STAFF REPORT
REQUEST: REQUEST FOR ACCEPTANCE OF WORK FOR CONTRACT NO.
C29370C WITH COOLEY CONSTRUCTION, INC., AND RATIFY
THE CITY MANAGER'S APPROVAL OF PAYMENT FOR
ADDITIONAL WORK BY SLADDEN ENGINEERING FOR THE
COOK STREET DRAINAGE AND INTERSECTION
IMPROVEMENTS PROJECT (PROJECT NO. 505-03)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
CONTRACTOR: Cooley Construction, Inc.
PO Box 401810
Hesperia, California 92345
DATE: August 23, 2012
CONTENTS: Notice of Completion
Memo Dated March 28, 2012
Vicinity Map
Recommendation
By Minute Motion:
1. Accept the work as complete and authorize the City Clerk to file a
Notice of Completion for Contract No. C29370C, the Cook Street
Drainage and Intersection Improvements Project (Project No. 505-03);
2. Ratify approval by the City Manager for an additional payment to
Sladden Engineering for work requested by the City in the amount of
$16,581.70; and
3. Authorize the City Clerk to File the Notice of Completion.
Background
On February 24, 2011, City Council awarded Contract No. C29370C for the construction
of the Cook Street Drainage and Intersection Improvements to Cooley Construction,
Inc., in the amount of $2,581,205.00. Staff has inspected the work performed by the
contractor and has found said work to be complete and in, accordance with the contract
Staff Report
Request for Acceptance of Work (505-03) (Contract C29370C)
August 23, 2012
Page 2 of 2
requirements. The project was completed under budget and within the contract
allowable time.
To expedite the work during the holiday season, additional material testing and
inspection was necessary. Sladden Engineering was able to accommodate the City's
request and provide these services. In order to take advantage of the reduced traffic
levels during this time, the City Manager approved the additional work at a cost of
$16,581.70.
Fiscal Analysis
There is no fiscal impact associated with this action.
Prepared By:
Cora L. Gaugush
Capit mprovement Projects Technician
Paul S. Gibson, Director of Finance
Approval:
n M. Wohlmuth, City Manager
Depa
Mark qrebnwood, P.E.
Direct r bf Public Works
CITY COUNCIL ACTION
APPROVED DENITD
RECEIVED OTHER
MEETING DATE � .as ��'61��
AYES• "nwn-P-ne=A-,1 4mtill�. rnrn�on� Soi
NOES:'
ABSENT -
ABSTAIN:
VERIFIED BY:
Original on File with City Cler s Office
To be recorded with the Riverside County Recorder
within 10 days after completion and acceptance by
the City Council. NO RECORDING FEE PER
SECTION 6103 OF THE GOVERNMENT CODE.
When recorded, return to:
Office of the City Clerk
City of Palm Desert
73-510 Fred Waring Drive
Palm Desert, CA 92260
NOTICE OF COMPLETION
(Cal. Civ. Code § 3093 — Public Works)
NOTICE IS HEREBY GIVEN:
1. That the interest or estate stated in paragraph 3 herein in the real property herein described is SOLELY
OWNED by the CITY OF PALM DESERT, A MUNICIPAL CORPORATION, a political subdivision of the State
of California, and whose address is 73-510 FRED WARING DRIVE, PALM DESERT, CALIFORNIA, 92260.
2. That the full name and address of the owner of said interest or estate is set forth in the preceding
paragraph.
3. That the nature of the title of the stated owner, as set forth in paragraph 1, Fee.
4. That on the 23 day of August, 2012, a work of improvement described as Cook Street Drainage and
Intersection Improvements at Country Club Drive and Hovley Lane Ease, Contract No. C29370C on the real
property herein described was completed.
5. That the name of the original contractor, if any, for said work of improvement was: Cooley Construction
Inc, PO Box 401810, Hesperia, California 92345
6. That the real property herein referred to is situated in the City of Palm Desert, County of Riverside,
State of California, and is described as 39-900 to 41-500 Cook Street; 74-990 to 75-000 Country Club Drive;
and 74-990 to 75-000 Hovley Lane East.
Dated
CITY OF PALM DESERT
0
Robert A. Spiegel, Mayor
STATE OF CALIFORNIA )
) ss
COUNTY OF RIVERSIDE ) 11
I hereby certify that I am the City Clerk of the governing board of the CITY OF PALM DESERT, CALIFORNIA, the political subdivision
which executed the foregoing Notice and on whose behalf I make this verification: That I have read said Notice, know its contents, and
that the same is true. I certify under penalty of perjury that the foregoing is true and correct.
Executed at Palm Desert, California, on this day of 20
RACHELLE D. KLASSEN, CITY CLERK
Rev. Oct 02
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
INTEROFFICE MEMORANDUM
To: John W. Wohlmuth, City Manager
From: Mark Greenwood, P.E., Director of Public Works
Date: March 28, 2012
Subject: Cook Street Improvement Project/Sladden Engineering
During the construction of the Cook Street intersection improvements at Hovley Lane
East and Country Club Drive, staff expedited the work during the holiday season to take
advantage of reduced traffic levels. Sladden Engineering, the material testing
consultant for the project, incurred additional costs in the amount of $17,815.50 due to
expediting the work. Some of this additional cost may be recoverable from the general
contractor, Cooley Construction, and staff will pursue that as a separate matter.
Sladden's original contract was in the amount of $9,700.00 and there is $1,233.80
remaining on that purchase order. Therefore, the amount currently due to Sladden is
$16,581.70 and your authorization of this amount is requested. If you concur with this
recommendation, please sign below and return this memo to me and a contract
amendment will be prepared.
If you have any questions, please let me know.
Mark Gr a ood, P.E.
Directo of Public Works
/bl
Enclosures
Reviewed and Approved:
M. Wohlmuth, City Manager