HomeMy WebLinkAboutHA29410B - CO12 - COV 825-11 Contract No. HA29410B PALM DESERT HOUSING AUTHORITY STAFF REPORT REQUEST: APPROVE CHANGE ORDER NO. 12 TO CONTRACT NO. HA294106 WITH OPTIMUS CONSTRUCTION, INC., IN THE AMOUNT OF $9,384.77 FOR CONSTRUCTION OF THE CARLOS ORTEGA VILLAS (PROJECT NO. 825-11) SUBMITTED BY: Heather Buck, Project Administrator CONTRACTOR: Optimus Construction, Inc. 440 Western Avenue, Suite 202 Gle�dale, CA 91201 DATE: September 10, 2015 CONTENTS: Change Order No. 12 Recommendation By Minute Motion, that the Authority Board: 1. Approve Change Order No. 12 to Contract No. HA29410B in the total amount of$9,384.77 for the Carlos Ortega Villas (Project No. 825-11); 2. Authorize the transfer of$9,384.77 from contingency to base; and 3. Authorize the Chairman to execute Change Order No. 12. Funds are available in Account Nos. 8718691-4400100 and 7038691-4400100, Capital Improvements, for this purpose. Commission Recommendation The Housing Commission reviewed the recommendation at the regularly scheduled meeting of September 9, 2015. Staff will provide a verbal report upon request of the Authority Board. Backqround On July 10, 2014, the Authority Board authorized award of the contract for construction of the Carlos Ortega Villas to Optimus Construction, Inc. The Notice to Proceed was issued on September 4, 2014. Construction is on schedule and anticipated to be completed in December. This Change Order incorporates revisions to the following items: light fixtures, monument signage, and tile. Costs for the additional labor and materials are within industry standards. Staff Report Approve CO No. 12 to Contract No. HA29410B (Optimus) for the COV project Page 2 of 2 September 10, 2015 Fiscal Analysis Below is a summary of the approved and proposed change orders: Descri tion Contin enc Contract Ori inal Contract $1,542,335.13 $15,423,351.39 Previousl A roved Chan e Orders $287,187.71) $287,187.71 Chan e Order No. 12 $9,384.77 $9,384.77 Revised Contract Total $1,245,762.65 $15,719,923.87 If Change Order No. 12 is approved, total Change Orders to date represent 1.92 percent of the contract. The estimated costs for the project are listed on ROPS lines 171 and 186. Although the Housing Authority will initially advance the funds for this work, the SARDA may reimburse the Authority for the costs from bond proceeds. The 2007 Housing Set-Aside bond issuance included the Carlos Ortega Villas as a project in the bond covenants. As a requirement of the State Department of Finance, a Bond Proceeds Funding Agreement was approved to facilitate this purpose by the Oversight Board on October 7, 2013, and by the Authority Board on October 10, 2013. Submi ed By: � � Heather Buck, P �ect Administrator ane . Moore, Director of Housing �� Martin Alvarez Rudy A osta, Assistant City Manager Director of Economic Development Review : �,v�d(5 D gr� HQUSG AUTH a-�v-��-'j' Paul S. Gibson, Director of Finance ON �Cpp v I: VERIFI�D BY: R�� r 1� � � ('�riginal on fiite with City C1erk's 4fficF J M. Wohlmuth, Executive Director cn a v c�o (� � �j � � Cfl CO 00 �l � U'I l� W N � O O # � 3 -� � � � � Om � � vcn � tn � 00 O � � � n� �' �" � � � m n � -o o � Z7 �l �l ° � o � D �, � _ = � � C� � � G� G� � � � c �' � N � (n < p o 0 v � Z Z Z � ;U O � �D N �• i� °- � o c�i 2 Q n�i � � � � � o �' �� � �' � _ � � � � -�a � O O O y �. f� � 7 � N n � N 7 = N cn N � n O � Z Z � v fD fp � � n D --I � co � ui n�i °' D � o �' � � r Z D (7 `° = � � � n�i m � '� � m n O a � � � 7 0 � (A � Z � Z � � n �, � � � _. n � � � v � 0 � - � 3 Q v � n � � p � `�° � � C� O � � - O � cn r C � � � � '0 � � O � D C� n 3 � � N � � � C co � � � � � � c,,� � � c -< n � -{ N � CD N W^ �I �I N --• W � U� � O O Q � � N O D D � � W �I -• CD �l �l O � W � O �J � � � (Q O �T'I O J Oo �l W � O �I N O �J N O -� CO � � ,1 � � N A O W N � U1 CO -� W N � W �A � 3 (7 fT1 '�G �A �l � W � N N �I O � A A 00 U1 �N-► O � � 00 �I U1 Ui U1 Oo CJi CD O CJi � 00 N W C Z O � �v � O � O � � C� o D � Z � � ? n m Z O -' 00 .0 .0 � 00000000 � � � '� � "'� CO O O O O N O O O O -� N O O � � � n D = y N � 00 CD --� N U1 00 �l N --• W W �l ,.n.t � 2 G D � � � � � � � � � � � � � � D � m o 0 0 o a o 0 0 0 0 0 0 0 0 � � 0 � � � � � � � � � � � � � � � � � m O cn cn cn cn cn cn cn cn cn cn cn cn cn n � cn O � O C � � � � � ininin � � A � �. � o c� � �� � � m —� —� co � � n� —� oc000 � wwo � < ry v coo � o -� � rn � wcflwoow ,-.. .-• �' D Z CD U1 �I CO OD --� W W N Oo N N CJi � � (D W � � � � rvwrnornrnoocncnoorncnA � Q- cn D O w ca oo ry � w ao 00 � w -� cfl cn � � z � oo � a> oo� w � wwa> iv � ifl i,.� � O �! O C,Ti O U1 �I N W W O� N 1�. N Cp � ' 1 � � � � v � n � � � O � � � N � D o ' � � a� a p � D o � � o: iv � 0 00 y o � � w c� v � _ ° � � o � � � cn C c,.� c� o Z � � v � _ v z `� � , � _a � .� � � � _a � .� � � � � � � 7 � rn O N N N N N A A A A �A A Ul U1 � C� (p Z � (J� � Cn Cn � � � �l �l CO N W .�« (D 7 p) � Ul CJ1 �l A W � Cfl � N U1 N �I N � �,� U1 D �I � Cfl �l Oo U� N W !� OD A A -� (") � � � � 00 N N CO N N O N N �A '" o n 0�0 N V V A --� W OD 00 CD N Ul � O 3� � � � J� 0� U1 00 � �A � � 00 W �I � (A� U7 C7� N �l N �l CJi O CO CD � O O� O N PALM DESERT HOUSING AUTHORITY contract ts l P.o.st HA294106 P0112010 Change Order No. 12 CONSTRUCI'ION CHANGE ORDER Contingency: YES rvo Contract Purpose Carlos Ortega Villas Account►vo. 8718691-4400100 7038691-4400100 ConsultanYs Name Optimus Construction Inc. P�oiecc No. 825-11 ,add�ess: 440 Western Avenue, Suite 202 vendor No. 13425 Glendale, California 91201 You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE Optimus COR Nos. 31, 51, 52, and 55 In Contract Price In Contract Price Monument redesign and primary and secondary ID signage 3,614.63 Light fixtures at cabinets 559.18 Building address lighting 3,069.87 Tile at restrooms 2,141.09 TOTALS: - 9,384.77 NET CHANGE IN CONTRACT PRICE: 9,384.77 JUSTIFICATION: Additions to the scope of the contract. TOTAL BUDGET FOR PROJECT: + 15,719,923.87 CONTINGENCY: Less: Expend. & Encumb. To Date: - 15,710,539.10 Amount Approved by Council: + 1,542,335.13 Less: This Change Order Amount: - 9,384.77 Less: Prior Change Order(s): - 287,187.71 BALANCE OF BUDGET Less: This Change Order: - 9,384.77 REMAINING FOR PROJECT: 0.00 Balance Remainin of Contin enc : 1,245,762.65 The amount of the Contract will be Increased by the Sum of: Nine Thousand Three Hundred Eight-four and 77/100 Dollars ($9,384.77). G:\PubWorks\PROJECTS\825-71 Carlos Ortega Villas\Staff Reports�2015-09-10 SR-Optimus OCO 12\Contract Change Order No.12.docx See reverse ... Contract HA29410B Change Order No. 12 Continued from front This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon between the Contractor and the City of Palm Desert, otherwise referred to as Owner. Contract Time Extension -0- Days. Revised Contract Total $15,719,923.87. The undersigned Contractor approves the foregoing Change Order No. 12 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order No. 12. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Change Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the Owner. Execution of this Change Order by the Contractor constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Change Order, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, loss of praductivity, and stacking of trades, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONTRACTOR Date Accepted 3. CERTIFIED FUNDS AVAILABLE: 4. APPROVED BY: FINANCE DIRECTOR SUSAN MARIE WEBER, CHAIRMAN Date Approved NOTE: No payments will be made prior to Executive Director and Housing Authority approval EXECUTIVE DIRECTOR Date Approved G�\PubWorks\PROJECTS\825-71 Carlos Ortega Villas\StaH Reports�2015-09-10 SR-Optimus OCO 12\Contract Change Order No.12.tlocz See reverse ...