HomeMy WebLinkAboutC26670A Change Order 1 Miscellaneous Drainage Improvements 520-05Contract No. C26670A
CITY OF PALM DESERT -
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: APPROVE CHANGE ORDER NO. 1 TO CONTRACT -NO. C26670A
WITH TRI-STAR CONTRACTING II FOR THE MISCELLANEOUS
DRAINAGE PROJECT (PROJECT NO. 520-05)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
CONTRACTOR: Tri-Star Contracting II, Inc.
15501 Little Morongo Road
Desert Hot Springs, California 92240
DATE: September 29, 2011
CONTENTS: Change Order No. 1
Recommendation
By Minute Motion:
1. Approve Change Order No. 1 to Contract No. C26670A in the
amount of $13,546.00 for the Miscellaneous Drainage Project;
2. Authorize the transfer $13,546.00 from contingency to base;
and
3. Authorize the Mayor to execute said Change Order No. 1.
Background
On June 9, 2011, City Council awarded Contract No. C26670A in the amount of
$996,972.70 to Tri-Star Contracting II of Desert Hot Springs, California, for the
Miscellaneous Drainage Project to improve five locations where nuisance or storm
water present risks to the City.
Shortly after award of this project, another location was identified where an existing
drainage system failed resulting in a large pool of standing water. The standing water
was located within the Haystack Greenbelt east of Calico Cactus Lane. Reports that
mosquitoes with West Nile Virus were found nearby prompted the Public Works
department to find an immediate solution. Tri-star Contracting provided a proposal to
construct an underground retention system with a clean -out structure. The City
Manager authorized Tri-Star to proceed with the construction of the system.
Staff Report
Approve Change Order No
September 29, 2011
Page 2of2
1 (Contract C26670A)
Funding for this change order is within the contract contingency, which has already
been approved by Council.
Fiscal Analysis
The initial contract amount was $996,972.70. This change order will increase the
contract amount to $1,010,518.70. The system that was constructed under this change
order will require periodic maintenance. The City already has a program for maintaining
water retention devices and this location will be added to the program. The
maintenance cost increase is negligible.
Prepared/Bye:
Ryan er, Pro Administrator
fol 'DMO JJ- UIU4 -
Paul S. Gibson4ij*to0of Finance
M. Wohlmuth, City Manager
Departm
Mark Greenw od, P.E.
Director of P blic Works
CITY COUNCIL ACTION
APPROVED ✓ DENIED
RECEIVED OTHER
MEETING DATE
AYES:
NOES: iJZ)Q'
ABSENT: _ N-0_
ABSTAIN: IJC� � -�
VERIFIED BY -
Original on File with City Clerk's ice
G:IPubWorks\Staff Reports120111September 29107 Approve CO 1 to C26670A Tri-Star for Misc Drainage ProjecASR Approve C0#1 for Tri-Star Contracting C26670A.docx
CITY OF PALM DESERT
CONSTRUCTION CHANGE ORDER
Contract Purpose Miscellaneous Drainage Project (520-05)
Consultant's Name Tri-Star Contracting If, Inc.
Address: 15501 Little Morongo Road
Desert Hot Springs, CA 92240
Contract # / P.O. #
Change Order No.
Contingency:
Account No.
Project No.
Vendor No.
C26670A
1
YE_Q
NO
420-4370-433-4001
520-05
11769
You are herebv reauested to comply with the followina chanaes from the contract clans and specifications:
DESCRIPTION OF CHANGES
DECREASE
In Contract Price
INCREASE
In Contract Price
Construction of undeground water retention system at Haystack Channel
TOTALS:
NET CHANGE IN CONTRACT PRICE:
13,546.00
-
13,546.00
13,546.00
JUSTIFICATION:
During the course of the project a drainage hazard was identified at the Haystack Channel. Due to the large volume
of stagnant water and the mosquito infected with West Nile Virus in close proximity the City Manager authorized the
construction of the underground water retention system.
OTAL BUDGET FOR PROJECT: + $1,100,000
Less: Expend. & Encumb. To Date: - $996,973
Less: This Change Order Amount: - $13,546
BALANCE CF BUDGET
REMAINING FOR PROJECT: 1 89, 481.30
CONTINGENCY:
Amount Approved by Council: + $99,697
Less: Prior Change Order(s): - $0
Less: This Change Order: - $13,546
Balance Remaining of Contingenc, . 86,151. 37
The amount of the Contract will be increased by the Sum of: Thirteen Thousand Five Hundred Forty -Six
Dollars and No Cents ($13,546.00).
G:\PubWorks\Staff Reports\2011\September 29\07 Approve CO 1 to C26670A Tri-Star for Misc Drainage Prcject\Contract Change Order No 1 520-05.doc See reverse
Contract C26670A Change Order No. 1
Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish
equipment and materials, and perform all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension 7 Days.
Revised Contract Total _ $1,010,518.70 .
The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract
price specified for each item including any and all supervision costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
REQUESTED BY: 2. ACCEPTED BY:
DEPARTMENT HEAD
3. CERTIFIED
FUNDS AVAILABLE:
FINANCE DIRECTOR
NOTE: No payments will be made prior
to City Manager and Council approval
CONTRACTOR
4. APPROVED BY:
JEAN M. BENSON, MAYOR
CITY MANAGER
Date Accepted
Date Approved
Date Approved
G:1PubWorks\Staff Reports120111September 29107 Approve CO 1 to C26670A Tri-Star for Misc Drainage Project\Contract Change Order No 1 520-05.doc See reverse ...