HomeMy WebLinkAboutHA35180 - Deck Improvements at Candlewood ApartmentsREQUEST:
PALM DESERT HOUSING AUTHORITY
STAFF REPORT
AUTHORIZE STAFF TO NEGOTIATE WITH RYDER INC. FOR CONTRACT
NO. HA-35180 FOR DECK IMPROVEMENTS AND RELATED SERVICES AT
CANDLEWOOD APARTMENTS
SUBMITTED BY: Veronica Tapia, Management Analyst II
CONTRACTOR: Ryder, Inc.
1950 Compton Avenue, Suite 113
Corona, CA 92881
DATE: May 12, 2016
CONTENT: Ryder, Inc.'s Proposal dated May _, 2016
Water Analysis Report dated April 27, 2015
Location Map
Recommendation
By Minute Motion, that the Authority Board,
1. Authorize staff to negotiate with Ryder, Inc. for Contract No. HA-35180 for deck
improvements and related services at Candlewood Apartments.
Monies are available in the FY 2015/2016 Palm Desert Housing Authority's replacement reserve
budget.
Housing Commission Recommendation
The Housing Commission will review this item at its meeting of May 11, 2016. A verbal report will be
provided.
Strategic Plan Obiective
This request does not apply to a specific strategic plan goal.
Executive Summary
The decks at Candlewood Senior Apartments are a major deferred maintenance item that needs to be
addressed immediately. Listed on the 2009 reserve study as a project to be completed in 2009, it is a
priority to complete now that we have the authority to do so. Monies have been set aside in the capital
replacement fund specifically for this purpose.
Backaround
The Reserve Study done by Association Reserves, Inc. in 2009 for the Palm Desert Housing Authority
identified several improvements that needed to be made immediately at Candlewood Apartments to catch
up on deferred maintenance inherited with the purchase of the senior community. Soon after their
recommendation, the redevelopment agency was eliminated along with our ability to let any new
contracts. In the interim, the management company has been arduously repairing items as needed;
however the condition of the decks has deteriorated greatly.
In November, 2014, the management company, housing staff, and a city building inspector walked the
property to determine the severity and extent of the scope of the project. The deterioration of the decks in
many places throughout the property were obvious, but what lay beneath was in question. Since this was
STAFF REPORT
Palm Desert Housing Authority — Negotiate Contract with Ryder, Inc.
May 12, 2016
Page 2
CONTRACT NO. HA-35180
flagged as a potential Health and Safety issue, the Executive Director authorized staff to hire a
professional services consultant to design plans in order to ensure all requirements were being met and
all issue were being addressed with the best solution possible.
The plans were drawn and submitted for approval to the Building Department. Plans were approved in
October, 2015. With the new laws going into effect soon after regarding the Department of Industrial
Relations (DIR) registration and prevailing wage requirements; staff worked diligently alongside legal
counsel to develop bid documents specific to the Housing Authority's needs and requirements and were
able to complete that process in March, 2016.
On April 1 and 5, 2016, staff published a notice in the Desert Sun requesting sealed bids for the deck
improvements. Bids were to be opened on April 22, 2016. There were five parties on the plan holders
list, nonetheless, no bids were received. Ryder, Inc (formerly Woods Construction, Inc.) did not submit a
bid because they were informed prior to the close of bidding that any bid could be subject to rejection.
Because of Ryder's initial work, Ryder's bid could potentially give Ryder an unfair advantage over the
other bidders. However, since there were no other bidders, there is no further issue with hiring Ryder.
Staff has confirmed that Ryder has maintained its interest in performing the work at Candlewood.
Ryder, Inc. has done work with the Housing Authority in the past to our satisfaction. Therefore, staff
believes it to be in the best interest of the senior community and the project to proceed with negotiations
to complete the deck improvements at Candlewood Apartments.
The project is expected to commence upon the successful negotiation with Ryder. Staff will bring back a
request to approve a contract for this work.
Fiscal Analysis
The fiscal impact of this contract is the cost of the contract itself plus 10% contingency (for unforeseen
conditions and permit fees). Although currently unanticipated, there may also be minimal costs
associated with temporary relocation of tenants during construction.
Sub ed by:
Veronica Tapia, Management Analyst II
Approval:
stin McCarthy, Executiv
Department Head:
Moore, Director •f H•
(1 BY HOUSG AUTH
ON_T h 1 'I
tor VERIFIED BY:.02.`ki
lJ
Original on file kivith City Clerk's OfficF
�1vi6 .-1(IMik,joyd-1iti1,Tanner, CL-04U,�I,�
*Gs " &Ion e_
G \rda\Veronica Tapia\Word Files\PDHA\Candlewood Decks\2016 Award Contract HA_ to Ryder, Inc for CDI 5-12-16 Rev by BBK.doc
Weather Impact and Water Infiltration Analysis Report
Candlewood Apartments
Palm Desert, California
Prepared for:
Woods Construction
1950 Compton Avenue, Suite 113
Corona, California 92881
Ph: (951) 371-8368
Contact: Mark Woods
Prepared by:
WJRB Consulting & Design
P.O. Box 1877
Rancho Cucamonga, California 91729
Ph: (909) 215-0955
Contact: Wayne J. R. Bowser
April 27, 2015
Table of Contents
Section 1: Executive Summary 1
1.1- Purpose and Methods of Analysis 1
1.2 - Project Summary 1
1.3 - Standard Building Practices 1
Section 2: Locale and Environmental Conditions 2
2.1- Project Location 2
2.2 —Weather 2
Section 3: Impact Analysis 2
3.1— Findings 2
3.2 — Recommendations 3
Section 4: Photographs 4
4.1- Damaged Surface 4
4.2 - Guardrail Attachments 5
4.3 - Ponding Water 6
4.4 - Exposing Structure 7
4.5 - Weathered Beams 9
4.6 — Flashing 9
i
1 EXECUTIVE SUMMARY
1.1 PURPOSE AND METHOD OF ANALYSIS
This weather impact and water infiltration analysis was prepared to determine what extent of damage
has been caused to the exterior wood framed members of the complex and what corrective measures
could be implemented, along with remedies to repair weather and water rotted structural elements, and
to prioritize the needed repairs. The assessment was conducted on April 12, 2015 under the direction of
Mark Woods, General Contractor, license #678131, who supervised the demolition and removal of
building components, and Peter Vander Meyden, Professional Engineer, license #C-35611, who observed
and documented, along with Wayne J. R. Bowser, who documented with dimensions and photographs.
Several areas of the common elevated walkways had stucco, sheathing, and or, decking removed to
expose the structural elements for evaluation of their conditions. Not all structural elements of the
complex were exposed.
1.2 PROJECT SUMMARY
It was determined that a majority of the common elevated walkways and their associated structural
elements had significant damage caused by years of water infiltration and replacement of said structural
elements are recommended. It was also determined that attempts had been made to correct said water
damage by adding additional layers of sheathing, and/or, bituminous material on top of the existing
decking and common elevated walkways, which initially may have solved some issues, but seemingly
created other problems where water ponding eventually developed, causing further means for standing
water to infiltrate into the structural elements already impacted by the weather. Several areas of concern
were also identified, which did not pertain to the walking surfaces, but rather the roof structures over the
stairs. The exposed wood beams showed considerable weather damage.
1.3 STANDARD BUILDING PRACTICES
There are numerous methods, and materials used to construct a building similar the subject property, but
because this was built of wood and stucco, the variables only occur depending in which time period it was
built. It is presumed that the buildings were constructed over 40 years ago, and building practices have
changed tremendously, particularly accounting for seismic activity, and more recently, weather protection.
It is unknown whether or not the addition of new weatherproofing, as mentioned above, was inspected
by a third party, but it is clear that standard flashing and the implementation of weep screeds at the base
of the stucco walls, for instance, were not utilized, as were common practices even 40 years ago. It has
become standard practice only recently, however, to eliminate, as much as possible, the attachment of
any guardrail directly to the deck, thus penetrating the weatherproofing. This penetration ultimately
causes water infiltration, and in the case of every elevated walkway, the direct connection of the guardrail
support members to the deck has caused a damming effect, and thus water remains upon its surface in
numerous locations along said elevated walkway.
1
2 LOCAL AND ENVIRONMENTAL CONDITIONS
2.1 PROJECT LOCATION
The Candlewood Apartments are located at 74000 Shadow Mountain Drive in the City of Palm Desert,
California. The property is the southern portion of the city, on 1.32 acres, south of Highway 111. The
nearest major cross street is Portola Avenue and Highway 111.
2.2 WEATHER CONDITIONS
Palm Desert has an arid climate with an average high temperature of 89 °F (32 °C) and average annual low
of 62 °F (17 'C). The area is comprised of a gently south -sloping valley, surrounded by high mountain
ranges on three sides. This creates a unique micro -climate which keeps the average night-time
temperatures in the winter significantly warmer than most desert around the world. Summer time highs
are commonly above 108 °F (42 °C) and sometimes exceed 120 °F (49 °C). Average precipitation is under
5 inches (130 mm), with over 348 days of sunshine.
Due to these above normal high temperatures throughout the year, day and night, common building
materials expand more frequently and become pliable to the extent that water, even though rainfall is at
a minimum, has more opportunity to infiltrate areas that typically remain sealed for a longer period of
time.
3 IMPACT ANALYSIS
3.1 FINDINGS
3.1.1 Decks / Elevated Walkway Surfaces
A. All deck surfaces show signs of wear, and in several places the deck is cracking and missing
the top layer of bituminous material, causing water infiltration within the structure.
B. The entire leading edge surface, or drip edge, lacks any kind of metal drip flashing, or has been
covered over by stucco, causing water to infiltrate into the stucco and the structure.
C. The leading edge surface, or drip edge, which has the guardrail support bolted through it, is
causing water to sit behind it and potentially seeps in through the decking.
D. There are several low spots causing water to pool. Although this generally does not adversely
impacts the structural integrity, unless it is near one of the aforementioned cracks, or missing
surface material, it does pose a nuisance to the residents, and a potential slipping hazard.
E. In all situations where the decking material meets the front door of the residences, the
threshold has had to be modified to accommodate the additional height, where the top
surface of the decking now appears to be higher than the finish floor of the individual dwelling
unit.
F. Where the decking surface extends beyond the 5 to 5-1/2 foot wide elevated walkway, and
into what appears to be a somewhat individual front porch for each unit, and where the
decking surface meets the abutting wall surface, the stucco screed is non-existent, or covered
2
up, resulting in very little flashing area to screed water away from the wall, resulting in
potentially a situation where water can infiltrate the structure.
3.1.2 Beams and Structural Members
A. All beams along the outer perimeter of the elevated walkways and bridges appear to have
some level of water damage, however, these beams were not all exposed during our site
assessment.
B. Several locations where the decking material and sub -flooring were removed and the
structure exposed, it was discovered that there was some water damage to the structural
members that join the elevated walkway, and bridge structure to the support beams.
C. The double beam supports for the roof structure over each of the three stairways showed
severe weathering due to exposure and lack of maintenance.
3.2 RECOMMENDATIONS (TO FINDINGS IN SECTION 3.1)
3.2.1 Decks / Elevated Walkway Surfaces
A. All deck and elevated walkway surfaces shall be removed down to the last two layers of Y2"
plywood sub -floor and a new waterproof surface applied, which shall be sloped to provide
positive drainage of any water along the surface.
B. Apply 26 gauge metal drip flashing and counter -flashing along edges of elevated walkways,
decks and bridges.
C. All existing guardrail shall be removed and a new guardrail design implemented to eliminate
the attachment of vertical supports to the top surface of the elevated walkways and decks.
D. All deck and elevated walkway surfaces shall be removed down to the last two layers of /2"
plywood sub -floor and a new waterproof surface applied, which shall be sloped to provide
positive drainage of any water along the surface.
E. All deck and elevated walkway surfaces shall be removed down to the last two layers of Y:"
plywood sub -floor and a new waterproof surface applied, which shall be sloped to provide
positive drainage of any water along the surface. Remove and replace threshold as necessary
to accommodate new deck surface.
F. All deck and elevated walkway surfaces shall be removed down to the last two layers of/2"
plywood sub -floor and a new waterproof surface applied, which shall be sloped to provide
positive drainage of any water along the surface. Install new 26 gauge metal flashing along
wall, where new deck surface meets wall.
3.2.2 Beams and Structural Members
A. Beams with noticeable water damage and/or rot shall be replaced.
B. Structural members with noticeable water damage and/or rot shall be replaced
C. All beams shall be removed and replaced with one single beam at each of the three stair
locations, and fastened to the existing columns with beam hangers welded in place.
3
STRUCTURAL GUARD RAIL CALCULATIONS.
CANDLEWOOD APARTMENTS, PALM DESERT, CA 4/21/15
DESIGN LOADS
CODE GUARD RAIL REQUIREMENTS
200 LB ANY WHERE
50 PLF ALONG LENGTH OF GUAF
PROJECT ADDITIONAL REQUIREMENT.
RAIL SYSTEM NOT DROOP OVER TIME DUE TO DEAD LOAD
ADDED A CENTER POST TO REDUCE THE SPAN OF EACH SECTION
EST WT OF RAILING IS 30 PLF
PROJECT DESIGN DICTATED A 3" TO 3-1/2" WIDE SECTION
AN HSS 3 X 2 X 1/8 SECTION WAS SELECTED FOR USE AS BOTH
THE TOP AND BOTTOM RAIL
HSS SECTION PROPERTIES
Ix = 1.30
Sx = 0.866
Iy = 0.692
Sy = 0.692
Fy = 36 KSI
Fb = 21.6 KSI
E = 2900 KSI
RAIL SPAN 14.75'/2 = 7.4'
200 LB LOAD M = 370 FT -LB
50 PLF LOAD M = 342 FT -LB
30 PLF LOAD M = 205 FT -LB
REQUIRED SECTION
Sx = 0.205 OK
Sx = 0.190 OK
Sy = 0.113 OK
CHECK DEFLECTION
GOVERNING LOADS
50 PLF LOAD DEFL = 0.096" OK TOP RAIL ONLY (Ix)
30 PLF LOAD DEFL = 0.054" OK BOTH RAILS (Iy)
POST LOAD @ TOP
50 PLF LOAD
200 LB LOAD
P = 370 LB GOVERNS
P = 200 LB
POLE HT = 3.5' M = 1295 FT -LB
TRY HSS 3 X 3 X 1/8
Sx = 1.19
Ix = 1.78
CHECK POLE DEFLECTION
50 PLF LOAD DEFL = 0.177" OK
REQUIRED SECTION
Sx = 0.719 OK
4 PHOTOGRAPHS
4.1 DAMAGED SURFACE
The elevated walking surface is cracked in several places and missing pieces of the bituminous material.
4
4.2 GUARDRAIL ATTACHMENTS
The guardrail supports are attached directly, causing water to dam and penetrate the walking surface.
5
4.3 PONDING WATER
The residual effects of standing water causes further damage and potentially creates a slipping hazard.
6
4.4 EXPOSING STRUCTURE
The stucco and surface material was removed to reveal structural damage due to water infiltration.
7
4.5 WEATHERED BEAMS
The structural members at each of the three stairs shows obvious signs of damage caused by exposure.
4.6 FLASHING
Lack of flashing and proper installation methods is causing additional water damage to develop over time.
9
LARREA ST
SHADOW
``G
\Z
sp
A
CHICORY ST CHICORY ST
3AV VNVII
•
LARREA ST
1011
CANDLEWOOD ST
b' VNV1NV7
Candlewood
Deck Improvements
7
CHICORY ST
ohm EP
VICINITY MAP
Candlewood
Deck Improvements
VICINITY MAP