Loading...
HomeMy WebLinkAboutC22310H - CO1 - Monterey Ave I-10 Intrchng Rmp Mdfctn 669-02W C5 Z WQ >_ <0 CC } ILI W I- CCZ W- H ZO 0' i G Z Q Contract Nos. C22310H CITY OF PALM DESERT PUBLIC WORKS DEPARTMENT STAFF REPORT REQUEST: APPROVE CHANGE ORDER NO. 1 TO CONTRACT NO. C22310H WITH POWELL CONSTRUCTORS, INC., RATIFY THE UTILITY COST TO IMPERIAL IRRIGATION DISTRICT (IID), AND INCREASE CITY MANAGER'S CONSTRUCTION CHANGE ORDER AUTHORITY FOR THE MONTEREY AVENUE AT INTERCHANGE 10 RAMP MODIFICATION PROJECT (PROJECT NO. 669-02) SUBMITTED BY: Mark Greenwood, P.E., Director of Public Works CONTRACTOR: Powell Constructors, Inc. 8555 Banana Avenue Fontana, California 92335 UTILITY CO.: Imperial Irrigation District La Quinta Division 81-600 Avenue 58 La Quinta, CA 92253 DATE: June 12, 2014 CONTENTS: Change Order No. 1 Vicinity Map Recommendation By Minute Motion; 1. Approve Change Order No. 1 to Cantractor C22310H for the construction of the Monterey Avenue at I-10 Ramp Modification Project (Project No. 669-02) to Powell Constructors, Inc., of Fontana, California; 2. Authorize the Mayor to execute Change Order No. 1; 3. Ratify the $70,125.71 utility cost paid to IID and approve the remaining final fee in the amount of $56,087.23; and 4. Increase City Manager's authority to approve construction change orders up to fifty percent of the approved contingency. Funds are available in Account No. 213-4389-433-4001, Monterey Avenue at I-10 Ramp Modification. Staff Report Approve Change Order No. 1 to Contract C23310H - Monterey at i-10 Page 2 of 3 June 12, 2014 Backqround On January 23, 2014, City Council awarded Contract C23310H to Powell Constructors, Inc., (Powell) in the amount of $7,037,417.35 and approved a 10 percent contingency. The Notice to Proceed was issued on March 31, 2014. Powell has been working diligently with property owners and various government and utility agencies. In reviewing the current field conditions, the construction management consultant has discovered that several contract items were overestimated or were no longer necessary. Also, Powell has proposed different form liner for the rabbit imprint on the tieback walls. This resulted in a net credit of $167,312.87. Unfortunately, the contractor has encountered some unforeseen conditions as well, such as an increase of contract bid item amount for the shoulder rumble strip, removal and reconstruction of 4-foot shoulder, upsizing the signal pole as the original specified pole was inadequate, the need for temporary lighting installation, the removal of recently Caltrans installed concrete barrier and an unidentified underground abandoned vault which were not identified on the approved plans and specifications. The total cost for these items is $160,996.74. This will result in a credit of $6,316.13 so the revised contract with Powell is $7,031,101.22. IID is the electrical provider for this project. To date the City has paid a total of $71,125.71. Additional invoices in the amount of $56,087.23 are now due. Staff has met with IID again recently and has been assured that they are working diligently to provide the services to the project without causing delay. Due to the amount of utility costs, staff requests Council ratify the $71,125.71 paid to IID and approve the remaining fee. In anticipation of the potential to cancelled council meetings in July and August, staff requests that the City Manager be given the authority to approve construction change orders up to fifty percent of the approved contingency for the duration of the project to avoid any potential delay claim by the contractor. The project is approximately twenty percent complete. Any change orders approved by the City Manager will be brought to City Council for ratification at the next available meeting. Fiscal Impact This fiscal impact associated with this action results a small credit with Powell construction contract, additional IID required fees, and the potential of additional Change Orders as appropriate and approved by the City Manager. Staff Report Approve Change Order No. 1 to Contract C23310H - Monterey at I-10 Page 2 of 3 June 12, 2014 Prepared By: Department Head: /� c� � L � � � Bo Chen, P.E., City Engineer Mark Greenwood, P.E., Director of Pubiic Works CITY COUNCIL�TION APPROVED DENfED Paul S. Gibson, Director of Finance RECEIVED OTHER MECTI G DAT "� '���� Approval: AVFs: ?1 ��d1 �/ �'� NOES: � � � ABSCNT: � �4. AI3STAIN: G� VCRIFIED BY: ohn M. Wohlmuth, City Manager Original on File with City rk's Office � ,l CITY QF PALM DESERT Contract#/P.O.# C22310H Change Order No. 1 CONTRACT CHANGE ORDER Contingency: YES N� Contract Purpose Monterey Avenue at I-10 Ramp Modification Account No. 232-4383-433-4001 Consultant's Name Powell Constructors, ItIC. Project No. 669-02 adaress: 8555 Banana Avenue Vendor No. Fontana, California 92335 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE Su lemental Plans, S ecifications, and Directives dated Attached In Contract Price In Contract Price 1. No cost change to incorporate lane closure hours - - 2. Decrease/delete contract items at contract unit price: Item 3 - Residence Engineer's Office 63,750.00 Item 207 - COZEEP Contract 69,426.00 Item 208 - Traffic Management Plan 25,000.00 3. Extra work to relocate existing fence to property line & clearing landscape and hardscape within right of way. 18,108.26 4. Extra work to remove and dispose of existing concrete barrier constructed by Caltrans recently but not shown on the approved plans. 19,964.34 5. Extra work for removal conc barrier & reconstruction barrier anchor. 14,731.50 6. Extra grinding/overlaying of ex median, reconstruct shoulder, increase rumber strip 35,653.00 7. Substitute the specified elastrometric multiple use form liner with plastic form � 9,136.87 liner for the rabbit imprint on the tieback walls. 8. Temporary lighting installation that the plans & specifications didn't include 72,539.64 TOTALS: 167,312.87 160,996.74 NET CHANGE IN CONTRACT PRICE: 6,316.13 JUSTIFlCATION: In reviewing the contract plans, it is discovered that several contract bid items were over-estimated or no long needed to complete the project. Also, contractor proposed to substitute the fracture rib texture architecture form liner which results in a total credit of $167,312.87. Upon review of the plans and specifications, there are some legitimate extra works that the contractor entitles as outlined above. TOTAL BUDGET FOR PROJECT: + 7,037,417.35 CONTINGENCY: Less: Expend. & Encumb.To Date: - 7,037,417.35 Amount Approved by Council: + 703,741.73 Less: This Change Order Amount: 6,316.13 Less: Prior Change Order(s): - BALANCE OF BUDGET Less: This Change Order: - REMAINING FOR PROJECT: 6,316.13 Balance Remainin of Contin enc : 703,741.73 The amount of the Contract will be decreased by the Sum of: Six Thousand Three Hundred Sixteen and 13/100 Dollars ($6,316.13). See reverse ... Contract C22310H Change Order No. 1 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension 0 Days. Revised Contract Total ___ _�7,031,101.22 . The undersigned Contractor approves the foregoing Change Order # 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order # 1 . The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONTRACTOR Date Accepted 3. CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR VAN G. TANNER, MAYOR Date Approved NOTE: No payments will be made prior to City Manager and Council approval CITY MANAGER Date Approved See reverse ...