HomeMy WebLinkAboutSupptl Info after 7/21/10 - R29450C DW Ktchn/Bldg XpnsnTo: From: Date: Subject: PALM DESERT REDEVELOPMENT AGENCY INTEROFFICE MEMORANDUM Agency Board Martin Alvarez, Redevelopment Manager July 27, 2010 Desert Willow Kitchen/Building Expansion: Bid Results Staff recommends the following action: By Minute Motion: 1. Approve project Additive Alternate No. 1; 2. Authorize the Chairman to execute Contract No. R29450C to the lowest responsive bidder in the amount not to exceed $2,880,873.49 (including Additive Alternate No. 1) for the Kitchen/Building expansion at Desert Willow Golf Resort; 3. Authorize the Finance Director to set aside the amount of $288,087.35 as 10 percent contingency (use of contingency requires additional action). Funds for the construction have been included in the proposed 2010/2011 Financial Plan in Project Area No. 2, Account No. 851-4663-454-4001; 4. Authorize the use of an amount not to exceed $231,000, including 10 percent contingency for non -fixed furniture, fixtures and equipment associated with the kitchen/building expansion. Funds are available in Desert Willow Golf Course Maintenance Fund 241; and 5. Waive further reading and adopt Resolution No. approving a loan in the amount not to exceed $500,000 from the City's Golf Course Maintenance Fund (Fund 241) to the Desert Willow Golf Course Q v` Operating Fund (Fund 520). o ;. c r; r_ Bid Results r - r ati On July 23, 2010, the City Clerk publicly opened and read four sealed bids. �0, c —f •w (7 T rn G \rda\Martin Alvarez \2010\Memos\Memo-Desert Willow KitEx Bid Update 7-27-10 doe Desert Willow Kitchen/Building Expansion Bid Opening Results July 27, 2010 Page 2of3 Below is a summary of the bids received: COMPANY NAME The Penta Building Group — Palm Desert, CA Additive Alternate (No. 1) Doug Wall — Bermuda Dunes, CA Additive Alternates (No.1) Davis Reed — San Diego, CA Additive Alternates (No.1) Orr Builders — Bermuda Dunes, CA Additive Alternates (No.1) Base Bid/Additive and Deductive Alternates BID AMOUNT $2,865,154.08 $ 15,719.41 Total $2,880,873.49 $2,914,133.00 $ 15,000.00 Total $2,929,133.00 $2,997,000.00 $ 14,000.00 Total $3,011,000.00 $3,149,000.00 $ 16,000.00 Total $3,165,000.00 The projects base bid includes, but is not limited to, a 5,264 square foot expansion of the existing kitchen/building, remodel/expansion of the existing lobby bar, widening of the pinch point at the ballroom hallway, new east banquet lobby and ancillary spaces. As part of the bid, staff requested one additive alternate bid and one deductive alternate that would enhance the project if budget allowed. Below is a description of each alternate and their bid costs: 1. Additive Alternate No. 1: Replacement of nine chandelier light fixtures with dimmable chandelier fixtures in the Firecliff Ballroom and Palm Desert Room ($15,719.41). 2. Additive Alternate No. 2: N/A 3. Deductive Alternate No. 3: Non -decorative vinyl interlayer at aluminum framed folding partition glass wall separating the Firecliff Ballroom from lobby and lobby bar (-$9,491.00). This alternate is not recommended. Base bid includes decorative logo on opaque glass wall. The lowest responsive bid price of $2,865,154.08 is below staffs anticipated construction estimate of $2.95 million. Staff is recommending approval of Additive Alternates No. 1. The total bid price including the additive alternate is $2,880,873.49. Including this item under this contract will enhance the projects aesthetics, provide dimmable lights at the ballroom, and minimize disruptions to business operations if this amenity is added at a later date. Schedule If the contract is awarded to the lowest responsive bidder, the project would commence in mid August 2010 with a 140 consecutive day completion date. The estimated completion G \rda\Martin Alvarez\2010\Memos\Memo-Desert Willow KitEx Bid Update 7-27-10 doc Desert Willow Kitchen/Building Expansion Bid Opening Results July 27, 2010 Page 3 of 3 date is mid January 2010. From an operation standpoint, the majority of the work will be completed during the non -peak period minimizing impacts to the golf resort. The City Attorney has reviewed and approved the lowest apparent bidders' bid bond and qualifications. Staff recommends approval of a contract with The Penta Building Group in the amount not to exceed $2,880,873.49 (including base bid and Additive Alternate No. 1). Submitted By: Alvarez, Rede elo men Manager f in p t Approval: ohlmuth, Executive Director/City Manager Rachelle D. Klassen, Secretary John M. Wohlmuth, Executive Director Justin McCarthy, ACM for Redevelopment G \rda\Martin Alvarez\2010\Memos\Memo-Desert Willow KitEx Bid Update 7-27-10 doc