HomeMy WebLinkAboutHA29410B CO10 Carlos Ortega Villas 825-11 Contract No. HA294106 PALM DESERT HOUSING AUTHORITY STAFF REPORT REQUEST: APPROVE DEDUCTIVE CHANGE ORDER NO. 10 TO CONTRACT NO. HA294106 WITH OPTIMUS CONSTRUCTION, INC., IN THE AMOUNT OF $13,133.35 FOR CONSTRUCTION OF THE CARLOS ORTEGA VILLAS (PROJECT NO. 825-11) SUBMITTED BY: Heather Buck, Project Coordinator CONTRACTOR: Optimus Construction, Inc. 440 Western Avenue, Suite 202 Glendale, CA 91201 DATE: May 14, 2015 CONTENTS: Change Order No. 10 Recommendation By Minute Motion, that the Authority Board: 1. Approve deductive Change Order No. 10 to Contract No. HA294106 in the total amount of $13,133.35 for the Carlos Ortega Villas (Project No. 825-11); and 2. Authorize the Chairman to execute Change Order No. 10. Funds are available in Account Nos. 871-8691-466-4001 and 703-8691-466-4001, Capital Improvements, for this purpose. Commission Recommendation The Housing Commission reviewed the recommendation at the regularly scheduled meeting of May 13, 2015. Staff will provide a verbal report upon request of the Authority Board. Backqround On July 10, 2014, the Authority Board authorized award of the contract for construction of the Carlos Ortega Villas to Optimus Construction, Inc. The Notice to Proceed was issued on September 4, 2014. Construction is anticipated to be completed in November 2015. This change order is a deductive change order — an overall credit back to the Housing Authority. This Change Order incorporates the following. Costs for the additional work, credits to the Authority and materials are within industry standards. • Reduced quantity of landscape screens (Credit) • Clerestory roofing material change required to maintain warranty (Credit) Staff Report Approve CO No. 10 to Contract No. HA29410B (Optimus)for the COV project Page 2 of 2 May 14, 2015 • Electrical material change (Credit) • Pool Heater substitution — improved efficiency and aesthetics • Additional fire stopping required by Building Code � Additional insulating materials in attic space— improved efficiency • Plumbing fixture modification Fiscal Analvsis Below is a summary of the approved and proposed change orders: Descri tion Contin enc Contract Ori inal Contract $1,542,335.13 $15,423,351.39 Previousl A roved Chan e Orders $287,550.61 $287,550.61 Chan e Order No. 10 $13,133.35 $13,133.35 Revised Contract Total $1,267,917.87 15,697,768.65 If Change Order No. 10 is approved, total Change Orders to date represent 1.78 percent of the contract. The estimated costs for the project are listed on ROPS lines 171 and 186. Although the Housing Authority will initially advance the funds for this work, the SARDA may reimburse the Authority for the costs from bond proceeds. The 2007 Housing Set-Aside bond issuance included the Carlos Ortega Villas as a project in the bond covenants. As a requirement of the State Department of Finance, a Bond Proceeds Funding Agreement was approved to facilitate this purpose by the Oversight Board on October 7, 2013, and by the Authority Board on October 10, 2013. Submitted By: Y Heather Buck, Projec oordinator Jan M. Moore, Director of Housing � Martin Alvarez Rudy osta, Assistant City Manager Director of Economic Development Rev' . �����SY HOUSG AUTH Paul S. Gibson, Director of Finance �N S�l�"�r S rov : VERiFIED �SY; � ���:�C� ' `nal on #i!e vvi�h City Clerk's Offic� � f�rog� hn M. Wohlmuth, Executive Director N O OO O � � � O � I� N I� Ln fq CD f� M e- �- � � 00 ln 00 U pCOp �+s O Cfl � N � CO 00 M � � I� � V "'' .., � N N O N N � N N 00 •-- (D � 0 U �-- � � 00 � M N lI� DO I� � Q�'� � N f� CV � N � � �-- c'M � f� H C�O C N "-' M N � I� I� (D � ln ln CO Z � �. U � � tn � � � � � �t N N N O � C7 O t0 V � � � �- e- � � � � c- c- � � Z V m 2 EA � �- U Z o .� M � cn o � N - a-°i ui � � .g � U � � ch c -- o � V � M O ,N O � � N � p� Z r- Q O � � n. � � � O � � a Q O U Q N C � N _ � � N � NOOMMNI� tnO � O Q M � � N (DMM � MCOO (O � •"' � � � M I� 00 00 M N 00 O fn Z Q � 'p j � � CD o0 � � QO CO � O (D � � M N �p N N 00 N M M � 00 � f� � W � c M •N ..`s +�-� M OO M � M � CO � � O I� Z � . N > C OMMf� 00 � O � N �- � � W � ,rn � � O H � d d' � � � lf) � I� I� Cfl � � � � �n � U �ri �ri �ri � �n �ri ui �ri �ri �ri �ri � Z � � � � � � � � � �- � � � N � O c� � � Z U o 0 0 0 0 0 0 0 0 0 0 o Z J Q o 0 0 � � � � � o 0 0 � W Q � = V I� M M � N I� 00 � N � � 00 (n 2 �j w �p O O N •-- O O O O N O O f� � � � V � \ C O O O O O O O O � O O � � Q ~ � U Z W U c � � � '� p � � ~ � MNO� Cfl � 0 � � o0 �� Cp ' d (n O r t!') 00 � � CO O 1� N N CO M N �+ W O N '�t M � N M e- � ln � N M f� C � J V = N ` C � � O N I� O N I� O CO M e- � � � � � N � � 1� O (O c'� � O f� f� �� � � U O = � L 'v � O � M CO c'M � � �` 0~O � � � � Q � V v � ¢ � v N �a o g a � ` �. � � Z � � � 0 � � 0 � � rn O V O � � � LL � Q � "' ani � N L ~ � U 'C � T C �� V N Z (0 O � Z f- uvi ,tS 3 � .c .� o � QW a� a� ca � u� C� � c � 'o •� � � io rn � Z J N F� � � � � � � c�e Z Z � � •� � c c � � .c � � t O O Q O n o :.. o � � � � y U U H � � rn =o u�°i .a- c � ° � o J J J C '�- � � N L � � � Z Z Z L f0 p O O � � � � n' (� � U o � d V � � .` � Q � � � � a�i o o- o � � � � � N .N O u O 00 � in � cna � � w0 � � � E � � � o J Q � N M � tn (p I� 00 � � � L U a� m � �v � rn CITY OF PALM DESERT Contract#/P.O.# H�94,og P019255 Change Order No. 9 CONSTRUCTION CHANGE ORDER Contingency: YES No Contract Purpose Carlos Ortega Villas Account►vo. 871'8691-466-4001 703-8691-466-4001 ConsultanYs Name Optimus Construction Inc. P�oiecc No. 825-11 add�ess: 440 Western Avenue, Suite 202 vendor►vo. 13425 Glendale, California 91201 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE Optimus COR Nos. 15-R2, 17, 30, 34-R1, 35, 37 In Contract Price In Contract Price Reduced quantity of landscape screens 1,558.78 Clerestory roofing material change 19,054.16 Electrical material change 6,607.00 Pool heater substitution 5,175.39 Additional fire stopping 3,530.52 Additional insulating materials in attic space 4,735.97 Wall hung lavatory in Maintenance Building 644.71 TOTA LS: 27,219.94 14,086.59 NET CHANGE IN CONTRACT PRICE: 13,133.35 JUSTIFICATION: Credits and additions to the scope of the contract. OTAL BUDGET FOR PROJECT: + 15,697,768.65 CONTINGENCY: Less: Expend. & Encumb. To Date: - 15,710,902.00 Amount Approved by Council: + 1,542,335.13 Less: This Change Order Amount: - 13,133.35 Less: Prior Change Order(s): - 287,550.61 BALANCE OF BUDGET Less:This Change Order: - 13,133.35 REMAINING FOR PROJECT: 0.00 Balance Remainin of Contin enc : 1,267,917.87 The amount of the Contract will be Decreased by the Sum of: Thirteen Thousand One Hundred Thirty-three and 35/100 Dollars ($13,133.35). G:\PubWorks\PROJECTS�825-11 Carlos Ortega Villas\Staff Reports�2015-05-14 SR-Optimus OCO 10\Contract Change Order No.10.docx See reverse ... Contract HA29410B Change Order No. 10 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension -0- Days. Revised Contract Total $15,697,768.65. The undersigned Contractor approves the foregoing Change Order No. 10 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order No. 10. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of productivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONTRACTOR Date Accepted 3. CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR SUSAN MARIE WEBER, CHAIRMAN Date Approved NOTE: No payments will be made prior to Executive Director and Housing Authority approval EXECUTIVE DIRECTOR Date Approved G:\PubWorks\PROJECTS�825-11 Carlos Ortega Villas\StaH Reports�2015-OS-74 SR-Optimus OCO 10\Contrect Change Order No.t0.docx See reverse ...