HomeMy WebLinkAboutC29890 Change Order 1 Civic Center Re-roofing 712-104
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: APPROVE CHANGE ORDER NO. 1 TO CONTRACT NO. C29890
WITH PROGRESSIVE ROOFING FOR THE CIVIC CENTER
REROOFING PROJECT IN THE AMOUNT OF $42,434 (Project
No. 712-10)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
CONTRACTOR: Progressive Roofing
17805 Comconex Road
Manteca, California 95366
DATE: July 14, 2011
CONTENTS: Change Order No. 1
Recommendation
By Minute Motion:
1. Approve Change Order No. 1 to Contract No.C29890 in the
amount of $42,434 for Civic Center Reroofing Project; and
2. Authorize the transfer of $42,434 from contingency to base: and
3. Authorize the Mayor to execute said Change order No. 1
Funds are available for this project in the Building Maintenance/Repair and
Maintenance City Hall, Account No. 450-4161-415-4001.
Background
On January 13, 2011, City Council awarded Contract No. C29890 for the Civic Center
Reroofing Project to Progressive Roofing of Manteca, California, in the amount of
$903,250. The project required tearing off the existing roof and installing a built up roof
system from the deck up. Following the tear off of the roof, the following four conditions
that required additional material and labor were discovered:
Staff Report
Approve Change Order No
July 14, 2011
Page 2 of 2
1 (Contract No. C29890)
1. Standard testing did not reveal that the Council Chambers roof deck was not
sloped like the rest of City Hall. Therefore, a new system of sloping insulation
had to be designed and installed to allow for proper drainage at a cost of
$28,824.
2. Ten new standard drain rings and baskets were installed on the Council
Chambers deck to replace the existing inadequate drains in order to ensure a
water tight operation on the built up roof at a cost of $3,396.
3. It was discovered that 47 overflow drains did not have proper sheet metal sleeve
insulation. This condition had to be corrected to preserve our 30-year warranty
from the material manufacturer. Therefore, 47 new metal scuppers were
installed throughout the Civic Center at a cost of $6,214.
4. Four of the five roof hatches had rusted at the base to the point of compromising
their ability to attach properly to the curbs. Therefore, the hatches were replaced
at a cost of $4,000.
The total amount for the additional labor and materials is $42,434. Funding for this
change order is within the contract contingency, also approved by City Council, bringing
the contract to a total amount of $945,684.
Fiscal Analysis
This is an on -going maintenance activity with no fiscal impact beyond the change order.
Prepared By:
David Flint
Building M
Paul S. G`V$oin, D
M
Mark Gree
Director of
.,—,
blic Works
CITY COUNCILACTION
inance APPROVED DENIED
RECEIVED OTHEIR
I: MEEA ING DATE
l�
NOES:
ABSENT: 5ay1
Wohlmuth, City Manager ABSTAIN: 1P-
VERIFIED I3Y- �� alp
Original on File with City Clerk's Office
Contract I C29890 Change No. 1 1 Continued from front
This Change Order covers changes to the subject contract as described herein and as set forth in Exhibit A. The
Consultant shall perform all work as necessary or required to complete the Change Order items for a lump sum price
agreed upon between the Consultant and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension N/A Days.
Revised Contract Total $ 945,684
The undersigned Consultant approves the foregoing Contract Change Order #1 as to the changes, if any, in the
contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to
the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Contract Change Order #1. The Consultant agrees to furnish all labor and materials and perform all other necessary
work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change
Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is
understood that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Consultant constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, and loss of productivity, as well as any and all
consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY: 2. ACCEPTED BY:
DEPARTMENT HEAD
3. CERTIFIED
FUNDS AVAILABLE:
FINANCE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
CONSULTANT Date Accepted
4. APPROVED BY:
JEAN M. BENSON, MAYOR Date Approved
CITY MANAGER Date Approved
Continued on reverse ...
CITY OF PALM DESERT
CHANGE ORDER
Contract Purpose Reroofing of the Civic Center Building
Consultant's Name Progressive Roofing
Address: 23 N. 35th Avenue
Phoenix, AZ 85009
Contract # / P.O. #
Amendment/
Change Order No.
Contingency:
Account No.
Project No.
Vendor No.
C29890 017237
1
ES NO
Asa-4161-415-4001
712-10
12437
You are herehv reauected to comnly with the fnllnwinn chnnnec from the rnntrart nlanc anti cnacifiratinnc-
DECREASE
INCREASE
DESCRIPTION OF CHANGES
In Contract Price
In Contract Price
1 . Install new system of sloping insulation for proper drainage
$28,824.00
2. Install 10 new standard drain rings and baskets for a water tight operation
3,396.00
3. Install 47 metal scuppers
6,214.00
4. Install four new roof hatches
4,000.00
TOTALS:
-
$ 42,434.00
$ 42,434.00
NET CHANGE IN CONTRACT PRICE:
JUSTIFICATION:
Include the additional labor and materials for the four conditions discovered following the tear of the roof.
TOTAL BUDGET FOR PROJECT:
+
$
993,575.00
CONTINGENCY:
Less: Expend. & Encumb. To Date:
-
$
903,250.00
Amount Approved by Council:
+
$90,325.00
Less: This Change Order Amount:
-
$
42,434.00
Less: PriorAmendment(s):
-
$0.00
BALANCE OF BUDGET
Less: This Amendment:
-
$42,434.00
REMAINING FOR PROJECT:
$
47,891.00
Balance Remaining of Contingency:
47,891.00
The amount of the Contract will be increased by the sum of: Forty -Two Thousand Four Hundred
Thirty -Four Dollars ($42,434).