CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: Approve Change Order No. 1 to Contract No. C28030A with
Contreras Construction for the Country Ciub Drive Curb Ramp
Retrofit (Project 619-08)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
APPLICANT: Contreras Construction Company
81-149 Indio Boulevard
Indio, California 92201
DATE: February 26, 2009
CONTENTS: Change Order No. 1
Project Cost Worksheet
Vicinity Map
Recommendation:
By Minute Motion:
1. Approve Change Order No. 1 to Contract No. C28030A in the
amount of$10,009 for the Country Club Drive Curb Retrofit;
2. Authorize the transfer $10,009 from contingency to base; and
3. Authorize the Mayor to execute said Change Order No. 1.
Discussion:
On September 11, 2008, City Council awarded Contract No. C28030A in the amount of
$129,600 to Contreras Construction Company of Indio, California, for the Country Club
Drive Curb Ramp Retrofit to conform with current Americans with Disabilities Act (ADA)
standards.
During the course of the project, three additional curb ramps were identified as requiring
truncated domes at a cost of $2,400 ($800 each). There was also 1,087 square feet of
sidewalk identified as being non-compliant with the ADA thus requiring removal and
replacement at a cost of $7,609 ($7 per square foot). Including these improvements in
the project will bring the curb ramps along Country Club Drive from Washington Street
to Eldorado Drive and from Portola Avenue to Monterey Avenue into compliance with
ADA.
Staff Report
Approve Change Order No. 1 for Contreras Construction (Contract C28030A)
Page 2 of 2
February 26, 2009
Funding for these additional improvements is available in Country Club Pavement
Rehabilitation, Account No. 400-4311-433-4001.
Therefore, staff recommends that City Council, by Minute Motion, approve Change
Order No. 1 in the amount of $10,009, move the same amount from contingency to
base, and authorize the Mayor to execute the same.
Prepared By: Departme t e :
i �'✓
�.
Aaron Kulp � Mark Greenwood, P.E.
Associate Engineer Director of Public Works
Approv :
Homer Croy Paul S. Gibson
ACM for Devel ment Services Finance Director
�
sti McCarthy CITY COUNCILACTiON
Actin City Man er APPROVF,D—�
DF.NIF,D
/bl RF,CEIVED.�____�_OTHER
MEF,TING DATE ' - �
AYES: J o i � �� �>
NOES: n��ne,
AI3SENT: /1�0�e-
ABS'I'AIN: �✓l
VERI�IF,D I3Y: E
Ori�;inxl on File w�ith City Clerk s Oftice
G:IPub WorkslStaff RepoRs120091February 26104 Country C/ub Pavement Rehab CO 1 for Contreres C28030A Projed No 619-081SR Approve COtil for Cont�eras to
� C28030A.docx
��� � ������5�� � Contract#/P.o.# C28030A 015710
{� T Change Order No. �
CV�������`�� ����� � �� ContingencY� YE NO
Contract Purpose Country Club Drive Curb Ramp Retrofit(Project 619-08) Account►vo. 400-4311-433-4001
ConsultanYs Name Contreras Construction Company Project No. 619-08
address: 81-149 Indio Boulevard; Indio, California 92201 vendor No. 166
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
Su lemental Plans, S ecifications,and Directives dated Attached In Contract Price In Contrdct PriCe
Installtion of ADA Compliant Curb Truncated Domes at 3 additional locations 2,400.00
3 ramps at $800 perramp
Removal and Replacement of non-ADA compliant sidewalk 7,609.00
1,087 sqft at $7 per sqft
TOTALS: - 10,009.00
NET CHANGE IN CONTRACT PRICE: 10,009.00
JUSTIFICATION:
During the course of the project three additional curb ramps were identified as requiring truncated domes at a cost of
$800.00 each. Also 1,087 square feet of non-Americans with Disabilities Act (ADA) compliant sidewalk were identified
as requiring removal and replacement, at a cost of$7.00 per square foot. Including these improvements in the project
will bring the curb ramps along Country Club Drive from Washington Street to Eldorado Drive and from Portola
Avenue to Monterey Avenue into compliance.
OTAL BUDGET FOR PROJECT: + $150,000 CONTINGENCY:
L�ess: Expend.& Encumb. To Date: - $129,600 AmountApproved byCoi.ncil: + $12,960
Less:This Change Order Amourit: - $10,009 Less: Prior Change OrcJer(s): - $0
BALANCE OF BUDGET Less: This Change Order. - $10,009
REMAINING FOR PRQIECT: 10,391.00 Balance Remaining of Coritingency: 2,951.00
The amount of the Contract will be increased by the Sum of: Ten Thousand. Nine Dollars and No Cents
($10,009.00).
G:\PubWorks\Staff Reports\2009\February 26\04 Country Club Pavement Rehab CO 1 for Contreras C28030A Project No 619-08\Contract Change Order.doc See reverse ...
Contract C28030A Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materiafs, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension 0 Days.
Revised Contract Total $139,609.00
The undersi�ned Contractor approves the foregoing Change Order# 1 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order# 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
DEPARTMENT HEAD CONTRACTOR Date Accepted
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR ROBERT A. SPIEGEL, MAYOR Date Approved
NOTE: No payments will be made prior
to City Manager and Council approval CITY MANAGER Date Approved
G:\PubWorks\Staff Reports\2009\February 26\04 Country Club Pavement Rehab CO 1 for Contreras C28030A Project No 619-08\Contract Change Order.doc See reverse ...
MONTEREY
� r��... . .� .. �
�
D' �_ -
SAN PABLO m O � -�
— � r�
D � __—�,
D
r
r
� � �
c PORTOLA �•
mo � �
�F- o r �—
o �
m' c� C) �
� � � � �
D m�
CORPORATE � � � p�
� ^
� N � D ��
� � W � �
�
COOK rn COOK� COOK D
m �
� �
� � '
� ^
� OO
� ��.;
Z
� �:
ELDORADO ELDORADO
��
-a
C�,���� �'� � ��y
O,A � ��
'��y � U ��
�, o, o�'�
�'� I �u ��' �
„ / � �.
p OASIS CLUB �
�� o � ■
� � r
�' o
d�N�o�nd� � r*.
�- o �
� �� � sv �
WARNER �p- =~
� _ � '•�.1
z p � �
D m �
� �-- -- -- �
WASHINGTON �d�'
5��