HomeMy WebLinkAboutC30640 Change Order # 1 2011 Curb Ramp Modification 753-11CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: APPROVE CHANGE ORDER NO. 1 TO CONTRACT NO. C30640 WITH SIMON CONTRACTING FOR THE 2011 CURB RAMP MODIFICATION PROJECT (PROJECT NO. 753-11) SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works CONTRACTOR: Simon Contracting P.O. Box 10990 Indio, CA 92202 DATE: June 23, 2011 CONTENTS: Change Order No. 1 Recommendation By Minute Motion: 1. Approve Change Order No. 1 to Contract No. C30640 in the amount of $4,500 for the 2011 Curb Ramp Modification Project; 2. Authorize the transfer $4,500 from contingency to base; and 3. Authorize the Mayor to execute said Change Order No. 1. Background On April 28, 2011, City Council awarded Contract No. C30640 in the amount of $88,975 to Simon Contracting of Indio, California, for the 2011 Curb Ramp Modification Project to conform with current Americans with Disabilities Act (ADA) requirements. After award of the project, a resident contacted the Public Works Department regarding three locations where he consistently has trouble safely making the transition from the sidewalk to the street, and vice versa. The resident is confined to a wheelchair, and because the area has rolled curb, he has nearly fallen out of his chair on multiple occasions. Upon request of Public Works staff, Simon Contracting submitted a cost proposal in the amount of $4,500 for adding the three subject locations to the contract. Funding for this change order is within the contract contingency, which has already been approved by Council. Staff Report Approve Change Order No. June 23, 2011 Page 2of2 Fiscal Analysis 1 (Contract C30640) The initial contract amount was $88,975. This change order will increase the contract amount to $93,475. This is an on -going maintenance activity with no fiscal impact beyond the change order amount. Prepared By: Ryan Gayler/Iroiecinistrator Paul S. Gibson, Director of Finance z. City Manager Depa Mark Greenykood, P.E. Director of Public Works CITY COUNCILACJION APPROVED_____3/ ` DENIED RECEIVED OTI1E'R MEETING DATE 3- U( AYES: - NOES: l c tl tv ` ABSENT: 1,�'[)oe ABSTAIN: VERIFIED BY: - Original on File with City Clerk's�fl5ce G:IPubWorksIPROJECTS1753-11 2011 Curb Ramp Modification ProjechSR Approve C0#1 for Simon Contracting C30640.docx UITY OF EALM USERT CONSTRUCTION URANGE ORDER Contract Purpose 2011 Curb Ramp Modification Project (753-11) Consultant's Name Simon Contracting Address: P.O. Box 10990, Indio, CA 92202 Contract # / P.O. # Change Order No. Contingency: Account No. Project No. Vendor No. C30640 1 YESJ NO 110-4312-433-3320 753-11 9965 • You are herebv reauested to comDly with the followina chances from the contract nlans anti -,nPr-ifinatinnG- DESCRIPTION OF CHANGES DECREASE In Contract Price INCREASE In Contract Price Installtion of ADA Compliant Curb Ramps at 3 additional locations 3 ramps at $1,500 per ramp TOTALS: NET CHANGE IN CONTRACT PRICE: 4,500.00 - 4,500.00 4,500.00 JUSTIFICATION: During the course of the project a resident requested three additional ramps be included within the project. The resident is confined to a wheel chair and has difficulty in safely making the transition from the sidewalk to the street, and vice versa. TOTAL BUDGET FOR PROJECT: + $100,000 Less: Expend. & Encumb. To Date: - $88,975 Less: This Change Order Amount - $4, 500 BALANCE OF BUDGET REMAINING FOR PROJECT: 6,525.0011 NGENCY: Amount Approved by Counci I Less: Prior Change Order(s): Less: This Change Order: Balance Remaining of Contin + $8,898 - $0 $4,500 4,397.50 The amount of the Contract will be increased by the Sum of: Four Thousand Five Hundred Dollars and No Cents ($4,500.00). e GAPubWorks\PR0JECTS\753-11 2011 Curb Ramp Modification Project\Contract Change Order.doc See reverse ... Contract C30640 Change Order No. 1 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension 0 Days. Revised Contract Total $93,475.00 The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. REQUESTED BY: 2. ACCEPTED BY: 3. CERTIFIED FUNDS AVAILABLE: DEPARTMENT HEAD FINANCE DIRECTOR NOTE: No payments will be made prior to City Manager and Council approval CONTRACTOR Date Accepted 4. APPROVED BY: JEAN M. BENSON, MAYOR Date Approved CITY MANAGER Date Approved GAPu1bWorks\PR0JECTS\753-11 2011 Curb Ramp Modification Project\Contract Change Order.doc See reverse