Loading...
HomeMy WebLinkAboutC30400 Change Order # 1 through 5 Parkview Office Complex Tenant Improvements - Doug WallCITY OF PALM DESERT FINANCE DEPARTMENT STAFF REPORT REQUEST: Approve Change Orders #1 through #5 to Contract No. C30400 with Doug Wall Construction, Inc. to construct tenant improvements at the State of California Water Resources Control Board Suite 100 at the Parkview Office Complex for a net overall increase of $6,456.39, and appropriate $6,456.39 from Fund 510- 4195-495-3370. APPLICANT: Doug Wall Construction, Inc 78450 Avenue 41 Bermuda Dunes, CA 92203 DATE: April 28, 2011 CONTENTS: Copy of Change Orders # 1 through #5, and summary of all change orders. Recommendation By Minute Motion, that the City Council: (1) Approve Change Orders No. 1through 5 to Contract No. C30400 with Doug Wall Construction, Inc. to construct tenant improvements at the State of California Water Resources Control Board Suite 100 at the Parkview Office Complex for a net overall increase of $6,456.39; and (2) Appropriate $6,456.39 from Fund 510-4195-495-3370. Background On December 9, 2010, City Council approved Contract No. C30400 with Doug Wall Construction, Inc to construct the tenant improvements for Suite 100 at the Parkview Office Complex in the amount of $216,000 plus a 10% contingency. During the course of construction, the State of California made some changes to better suit their office space utilization. As a result, five change orders were accepted. Change Order No. 1 resulted from changing the board room flooring from ceramic tile to carpet, an increase of $576.19. Change Order No. 2 added a new computer rack in the information technology room to house their network servers, an increase of $4,400.09. Change Order No. 3 added a plug for a copier that will be housed in the public viewing room for better access by the public, an increase of $383.91. Change Order No. 4 provided an automatic remote buzzer to open the public access door from the reception area, as well as replace a warped door for a total increase of $800.89. Change Order No. 5 allowed for the installation of an emergency light in the new board room, an increase of $295.31; an item required by the State Fire Marshal. There will not be any additional change orders for this contract. H:IWPDOCSk1nteroffice MemoslParkViewlParkview 2010-20111SR-Doug Wall Change Order 04281 1.doc Staff Report Change Order Contract C30400 — Doug Wall Construction, Inc. April 28, 2011 Page 2of2 The table below summarizes the change orders. Change order Amount 1 $ 576.19 2 $4,400.09 3 $ 383.91 4 $ 800.89 5 $ 295.31 Total Description Change floor the to carpet Add and install additional network computer rack Add electrical plug for copier Add remote buzzer for entry door Add emergency light in new boardroom City staff has discussed the change orders with State of California representatives and they have agreed to provide an additional $10,000 to their previous contribution towards the tenant improvements. The State of California has agreed to reimburse the City for their portion of the tenant improvements by increasing their rental rate for the first 48 months. Staff recommends that the City Council approve and execute Change Order Nos. 1 through 5 of Contract No. C30400 with Doug Wall Construction, Inc. for a total of $6,456.39. Fiscal Analysis The change orders have increased the overall cost of the project by $6,456.39; however, the State has agreed to contribute an additional $10,000 for this project to cover these change orders. Therefore the impact of these change order is borne by the State of California. The State will reimburse the City for their portion through a rent increase for the first 48 months of lease agreement. Submitted By: Paul S. Gibson, Director of Finance n M. Wohlmuth, City Manager PSG:AH:nmo CITY COUNCIL ACTION APPROVED ✓ DrNIED RECEIVED O'FI IElii . MEETING DATE - -7)(5 AYES: i ---- NOES:�r ABSENT:{ �_� - -- ABSTAIN: N �- VERIFIED BY R f')L ra ----_ Original on File with City Cler a celf WWPDOCSIInterofice MemoslParkViewlParkview 2010-20111SR-Doug Wall Change Order 042811.d0c City of Palm Desert CONSTRUCTION CHANGE ORDER Contract # / PO # Change Order No. Contingency Account No. Contract Purpose: I Tenant limprovements at Parkview Suite 555-100 Contractors Name: I Doug Wall Construction, Inc. C30400 1 through 5 Yes ❑ No 510-4195-495-3370 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE (Supplemental Plans and Specifications In Contract Price In Contract Price Attached Eliminate tile flooring for boardroom and install $ 576.19 carpet tiles. Add new Computer Network Rack $4,400.09 Install electricasl outlet in public viewing room $ 383.91 Add new remote entry door buzzer and replace bad door $ 800.89 Add emergency light in boardroom $ 295.31 TOTALS $6,456.39 NET CHANGE IN CONTRACT PRICE $6,456.39 JUSTIFICATION: During the courase of construction the State of California changed some of the aforementioned items to better suit their utilization of their suite and to better serve the public. The local State Office does not have any onsite Computer Service Staff so the the new network rack was needed to install computer equipment that can be accessed remotely from Sacramento. The State of California agreed to add an additional $10,000 to the rent as repayment for these change orders. TOTAL BUDGET FOR PROJECT: + CONTINGENCY: Less: Expend. & Encumb. To Date - Amount Approved by Council + Less: This Change Order Amount: - Less: Prior Change Order: - BALANCE OF BUDGET REMAINING Less: This Change Order: FOR PROJECT: $ BALANCE REMAINING OF CONTINGENCY: $ The amount of the Contract will be Increased by the sum of: Six thousand four -hundred fifty-six and 39 cents Dollars ($6,456.39). This document will become a supplement to the contract and all provisions will apply hereto, all items included above must have required signatures as per the purchasing resolution. ORDERED BY: 2. ACCEPTED BY: H MPDOCSUdardf MamoslParW—WarkA-2010- 'tCONTRACT CHANGE ORDER FORM,Da Wall dw Department Head 3. CERTIFIED FUNDS AVAILABLE Finance Director Date Approved ContractorNendor 4. APPROVED BY: City Manager City Council NOTE: No Payments will be made prior to City Manager and City Council Approval Date Approved Date Approved H�PDOCSUMaW Mem.s� ,kVewW,rkwe 2010-201t1CGHTRACTCHAHGE ORDER FORM -Do WAd. 3 c EoGG 0 ?: 2EEE i- 0) @R a/G� n Q E\ \ §ƒ M R & � =0.0a G=- -0 k- 6 § 8 / R S ] 7 0 ) w~; < aCr/] m ]m\ n£ CD o� m � D 0 m ® \ N\[ Q) a o / �CD 2 77 0 ERtg E a ] 3 £ 2 $c ¢ o £ 00 // a ? o o / m # w / ) \ 0 m 2 n ■ \ $ 0 ( C \ _ CL = 0 00 7 3 �«�\�0 / ® $® Q m]] m n o o° + m e - o f nƒtEe « a D E kCD CD 0/ <=- G $ ® ® \�-0 ( , (D CL�ae o m -pƒ A 0- § 0 = \G a = E __#_#/72k U A 2 tj%� n} 0'<0CD ° gewe�a)�=-4 w& CL \ GRSRk/3Gd R g n 30 k � � / g ■ 2 , 2 ■ 2 ■ 2 ■ 2 ® q E o g$ a 0 0 / /M/ C E 2 R G Cl R 7/// . # # 00 0 \ ®CD � cn SCD � 02 E c 2 7 _ _ _ / _ > � - = - 2 \� _ e « G w� w� / ] _ 2 8 # $ = o g% $ $ �� 2 ¢S\ G ƒi % % / L CD o t CL S CD# \ f J a \ o \ 5 Eq m� «- Eo I n a \> OD _ E2 U ~ >= \e @ « w e kka R w Cl m s< cn o < o $�\ o G < w � -. §am � \E a m o to & � 2 k � \ 2 DoLTG WALL CONSTRUCTION, INC. CA 8t L k 4 743112 PROPOSED CHANGE ORDER PROJECT: California Water Board T.I. TO: Anthony Hernandez PENDING x Approved OWNER x INTERNAL SUBCONTRACT Completed CHANGE ORDER NUMBER DWC-01R1 DATE: 1 /31 /2011 COST CODE: JOB # 1026 The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and specifications: Install Shaw Carpet "Range" 54435 thru out project Cost Code Trade Description Sub Adds Credit 918 Carpet install "Range" 54435 Mike's $4,460.20 918 Carpet install car et at two board rooms Mike's $5,869.50 915 Ceramic Tile delete tile from two board rooms the works -$9,171.92 611 casework delete casework at board room miller -$670.00 subtotal $487.78 2010 15% Profit & Overhead $73.17 subtotal $560.95 2110 1.2% Insurance $6.73 subtotal $567.68 1911 1.5% lbonding,$8.52 Total Amount I 1 1 $576.19 All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. Original Contract Amount Total Previous Change Orders Total Before this Change Order Amount of this propose change Revised Contract Amount: $216,000.00 $576.19 OWNER/SUBC T TOR: _ SIGNED: _ DATED: TITLE: DOUG WALL CONSTRU ION INC. SIGNED: DATED: TITLE: 78450 Ave 41, Bermuda Dunes, CA 92203 Tel: 760-772-8446 Fax: 760-772-9407 WWI Dom WALL CONSTRUCTION, INC. CA It L le #?aaiu PROPOSED CHANGE ORDER PROJECT: California Water Board T.I. TO: Anthony Hernandez PENDING x Approved OWNER x INTERNAL SUBCONTRACT Completed CHANGE ORDER NUMBER DWC-02 DATE: 1 /31 /2011 COST CODE: JOB # 1026 The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and specifications: Additional I.T. work per owner's request Cost Code Trade Description Sub Adds Credit 1623 Communication additionalpost/rack, cords, switches, etc. Adept $3,469.92 156 Misc Labor install 2 5/8 fire rated 4'x8' I ood DWC $255.00 subtotal $3,724.92 2010 15% Profit & Overhead $558.74 subtotal $4,283.66 2110 1.2% Insurance $51.40 subtotal $4,335.06 191 1.5% bonding $65.03 Total Amount $4,400.09 All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. Original Contract Amount Total Previous Change Orders Total Before this Change Order Amount of this propose change Revised Contract Amount: $216,000.00 $4,400.09 OWNER/SUB TOR: SIGNED: DATED: TITLE: DOUG WALL CONSTRU2 ON INC. SIGNED: DATED: TITLE: 78450 Ave 41, Bermuda Dunes, CA 92203 Tel: 760-772-8446 Fax:760-772-9407 Dom WALL CONSTRUCTION, INC. CA 'it Lit 0'43112 PROPOSED CHANGE ORDER PROJECT: California Water Board T.I. TO: Anthony Hernandez PENDING x Approved OWNER x INTERNAL SUBCONTRACT Completed CHANGE ORDER NUMBER: DWC-03 DATE: 2/22/2011 COST CODE: JOB # 1026 The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and specifications: additional electrical Cost Code Trade Description Sub Adds Credit 1601 electrical add plug for printer at viewing room cs electric $325.00 925 drywall patch waive DWC $0.00 subtotal $325.00 2010 15% Profit & Overhead $48.75 subtotal 1 $373.75 2110 1.2% Insurance $4.49 subtotal $378.24 191 1.5% bonding $5.67 Total Amount $383.91 All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. Original Contract Amount Total Previous Change Orders Total Before this Change Order Amount of this propose change Revised Contract Amount: owNewsuecoNT oR: SIGNED: --- DATED: i TITLE: �;^rwrCti., - DOUG WALL CONSTRUCIJON INC SIGNED: - DATED: TITLE: 78450 Ave 41, Bermuda Dunes, CA 92203 Tel: 760472-8446 Fax: 760-772-9407 $216,000.00 $383.91 D�VC DOuG WALL CONSTRUCTION, NC. ca tt Ur rt itii� PROPOSED CHANGE ORDER PROJECT: California Water Board T.I. TO: Anthony Hernandez PENDING x Approved OWNER x INTERNAL SUBCONTRACT Completed CHANGE ORDER NUMBER: DWC-04 DATE: COST CODE: JOB# The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and specifications: provide remote controi for reception room door latch - supply and install new door at board room 4/13/2011 1026 Cost Code Trade Description Sub Adds Credit 810 remote control remote control for door latch guy evans $273.00 801 doors board room door guy evans $405.00 subtotai $678.00 2010 15% Profit 8 Overhead $101.70 subtotal $779.70 2110 1.2% Insurance $9.36 subtotal 1 $789.06 1911 1.5% bonding 1 $11.84 Total Amount $SIM-89 All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. Original Contract Amount Total Previous Change Orders Total Before this Change Order Amount of this propose change Revised Contract Amoun OWNERISUBCONTRACTOR: SIGNED: DATED: TITLE: $216,000.00 DOUG WALL CONSTRUC N INC. / SIGNED: — _ X DATED: TITLE: 78450 Ave 41, Bermuda Dunes, CA 92203 Tel:760-772-8446 Fax:760-772-9407 $800.89 Do� INt'. PROPOSED CHANGE ORDER PENDING Approved x OWNER x INTERNAL SUBCONTRACT Completed PROJECT: California Water Board T.I. CHANGE ORDER NUMBER: OWC-05 DATE: 4/13/2011 TO: Anthony Hernandez COST CODE: JOB # 1026 The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and specifications: per fire department requirements, install emergency light at board rooms Cost Code Trade Description Sub Adds Credit 1610 electrical supply and install emergency light at board rrn. CS elec. $250.00 subtotal $250.00 2010 15% Profit & Overhead $37.50 subtotal 1 $287.50 21101 1.2% Insurance $3.45 subtotal 1 $290.95 1911 1.5% bondinq $4.36 Total Amount $296.31 All other provisions of the original contract and agreement shall remain in full force and effect without change because of the above deviations. Original Contract Amount $216,000.00 Total Previous Change Orders Total Before this Change Order Amount of this propose change $295.31 Revised Contract Amount: OWNERISUBCONTRACTOR: DOUG WALL CONSTRUC' QFl INC. SIGNED: SIGNED: DATED: DATED: TITLE: TITLE: -1-- 78450 Ave 41, Bermuda Dunes, CA 92203 Tel:760-772-8446 Fax: 760-772-9407