APPROVE CHANGE ORDER NO. 6 TO CONTRACT NO.
HA-25760 (PORTRAIT HOMES, INC.) IN THE AMOUNT OF
$115,072.27 FOR SITE MODIFICATIONS AND EXTENDED
GENERAL CONDITIONS FOR THE HOUSING AUTHORITY
PROPERTY KNOWN AS LAGUNA PALMS
MARTIN ALVAREZ, REDEVELOPMENT MANAGER
PORTRAIT HOMES, INC.
265 N. JOY ST., STE. 200
CORONA, CA 92879
MARCH 27, 2008
CHANGE ORDER NO. 6 TO CONTRACT HA-25760
By Minute Motion, that the Housing Authority:
1. Approve Change Order No. 6 to Contract No. HA-25760 with Portrait
Homes, Inc., in the cumulative amount of $115,072.27 for items not
included in the original contract and extended general conditions;
2. Authorize the Chairman to execute the said documents;
3. Authorize the Finance Director to transfer $60,864.92 from
contingency to base for Change Order No. 6; and
4. Appropriate $54,207.35 to base contract from unobligated housing
funds.
Executive Summary:
The Laguna Palms rehabilitation project is substantially complete, with only minor punch
list items remaining. Approval of staffs recommendation will authorize Change Order
No. 6 in the amount of $115,072.27 to address minor site modifications not included on
the plans and close out negotiations with Portrait Homes for extended general
conditions (overhead & supervision) associated with project delay. The proposed
modifications will finalize the project and improve the project's over-all quality. Attached
please find a summary table with itemized costs:
Staff Report
Approve Change Order No. 6 to Contract No. HA-25760 — Laguna Palms Renovations
Page 2 of 4
March 27, 2008
DESCRIPTION
Concrete Work
Cool deck application at pool, grounding of new deck,
ADA transition at northeast corner of property
ADA Pool Lift: Required by Building Department
Drainage Modifications:
Installation of drainage improvements to properly receive
drainage from the southwest section of the property
Block Wall Modifications:
Remove and replace damaged section of west perimeter
block wall
Modifications to south wall (remove exposed footing and
loose blocks)
Extended General Conditions:
[60 Days ($1,365/Day)
Cumulative Total:
Discussion:
COST
$9,900.00
10,000.00
$3,617.57
$4,050.20
$5,604.50
$81,900.00
$115,072.27
The 48-unit Laguna Palms is substantially complete with only minor punch list items
remaining. Change Order No. 6 will close out Contract HA-25760. The proposed
change order consists of minor site modifications and finalizes contract negotiations
regarding extended general conditions for project delays associated with structural
redesigns/modifications and the additional scope of work to improve project safety.
Concrete Work / Site Modifications:
The concrete surrounding the pool requires application of cool decking material. This
material reduces the temperature of the deck surface and reduces slipping. In addition
to the cool deck, the Building Department requires that we properly ground the new
deck (eliminates transmission of electricity). The final item in this category includes
minor concrete work associated with creating a new ADA transition (between street and
new sidewalk) at northeast corner of property. The total cost to provide these
improvements is $9,900.00.
ADA Pool Lift:
In an effort to enhance the accessibility of the pool for occupants with disabilities, the
Building and Safety Department requires that we install an ADA pool lift that will allow
individuals with a disability to access the pool. The cost for the lift is estimated at
$10,000.00.
G\rda\Martm Alvarez\Laguna Paims\CO\032708C06PortraitHomesLP doc
Staff Report
Approve Change Order No. 6 to Contract No. HA-25760 — Laguna Palms Renovations
Page 3 of 4
March 27, 2008
Drainage Modifications:
This category consists of the installation additional drainage boxes and grates with
underground pipe to properly receive drainage at the southwest section of the project.
After installation of final grading at this location, the Public Works Department required
additional mitigation to properly handle drainage. The cost to implement this change
totals $3,617.57.
Block Wall Repairs / Modifications:
The modifications under this category consist of repairs to a 15 linear foot section of the
existing west perimeter wall, installation of a screen gate to conceal a utility box and the
cleanup of an exposed footing area at the south perimeter wall.
During site inspections, staff and the construction manager identified a large crack in
the existing west perimeter wall. This was noticed prior to the contractor applying the
final stucco coat. Staff believes that the damage may have been caused by the
construction occurring on the adjacent parcel. The cost to repair this 15 linear foot
section of wall is $4,050.00. Staff has contacted the adjacent property owner and is
seeking reimbursement for this damage. In order to avoid delay on the stucco finish,
staff requested that the contractor make the repairs.
The second modification under this category consists of cleaning up of an exposed
footing along the existing south perimeter wall and repairs to blocks to receive the
stucco finish. This work will improve the aesthetics of the project and totals $5,604.50.
Extended General Conditions:
The Laguna Palms rehabilitation project under Contract HA-25760 was scheduled to be
complete in September 2007. Due to unforeseen structural redesigns to both the single
and two story structures, the addition of various new scopes such as a fire sprinkler
system and new electrical wiring created impacts to the project's original completion
date.
The structural modifications were required by the Building and Safety Department and
Engineer to comply with today's Code. The addition of a fire sprinkler system and new
electrical wiring also required redesigns, but improved the project's safety. These items
created impacts to the contractor's extended general conditions (overhead, supervision
and administration). Although the approved change orders addressed the costs of
these upgrades, the contractor's extended general conditions were not included.
The Contractor has requested consideration of extended general conditions for the six-
month delay. Staff and the Construction Manager believe that the Contractor should be
given consideration for a maximum of 60 days for extended general conditions. The
G:\rda\Martin Alvarez\Laguna Palms\CO\032708CO6PortradHomesLP doc
Staff Report
Approve Change Order No. 6 to Contract No. HA-25760 — Laguna Palms Renovations
Page 4of4
March 27, 2008
original schedule of values identifies a monthly overhead and supervision cost of
$40,950 ($1,365/day). This two -month acknowledgement for extended general
conditions has been negotiated by our Construction Manager and totals $81,900. If the
item is approved, the following conditions would apply:
• Completion of all punch list items by March 28, 2008 (assess liquidated damages
if project not complete).
• Authorize legal counsel to draft an agreement containing language requiring a full
and final release for all claims associated with Contract HA-25760.
Staff and our Construction Manager have reviewed the proposed change order and
recommend approval. On March 12, 2008, the Housing Commission reviewed this item
and recommended approval. Therefore, staff is requesting approval of Change Order
No. 6 in the amount of $115,072.27. The proposed change order will bring the project
to completion. Staff recommends that the remaining $60,864.92 from contingency be
transferred to the base contract, and an additional $54,207.35 be appropriated from
unobligated housing funds.
Submitted by:
Martin Alvarez, Redevelopment Manager
Department Head:
iz}
JandM>loore, Director of Housing
Approval:
Department Head:
��ave YrigofDir. of Red./Housing
development
Carlos L. Orte, Executive Director Paul S. Gibson, Director of Finance
42proved BY HOUSG AUTH 5-0
ON 3-{ -1--0?
VERIFIED BY: _'DK
Original on file with City Clerk's Office
G:\rda\Martin Alvarez\Laguna Palms\CO\032708C06PortraitHomesLP.doc
LAGUNA PALMS - INTERIOR & EXTERIOR REHAB
SUMMARY OF CONTRACT CHANGE ORDERS
CONTRACTOR: PORTRAIT HOMES, INC. CONTRACT NO. HA25760
871-8610-466-4001
ORIGINAL CONTRACT
ORIGINAL CONTINGENCY
ORIGINAL TOTAL
CO # Change Order Description
1 Add fire sprklr, deduct wall, repair
headers, const closet walls, cabnts
2 Deduct subfloor, wiring, alcoves, trim, headers,
cleanouts. Add framing, abatement, structural
3 Deduct for bldg ext change. Adds for plumbing,
concrete, fixtures, and accessories
4 Block wall', plumbing & misc upgrades
not included in original contract
5 Add'I fencing, drainage modifications. flooring
6 Concrete work, ADA pool lift, drainage modif.,
block wall mods., extended gen'I conditions
TOTALS
CONTRACT
Change
Order
Amount
693,530.98
289,124.84
16,085.95
115,774.31
144,699.98
115,072.27
$ 1,374,288.33
% of
Contract
13.74%
5.73%
0.32%
2.29%
2.87%
2.28%
27.22%
Original Appropriation Allocated to THIS CONTRACT
not to entire 71ect)
$ 5,047,924.00
Revised
Contract
Total
5,741,454.98
6,030,579.82
6,046,665.77
6,162,440.08
6,307,140.06
6,422,212.33
For Internal Use Only - DO NOT SEND TO VENDOR
$ 504,792.00
$ 5,552,716.00
FUNDING
Additional
Appropriations
allocated to THIS
CONTRACT
693, 530.98
121,758.00
54,207.35
Contingency
Balance for this
contract
504,792.00
215,667.16
199, 581.21
83,806.90
60,864.92
g/rda/Beth Longman/Staff Reports/Portrait Homs LP CO Log