� {' Y�' Y� �� . � , �7 5k�� c:. * . , ' ,"7� �°�. ,^M��s�F , h:� � �::<. �� Yry . .�},� �r.; 1;�t. � s. �� �> '� �•,�� ��� �e � .� .� * �-� �`� ����`� a.', � � � �k�� ��f � ,��" '��r rr n�a yr�`��u ��,����� r ��`�°�'� f�9��� ,�� ��� �; �`t, {�� ,��,��� r,, ,.� � ';� � Jr'�� � s �,��"� "� r .`_ ,�� '�� _. � ������ �h� r�� � ` � � a � �� ��� � � ��� �� ����� � ���� �.� �� zf` :� �� � � � ��� ar � � � ��� ������ � � �� �y �a+�� � �' �� {� ,� � m � � ��<�" �, �� � � �`�,�F =y�,� z � ��� � � � � �+�� '� �� � �1' 4���\ 1 ������ „ t �.�� �.,� �.:.� " �. � a t �c� �� �� ����� ���� ���.. . . . � � k y $ � aq1{ � 3 AT�'s�&i�AK.± �4 �F� �,�y _ . � �`� �i"� ���" r�� r ��'.. �� , U"`;;� ��.,.�..'� s i t" � L, .... . ,$ S ; �i�}t,!a �. �g: � � r� � �� �� x � ���.����� . t � � � �,}.� '��;�� ' s� � . ��"a��,�3 p:�v��. t �t� '�fi� • '�,, � w ;�� � �.�� �;Wr,�� '�` :.�x�'`'� yp. , r } I ,. .. �' n` � ���m�$� ' � � � . � �s v. .:r�z � w.....�.. h,k � �, �� x � ., �' ��'�sk= . � . � �� � �" y �, .�v:. �'�r��`� '� "� ��l �� ,,.%, .�., $�,.+,a� `'���� �., it' . ' � � � � .��a � � ry ���t"�� �1 .�c§� ,.�,. , x �., �,,' �'z � ` � � �;���g��� 7"� "}, � v�` �s i� fi:,. �.. � '�"'�'"�,�. ��F�.r�f'sr� .;��`�� ��� . � ' ; �.. =.t '�" � � � 1 � �II �`'��s. r. K .: � � � �#x ' � � ' � . sJ�����. :,� �� a � �. ��' , � ,�a" � 7�� h � .ru�`n�v 3 � > s� 1�; v� i 5 � f '�' � "dc. ' � l ?, �� j� 5,f d. � ., � � .. .. ��?��i'�. y. �A1 � t� � §y. r. FS 4�'�, x.. � '�- 5 ' w�`y���5�. ,� � ��'w :,.�p. 3 F�s��a b;jS �.£�?fj�4T ��� ,�. � ' � ,� .� � j k�Gfv�r:.� 4, ..;�� � �'�5'�'�' ,. rr� � . '@._ �"`:4 �2�,�t$�t 1${t ...� .. �; . �'2t� �� '�' � � ��� � ��,���� �i� � ��� ���.= �,��.��,��¢�`�, , x " � Y N, � `�` � � � �� �i x �: ,��� ,.� �. ;..- r ' �x� ��'�71 a� � ;� �� �F �� �� � �y e, _. � �:`.� �.�, � �- x �� '� � � �`'� y%� ir � � �M������Il�{�. ��'� ��� . $�, � �. f � ��� '� � ,� � �' M r ,�.s'�`'+..�t� �ua„+�.:a.. � �f `Y{� � .1� f ;�;§,�# �� �� . �`� ;x r � y� �. �� . X: � a�, g,� a�' §`' ,+ �� ��ffi� � � P ..� � � .�k �.. I 1^��+Y��. a":� g 4y�P�� �v,�, ���,� &" A�� •� � �"i Y�'. x '� .7.i� '..;' "' � � .��x„ �:�.: ' . � . . .Y.� �'".:.... � �..r,� ..._. �