HomeMy WebLinkAboutC30300 Change Order 1 Renovation Fire Station 33 and 71 - Joint ConsiderationCITY OF PALM DESERT/PALM DESERT REDEVELOPMENT AGENCY
CITY MANAGER'S OFFICE
STAFF REPORT
REQUEST: APPROVAL OF CHANGE ORDER NO. 1 TO CONTRACT NO C30300
(THE PENTA BUILDING GROUP) IN THE AMOUNT OF $7,481 FOR
THE FIRE STATION NO. 33 RENOVATION PROJECT.
SUBMITTED BY: Stephen Y. Aryan, Assistant to the City Manager
CONTRACTOR: The Penta Building Group
44-250 Monterey Avenue
Palm Desert, CA 92260
DATE: August 25, 2011
CONTENTS: Change Order No. 1
Recommendation
By Minute Motion:
Approve Change Order No. 1 to Contract No. C30300 with the Penta Building
Group in the amount of $7,481 to perform a structural repair of an existing
condition, as part of the Fire Station No. 33 Renovation Project (Project No.
613-09).
2. Authorize the Chairman to Execute said documents; and
3. Authorize the Finance Director to transfer $7,481 from the 10% contingency
set -aside to the base contract.
Funds are available in Account No. 850-4220-464-4001
Background
On February 24, 2011, the City Council approved Contract No. C30300 to The PENTA Building
Group in the amount not to exceed $848,149 (including Landscaping and QuakeGuard Options)
for the Fire Station No. 33 and Fire Station No. 71 renovation projects. The City Council also
authorized a ten percent (10%) contingency in the amount of $84,814.90.
Funds for these projects are included in the 2011/2012 Redevelopment Agency Financial Plan
in Project Areas No. 1 and No. 2, Account No. 850-4220-464-4001 (Station No.33) and Account
No. 851-4220-464-4001 (Station No.71).
During the course of renovating Fire Station No. 33, the contractor discovered that an 18" deep
structural beam (known as a glulam) adjacent to the area of work had two 8" cuts through it.
This change order includes the conditions review, engineering, design coordination, plan check
re -submittal and installation of a new 12" deep beam (below the cut beam) as well as drywall
and finishes, to correct this structural deficiency.
Staff Report: Fire Stations No. 33/71 Renovation Project (Change Order No. 1)
August 25, 2011
Page 2 of 2
Fiscal Analvsis
As part of the contract approval, a ten percent (10%) contingency in the amount of $84,814.90
was allocated as follows:
Fire Station
Fire Station
Cumulative
No.33
No. 71
Projects Total
Design/Build Renovation Project
$286,396
$388,813
675,209
Landscaping Option
$52,988
$45,440
98,428
Quakeguard Option
$37,256
$37,256
74,512
Total
$376, 640
$471,509
$848,149
Contingency Amount (10%)
$37,664
$47,150.90
$84,814.90
With approval of Change Order No. One, the contingency amount for the Fire Station No. 33
Renovation Project will be reduced by $7,481 leaving a remaining contingency balance of
$30,183.00 for this project. The total project cost will also increase from $376,640.00 to
$384,121.00. In addition, the contract duration will be extended by ten (10) days. Funds are
available in Account No. 850-4220-464-4001. The project is funded with Redevelopment Agency
funds; therefore, there is no fiscal impact to the City's General Fund.
Submitted By:
CITY COUNCIL A TION
APPROVED _... DENIED
Stephen Y. Aryan, AssistaZ�'t6 the City Manager RECEIVED OTHER
Reviewed By: MEETING DATE
AYES: In 'il
NOES:
1 ABSENT: W019
ABSTAIN:
J stin McCarthy, Assis Cit Manager VERIFIED BY: KQ qlm
Original on File with City Clerk's Office
Paul S. Gibson, Director of Finance/City Treasurer
BY RDA
Approved By: ON ----------
VERIFIED Sy R:pj�)ry)
r_12t ���� original en file with City Clerk's office
John . Wohlmuth, City Manager
PALM DESERT REDEVELOPMENT AGENCY
CONSTRUCTION CHANGE ORDER
Contract Purpose Fire Station No. 33 Renovation Project
Contractor's Name The Penta Building Group
Address: 44250 Monterey Avenue
Palm Desert, CA 92260
Contract # / P.O. #
Amendment/
Change Order No.
Contingency:
Account No.
Project No.
Vendor No.
C30300
017186
1
YES X
NO
850-4220-464-4001
613-09
12177
eou are hereby requested to comply with the following changes trom the contract plans ana specitications:
DECREASE INCREASE
DESCRIPTION OF CHANGES In Contract Price In Contract Price
Station No. 33 Structral Repairs of Existing Condition (Glulam Support) 7,481.00
TOTALS: 7,481.00
NET CHANGE IN CONTRACT PRICE: 7,481.00
JUSTIFICATION:
To address unforeseen structural repairs not in the project scope.
TOTAL BUDGET FOR PROJECT: + 376,640.00
Less: Expend. & Encumb. To Date: - 376,640.00
Less: This Change Order Amount: - 7,481.00
BALANCE OF BUDGET
REMAINING FOR PROJECT: 7,481.00
CONTINGENCY:
Amount Approved by Board: + 37,664.00
Less: Prior Amendment(s): - -
Less: This Amendment: - 7,481.00
Balance Remaining of Contingency: 30,183.00
The amount of the Contract will be (Besreased) Increased by the Sum of: Seven Thousand, Four Hundred
Eighty -One and NO/100 Dollars ($7,481.00).
CaUserslsaryanWppDatalLocalMcrosoft\Windows\Temporary Internet Files\Content.Outlack\8NCOAETE\Penta R29450C-Chng 3.docx See reverse ...
Contract C30300 Change Order No. 1 Continued from front
This Contract Amendment covers changes to the subject contract as described herein. The consultant shall perform
all work as necessary or required to complete the Contract Amendment items for a lump sum price agreed upon
between the Consultant and the Palm Desert Redevelopment Agency, otherwise referred to as Owner.
Contract Time Extension -10- Days.
Revised Contract Total $ 384,121.00
The undersigned Consultant approves the foregoing Change Order # 1 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order # 1 . The Consultant agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Contract
Amendment items. This document will become a supplement of the contract and all provisions will apply hereto. It is
understood that the Contract Amendment shall be effective when approved by the Owner.
Execution of this Contract Amendment by the Consultant constitutes a binding accord and satisfaction that fully
satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity,
arising out of or related to the subject of the Contract Amendment, whether known or unknown, including but not
limited to direct and indirect costs and/or damages for delay, disruption, acceleration, and loss of productivity, as well
as any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY:
EXECUTIVE DIRECTOR
3. CERTIFIED
FUNDS AVAILABLE:
FINANCE DIRECTOR
NOTE: No payments will be made
prior to Executive Director and
Agency Board approval
2. ACCEPTED BY:
CONTRACTOR
4. APPROVED BY:
JEAN M. BENSON, CHAIRMAN 08/25/2011
SECRETARY
08/25/2011
C\Userslsaryan'AppData\LocalWicrosoft\Windows\Temporary Internet FileslContent.Oubook\8NCOAETE\Penta R29450C-Chng 3.docx See reverse ...
P E N TA Owner Change Order
PENTA - No Architect Signature
The PENTA Building Croup
Date: 8/1l2011
To Contractor:
The PENTA Building Group
42250 Monterey Ave.
Palm Desert, CA 92260
Architect's Project No:
Contract Date:
Contract Number: 11-429-000
Change Order Number: 0001
The Contract is hereby revised by the following items:
Station 33 Structural Repairs of Existing Conditions
PCO COR Description
Amount
0001 0001 Station #33 Structural Repairs (Glulam Support)
$7,481
An 18" deep structural beam (glulam) adjacent to the area of work, was found to have two (2) 8" cuts through it. This change order
includes the conditions review, engineering, design coordination, piancheck re -submittal and installation of a new 12" deep beam (below
the cut beam) as well as drywall and finishes.
Theoriginal Contract Value was..........................................................................................................................................
$848,150
Sum of changes by prior Prime Contract Change Orders.................................................................................................
$0
The Contract Value prior to this Prime Contract Change Order was...................................................................................
$848,150
The Contract Value will be changed by this Prime Contract Change Order in the amount of ............................................
$7,481
The new Contract Value including this Prime Contract Change Order will be....................................................................
$855,631
The Contract duration will be changed by .................. ............ .........
10 Days
The revised Substantial Completion date as of this Prime Contract Change Order is ........................................................
The PENTA Building Group
CONTRACTOR
42250 Monterey Ave.
Palm Desert, CA 92260
Address
By David Slokken
SIGNATURE
DATE
City of Palm Desert
OWNER
73-510 Fred Waring Drive
Palm Desert, CA 92260
Address
By Steven Aryan
SIGNATURE
DATE
P E N TA
Change Order Request
The PENTA Building Group
Change Order Request: 0001
.. r
To: Steven Aryan
From: David Slokken
City of Palm Desert
The PENTA Building Group
73-510 Fred Waring Drive
42250 Monterey Ave.
Palm Desert, CA 92260
Palm Desert, CA 92260
Description
Category Status
Station #33 Structural Repairs of Existing Conditions
Pending Submitted
Reference
Required By Days Req Amt Req
8/8/2011 10 $7,481
Notes
PCO No Date Reference Amt Prop Days Req Category
Description Notes
0001 8/1/2011 $7,481 10 Owner Change Order
Station #33 Structural Repairs (Glulam Support) An 18" deep structural beam (glulam) adjacent to the area of work, was
found to have two (2) 8" cuts through it. This change order includes the
conditions review, engineering, design coordination, plancheck
re -submittal and installation of a new 12" deep beam (below the cut
beam) as well as drywall and finishes.
Item No
Item Description
Cost Code
Amt Prop Reference
0001
Engineering (Structural) field research, calcs and
01 01.55140 S
$1,150
drawings.
0002
Ceding demolition to expose the beam.
01 02.05010 S
$135
0003
Furnish and install the support beam, columns and
01 09.25000 S
$3,520
hardware.
0004
Drywall, tape, texture and paint new soffit (for beam).
01 09.25000 S
$1,017
0005
Architectural coordination, and re -design of entry
01 01.551408
$1,042
(soffit), door and planning review.
Level 1
Insurance - .8%
99 91.70020 0
$65
Level 3
Fee - 6%
99 98.00110 0
$415
Level 5
Bond - 2%
99 91.70060 0
$147
Approved By:
Signature
Name
Date
FF`9