PALM DESERT HOUSING AUTHORITY
STAFF REPORT
REQUEST: APPROVE CONTRACT AMENDMENT NO. 1 IN THE AMOUNT OF
$34,855 TO VANIR CONSTRUCTION MANAGEMENT, INC.,
(CONTRACT NO. HA 25760A) FOR CONTINUED CONSTRUCTION
MANAGEMENT SERVICES FOR THE LAGUNA PALMS RENOVATION
PROJECT
SUBMITTED BY: MARTIN ALVAREZ, REDEVELOPMENT MANAGER
CONTRACTOR: VANIR CONSTRUCTION MANAGEMENT, INC.
290 NORTH D ST., SUITE 900
SAN BERNARDINO, CA 92401
DATE: NOVEMBER 8, 2007
CONTENTS: CONTRACT AMENDMENT NO. 1
VANIR CONSTRUCTION MANAGEMENT, INC. PROPOSAL
Recommendation:
By Minute Motion, that the Housing Authority:
1. Approve Contract Amendment No. 1 in the amount not -to -exceed $34,855 to
Vanir Construction Management, Inc., (Contract No. HA 25760A) San
Bernardino, California, for continued construction management services for
the Housing Authority property known as Laguna Palms Renovation Project;
and
2. Authorize Chairman to execute said amendment.
Funds are available in Account No. 871-8610-466-4001.
Executive Summary:
Approval of the staff recommendation will allow Vanir Construction Management, Inc., to
continue construction management services beyond their original contract term and through the
completion of the Laguna Palms Renovation Project projected for January 2008. Vanir has
provided a proposal to amend their current contract in the amount of $34,855 to continue to
monitor the construction project, assist with Request for Information, negotiate change orders
and facilitate construction progress meetings through project closeout.
Discussion:
At its regular meeting of December 14, 2006, the Palm Desert Housing Authority authorized
award of contract to Vanir Construction Management, Inc., for construction management
services at the Laguna Palms Renovation project.
Staff Report
Approval of Contract Amendment No. 1 to Contract HA25760A — Laguna Palms Rehab
Page 2of2
November 8, 2007
The Laguna Palms project is now 75% complete and is scheduled for completion in January
2008. As part of the renovation process, staff has encountered unforeseen conditions including
structural modifications requiring re -engineering to bring the buildings into full compliance with
new building codes. In addition, minor interior modifications to floor plans, the addition of a fire
sprinkler protection system, and a complete rewire of all units has impacted the completion
date. Therefore, staff is requesting approval of an amendment to the construction management
services contract in the amount of $34,855 to allow Vanir Construction Management to continue
to oversee the construction through project completion.
The original contract total plus the proposed Amendment No. 1 of $34,855 for construction
management services rendered on the Laguna Palms Project is 3.3% of the overall contract
price, which is well within industry standards for construction management services.
The additional term and cost will take us through completion of the project to include closeout.
Based on the additional scope of work added to this project, staff recommends approval of the
amendment for construction management services with Vanir Construction Management.
Submitted by:
, 4(artin Alvarez, Redevelopment Manager
a et oore, Director of Housing
Department Head:
eve Yrig n, Dir. Red./Housing
/./1/,‘h
Carlos L. Ortega, Eacutive Director Paul S. Gibson, director of Finance
Approval:
F1development
4 L "C-BY HOUSG AUTH - 0
ON /J�
VERIFIED BY: ( ` /T77 1
Original on file with City Clerk's Office