HomeMy WebLinkAboutC31810 - CO1 - Hwy 111 Resurfacing 752-13 Contract No. C31810
CITY OF PALM DESERT
PUBLIC WORKS DEPARTMENT
STAFF REPORT
REQUEST: APPROVE CHANGE ORDER NO. 1 TO CONTRACT NO. C31810
WITH MATICH CORPORATION FOR THE HIGHWAY 111
RESURFACING PROJECT (PROJECT NO. 752-13)
SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works
CONTRACTOR: Matich Corporation, Inc.
P.O. Box 10
Highland, California 92346
DATE: June 13, 2013
CONTENTS: Change Order No. 1
Recommendation
By Minute Motion:
1. Approve Change Order No. 1 to Contract No. C31810 in the
amount of$109,070 for the Highway 111 Resurfacing Project;
2. Authorize the transfer $109,070 from contingency to base; and
3. Authorize the Mayor to execute said Change Order No. 1;
Funds are available in Account No. 213-4311-433-3320, Street Maintenance.
Backqround
On July 12, 2012, City Council awarded Contract No. C31810 in the amount of
$3,109,000 to Matich Corporation, Inc., of Highland, California, for the Highway 111
Resurfacing Project. The project will repave the street by grinding off the top two inches
of asphalt, and recycling the next three inches by cold-milling the existing asphalt
concrete, pulverizing it, and reusing it as base paving. After placing the base paving, a
two-inch surface course will be paved.
The project was scheduled to fit in a very tight timeframe in the fall of 2012 before the
seasonal residents returned to the City. However, there was concern that any delay in
the project could cause it to extend into the season. The City Manager was mindful to
avoid any construction work that would have required major traffic control along a
business corridor during the shopping season, especially in light of the Cook Street
Intersection Improvement project that ran through the winter season a few years ago.
Staff Report
Approve Change Order No. 1 (Contract C31810)
Page 2 of 2
June 13, 2013
The City Manager scheduled a meeting with Public Works staff and Matich Corporation
and requested that the contractor postpone the project until the summer of 2013. The
result of the meeting was that the contractor agreed to postpone the project if
consideration was given to the fact that over the course of a year prices for asphalt oil,
trucking, construction materials, and labor would tikely increase. The contractor
estimated that the increase over one year in a worst case scenario could be as much as
$300,000. This information was provided to Council in an informational item at the
September 27, 2012, Council meeting.
The City Manager agreed that the City would compensate the contractor for legitimate
cost increases using a method to be agreed upon by both parties. The contractor has
provided the City with the cost increases for specific cost centers, namely labor, freight,
material, and subcontractor costs. Those costs were transferred into bid items and
represent an increase of 2 cents per square foot for cold milling, 1 cent per square foot
for cotd-in-place recycling, and 4 cents per square foot for warm mix asphalt.
The proposed change order of $109,070 equals approximately 3.5 percent of the
$3,109,000 contract amount. By comparison, the Caltrans Asphalt Price Index rose
approximately 6 percent from the project bid date until now.
Fiscal Analvsis
The initial contract amount was $3,109,000. This change order will increase the
contract amount to $3,208,070. This street resurfacing project is being done as a part of
the City's annual Street Maintenance Program. There is no fiscal impact beyond the
change order amount.
Pre red By: Depart n H ad:
.�
Ry Gayle roject Administrator Mark Gree w od, P.E.
Director of Pu lic Works
CiTY COUNCIL ON
APPROVED DENiED
RECEIVED OTHER
Paul S. Gibson, Director of Finance
MF,ET DAT '� �
AYES: ��
Approval� NOCS:
AB5ENT:
ABSTAIN:
VERIFIED BY: U
J n . Wohlmuth, City Manager Original on File with City C{le k's Office
G:IPubWorkslStaff RepoRs12013Uune 13119 CO 1 to C31810 Matich Corp/or Hwy 111 Resur(acing P752-131SR Approve CO#1 for Matich Corp C31810.docx
��° rA� � ����'� Contract#/P.O.# C31810 18251
\��/i�
Change Order No. 1
�������������� ��,��� conengency: E NO
Contract Purpose Highway 111 Resurfacing Project nc�o��t n�o. 213-4311-433-3320
Consultant's Name Matich Corporation Prolect No. 752-13
Address: P.O. Box 10 ver,aor No. 279
Highland, CA 92346
You are hereby requested to comply with the following changes from the contract plans and speci�cations:
DESCRIPTION OF CHANGES DECREASE INCREASE
In Contract Price In Contrad Price
Increase unit price forcold mill asphalt by$.02 persquare foot 29,220.00
Increase unit price forcoid-in-plaoe recycling by $.01 per square foot 15,970.00
Increase unit price forwarm-mix by$.04 per square foot 63,880.00
TOTALS: - 109 0 70.00
NET CHANGE IN CONTRACT PRICE: 109 070.00
JUSTIFICATION:
Additional cost related to postponing the project approximately ten months.
OTALBUDGET FOR PROJECT: + 3,419,900.00 CONTINGENCY:
Less: Expend. 8 Encumb.To Dabe: - 3,109,000.00 Amount Approved by Council: + 310,900.00
Less:This Change Orcier Amount: - 109 070.00 Less: Prior Change Order(s): - -
BALANCE OF BUDGET Less: This Change Order: - 109 070.00
REMAINING FOR PROJECT: 201 830.00 Balance Remaini of Conti e 201 830.00
The amount of the Corrtract will be Increased by the Sum of: One hundred nine thousand seventv Dollars
($109,070.00).
See reverse ...
Contract C31810 Change Order No. 1 Continued from front
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, fumish
equipment and materials, and perfoRn all work as necessary or required to complete the Change Order items for a
lump sum price agreed upon befinreen the Contractor and the City of Palm Desert, otherwise referred to as Owner.
Contract Time Extension 0 Days.
Revised Contract Total $3,218.070.00
The undersigned Contractor approves the foregoing Change Order# 1 as to the changes, if any, in the contract
price spec�ed for each item including any and all supervisian costs and other miscellaneous costs relating to the
change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said
Change Order# 1 . The Contractor agrees to fumish all labor and materials and perform all other necessary work,
inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order
items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood
that the Change Order shall be effective when approved by the Owner.
Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies,
waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of
or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and
indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as
any and all consequential damages.
This document will become a supplement to the Contract and all provisions will apply hereto, all items included above
must have required signatures as per the purchase resolution.
1. REQUESTED BY: 2. ACCEPTED BY:
DEPARTMENT HEAD CONTRACTOR Date Accepted
3. CERTIFIED
FUNDS AVAILABLE: 4. APPROVED BY:
FINANCE DIRECTOR JAN C. HARNIK, MAYOR Date Approved
NOTE: No payments will be made prior
to City Manager and Council approval CITY MANAGER Date Approved
see reverse ...