HomeMy WebLinkAboutC27950C - Utility Rlctn 4 Frank Sinatra & Portola Imprvmnts (572-08) Contract No. C2790C
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: RATIFY THE ENGINEERING ADVANCE TO SOUTHERN
CALIFORNIA EDISON SOUTHERN CALIFORNIA EDISON AND
AUTHORIZE PAYMENT FOR THE UTILITY RELOCATION FOR
FRANK SINATRA DRIVE AND PORTOLA AVENUE
INTERSECTION IMPROVEMENTS (PROJECT 572-08)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
DATE: July 27, 2010
CONTENTS: Engineering Advance Memo
Relocation Estimate Agreement
Recommendation
By Minute Motion:
1. Ratify the engineering advance to Southern California Edison
(SCE);
2. Authorize payment for the utility relocation in conjunction with the
construction of the Frank Sinatra Drive and Portola Avenue
Intersection Improvements project; and
3. Authorize the City Manager to execute the relocation estimate
agreement.
Funds are available in the Portola Avenue at Frank Sinatra Intersection Improvement
project Account No. 213-4548-433-4001, Measure A.
Backqround
The Portola Avenue at Frank Sinatra Drive Intersection Improvement Project design has
been completed. The project requires that SCE perform some relocation of transmission
and distribution lines. This portion of the work has always been a part of the project
scope and budget, included in the construction phase. The City has greatly reduced the
cost of the relocation from an anticipated $700,000 to $289,000, which is currently being
Staff Report
Payment for SCE Relocation
July 27, 2010
Page 2 of 2
estimated by SCE. These relocations are required prior to construction being able to
take place.
This project is funded in the recently adopted City Budget, and the relocation cost is part
of the anticipated construction cost in excess of $7.8 million. The City previously paid
$75,000 as an engineering advance to SCE. Therefore, the balance due to SCE at this
time is $214,000.
Fiscal Analysis
Upon completion of the relocation the estimated $289,000 will be reconciled with the
actual cost incurred by SCE. At that time the City will be sent a final invoice and billed or
refunded any difference covering the actual cost of the relocation. It is the experience of
the City that generally SCE will stay under the estimated budget and the City will be
refunded.
Prepared By: Departme t e d:
�_ �
�aron Kulp, P.E., Associate Engineer Mark Green ood, P.E.,
Director of ublic Works
CiTY COUNCILA�'TION
Paul S. Gibson, Director of Finance APPROVED DENiED
RECEIVED OTHER
Approval: MEETI1vG DA '
AYES � � � � �
� )- ���. NOES:
�_ �j� --�' ABSENT:
City Manager AB5TAIN:
Jo M. Wohlmuth, VERIFIED BY: �
Original on File with City k's O�ce
�
+ :,
,,� sc��rfiri:ti caurc��z�via
� �� �,�� Albert Ramirez
Project Manager
��,r,?r;o���.r;.r��.v;u�.0 r,.,�,F>���;. TransmissionProject
Management
May 1 3, 2009
City of Palm Desert
C/o: Butsko Utility Design, Inc.
Attn: Eddie Pablos
26835 Jefferson Avenue, Suite A
Murrieta, CA 92562
SUB)ECT: Relocate Edison's existing overhead and underground transmission and
distribution facilities to attommodate intersection improvements
Edison's impacted facilities: Devers-Santa Rosa and Santa Rosa-Tamarisk
1 15kV transmission line and Pistola 12kV distribution circuit
Location: Portola Avenue and Frank Sinatra Drive in Palm Desert
WBS File Number: WEP-QQ618
Dear Mr. Pablos:
Southern California Edison (SCE) has received your request ta relocate SCE's existing
overhead and underground facilities to accommodate intersection improvements at the
location referenced above. In order to process your request in a timely manner, please
provide an engineering advance in the amount of $75,000 payable to Southern
California Edison Company, so we may proceed with the development of the scope of
work and provide the cost estimate.
If this project is canceled, we will deduct from the engineering advance, any expenses
incurred in connection with the relocation prior to any refund. However, if the project is
continued, the engineering advance will be applied to the total actual cost of the
relocation.
Please issue your check payable to Southern California £dison Company and forward it
to the address shown below, Attention: Albert Ramirez. Also, identify your check with
our WBS Number, WEP-OQ618.
Following reteipt of the engineering advance, the cost estimates, and any documents
will require a minimum of three (3) months to process.
Upon completion of the preliminary engineering, SCE will provide the cost estimate for
the requested relocation. All prices quoted and/or written are applicable for a period of
90 days and are subject to change thereafter. SCE wi(I require the full amount be paid
prior to the commencement of any work.
� �� � . ,,,:
;.,,3;. _ �g;'":,
- . .:._.. : •?;
Albert Ramirez
Project Manager
Transmission Project
Management
When SCE receives your check for the estimated amount; contracts and/or replacement
rights have been acquired (if necessary) the project will be cleared for construction. The
actual construction will commence approximately 90 days after clearance and will
depend on the availability of our resources.
Upon completion of the relocation work, the actual cost of the project will be calculated
and any additional funds will be required and/or a refund of any overpayment will be
made at that time.
I wiil be coordinating your project and should be notified immediately if the praject is
delayed, canceled, or if there are changes in scope andior other conditions affecting the
proposed relocation, work schedules or completion dates.
If you have any questions, please feel free to call me at (951) 492-1313.
Thank you for your cooperation in this matter.
Sincerely,
G�c� � .
Albert Ramirez
Project Manager
Transmission Project Management
cc: Barbara Miljkovic
Robert Franzo
Ray Gleim
Robert Castillo
Mil<e Maxwell
Amir Shaterian
File
.._ 7�! � -. . ._,,...
�..-...',i _�:=� :�.` .
... ';��;'' .,_. _
d{�'?;;�:3mirc"r- �.�. ,.')u;
50 A
� EDISO
July 7, 2010
City of Palm Desert
C/o Butsko Utility Design
Attention: Eddie Pablos
26835 Jefferson Ave., Suite A
Murrieta, CA 92562
SUBJECT: Relocate Existing Overhead and Underground Southern Californfa
Edison Facilities
Santa Rosa-Tamarisk 115kV Transmission Line
Portola Avenue and Frank Sinatra Drive and east side of Portola
Avenue just north of Desert Willow Court in Palm Desert
WBS File Number: WEP-Q0518
Southern California Edison (SCE) has reviewed your request to provide a cost
estimate for the billabie portion of this relocation project. This cost estimate
includes the cost to re(ocate existing overhead transmission facilities, relocate
existing underground distributian facilities on the east side Portola Avenue just
north of Desert Willow Court, and work needed to secure a Joint Use Agreement.
This relocation project impacts SCE's Santa Rosa-Tamarisk 115kV transmission
line, and SCE's Pistola, Taberna, Clubhouse, and Bandana 12kV distribution
circuits located at the intersection of Portola Avenue and Frank Sinatra Drive and
along the east side of Portola Avenue just north of Desert Willow Caurt in the
City of Palm Desert. Dur file identification number is WEP-00618. In order to
accommodate your request, SCE's facilities will be modified as follows:
SCE's transmission facilities will relocate and include the following work:
• Install one 55 foot wood guy stub pole
• Install one 45 foot wood guy stub pole
• Install one 35 foot wood guy stub pole
• Install all associated span guys, down guys, and anchors
• Remove two existing 40 foot wood guy stub poles
• Remove one existing 35 foot wood guy stub pole
• Remove all existing span guys, down guys, and anchors
5CE's existing underground distribution facilities on the east side of Partala
Avenue just north of Desert Willow Court will be relocated from their current
location to accommodate the widening of Partola Avenue. The City af Palm
Desert will be responsible to provide al! the new conduit and substructures to
accommodate this portion of the underground relocation. The city's contractor
300 N.Pepper Ave
Rialto,CA 92376
951.492.1313
Albert.Ramirez@sce.com
' will be responsible to perform the following work per SCE's standards and
maintafn a five foot distance from any energized facilities:
• Install one 5 foot by 10 foot 6 inches by 7 foot PME tub-style concrete
enclosure
• Install approximately 830 feet of four inch PVC conduit
• Install approximately 1,200 feet of five inch PVC conduit
• Remove one 5 foot by 10 foot 6 inches by 7 foot PME tub-style
concrete enclosure (after structure has been de-energized)
The City of Palm Desert wil! also be responsible to pravide intercept structures
that must be installed by Edison's Cost Plus underground contractor at the city's
expense due to the existing energized cables. Edison's Cost Plus underground
contractor to instail the following materials provided by the city:
• Two 5 foot by 10 foot 6 inches by 7 faot intercept manholes
• Two manhole covers and frames
• Two ladders
SCE's dlstribution crews will perform the following wark for the new
underground system:
• Install approximately 520 feet of three-one conductor 750 jacketed
cable with a neutral
• Instali approximately 340 feet of three-one conductar 1/0 jacketed
cable with a neutral
• Install one PME 10 switch
• Splice and make-up the new underground cabie
• Energize the new underground system
• Remove all existing cable and components from the old system
(existing conduit will be abandoned in the field)
The estimated cost to relocate the existing overhead transmission facilities and
relocate the existing underground distribution facilities to accommodate the
development of your project is $289,000 (Twa hundred and eighty nine
thousand dollars), which does not include Income Tax Component of
Contribution (ITCC).
SCE acknowledges receipt of $75,000 as an engineering advance, therefore the
balance due at this time is $214,Q40 (Two hundred and fourteen thousand
dollars). Please ensure your check is made payable to Southern California Edison
Company and forward to me at the address shown below. Please identify your
check with our WBS file number, WEP-00618.
This estimate is provided based on unapproved plans dated April 19, 2010. Any
changes in the final city approved plans could lead to re-engineering, additional
costs, and possible delays on the start af construction.
300 N.Pepper Ave
Rlalto,CA 92376
951,492.i313
AlberE.Ramirez�sce.com
This cost estimate is oniy for the city funded joint relocation portion of this
project, as described above. Street lights, pedestais, service work orders, or any
other SCE work orders are not part of this estimate, and will be provided by
other SCE department(s). Other projects than the relocation project identified
above will include conduit or structures as needed for those separate projects.
SCE will require replacement rights for the relocation of above referenced
facilities. Upon receipt of the funds, the signed acknowledgement set forth
below, required Permits, and a Joint Use Agreement for the relocation af
facilities, this project will be released for construction. SCE will require 9Q days
to order material and schedule crews.
As part of this praject, there are additional underground distrlbution facilities to
be relocation at the intersectians of Portola Avenue and Frank Sinatra Drive and
Shepherd Lane and Frank Sinatra Drive. These portions of the project will be
funded by SCE due to our facilities being in the franchise with no priar rights.
Please note that the preliminary cost estimate presented in this IeCter is based
on conceptual engineering and system unit costs. The costs are subject to
change based on the final design and actual material costs. All prices quoted or
written are applicable for 90 days from receipt of this letter.
Upon completlon of the installation and closure of the subject work orders, the
originally estimated cost will be reconciled to actual costs. At that time, the
necessary billing adjustrnents will be made.
Therefore, at the completion of the project, the customer will be sent a final
invoice and be billed ar refunded any difference covering the actual cost of the
project. Please allow approximately one year after job completion for the final
invoice to be prepared. Any amount owed by the city to SCE at the completion
of the project shall be due no later than 30 days after receipt of the final invoice.
This completed cast estimate has been calculated and presented to the city
without an Income Tax Component of Contribution (ITCC). In the event the
Internal Revenue Service (IRS) state, city and/or local government taxing
authority determines that this project is taxable, the City of Palm Desert will
reimburse Southern California Edison Company for the full amount of the tax
liability determined by the IRS, state, city and/or local government authority,
plus interest, penalties, fees, and related cost. Such amounts will be paid to
Edison within 60 days after notification of such event by Edison to the City of
Palm Desert. By execution of this document, the City of Palm Desert hereby
acknowledges that this project is funded by the City af Palm Desert.
Please acknowledge your understanding of SCE's relocation and billing process,
as stated above, by having the appropriate city official sign and return the
executed letter.
If there are any delays or this project is canceled, please natify me immed(ately
at 951-492-1313.
300 N.Pepper Ave
Ridlto,CA 92376
951.492.1313
Albert.Ram I rez�sce.com
Sincerely,
�'v`"i ' � .
Albert Ramirez
Project Manager
Transmission Project Management
� acknowiedge and agree to the above referenced indemnitv and SCE's
billing �rocess as a duly authorized representative of the City of Paim
Desert
By: Date:
City of Palm Desert
John M. Wohlmuth TItIE: City Manager
Print Name
Enclosure
cc: Rob Franzo
Ray Gleim
Ralph Meraz
Melissa Lee
Amir Shaterian
Mike Maxwell
Kenji Coleman
Mike Beard
Carol Brown
File
300 N.Pepper Ave
Rialto,CA 92376
451.492.1313
Albert.Ramirez�sce.Com