Loading...
HomeMy WebLinkAboutHA35590A - CO1 - Plumbing Svcs at One Quial Pl Bldg 30CONTRACT NO. HA35590A PALM DESERT HOUSING AUTHORITY STAFF REPORT REQUEST: RATIFICATION OF CHANGE ORDER NO. 1 TO CONTRACT NO. HA- 35590A WITH VINCOR CONSTRUCTION, INC. FOR RE-ROUTING PLUMBING SERVICES AT ONE QUAIL PLACE BUILDING NO. 30 SUBMITTED BY: Jessica Gonzales, Senior Management Analyst - Housing CONTRACTOR: VINCOR Construction, Inc. 2707 Saturn Street Brea, CA 92821 DATE: November 10, 2016 CONTENTS: VINCOR Construction, Inc. Proposal (dated September 14, 2016) Change Order No. 1 to Contract No. HA35590A Recommendation By Minute Motion, that the Housing Authority Board, 1) Ratify the Executive Director's approval of Change Order No. 1 to Contract No. HA35590A with VINCOR Construction, Inc., for re-routing plumbing at One Quail Place building No. 30 in the total amount not to exceed of $8,735.80; and 2) Authorize the Palm Desert Housing Authority Chairman and/or the Executive Director to execute any contracts and any documents necessary to effectuate the actions taken herewith. Monies are available in the FY 2016/2017 Palm Desert Housing Authority's ("Authority") capital replacement budget. Housing Commission Recommendation The Housing Commission will receive the recommendation as informational at its regular meeting of November 9, 2016. Strategic Plan Objective: This request does not apply to a specific strategic plan goal. Executive Summary Acceptance of the Executive Director's approval will ratify field verified changes, and additional work to the scope of Contract No. HA35590A for the mobilization and completion of the re- routing plumbing services at One Quail Place Building No. 30. Staff Report Ratify Change Order No. 1 to Contract No. HA35590A - VINCOR Construction, Inc. November 10, 2016 Page 2of2 Background On July 28, 2016, the Palm Desert Authority Board ("Authority Board") authorized the award of Contract HA-35590A to Vincor Construction, Inc. ("Vincor"), in the amount of $70,116.00 plus 10% contingency in the amount not to exceed $7,012.00 (for unforeseen changes) for re-routing plumbing services at the Palm Desert Housing Authority ("Authority") owned residential property One Quail Place on Building No. 30 (the "Project"). As part of the request, the Authority Board authorized the Executive Director to review and approve written requests for the use of the contingency in the amount of $7,012.00 for unforeseen changes. Vincor started the Project and realized additional investigation of the water lines was needed which was not included in the original cost, in the amount of $975.00. During the investigation, Vincor found that the hot water servicing the residential units in Building No. 30 also serviced Buildings No. 29 and 31. Isolation of valves to the buildings was required on the original scope of work, however, isolating the valves to the individual units was not included and the cost is $1,250.00. Additionally, there was an adjustment in material cost due to differing existing water line sizes. Staff has used a price sheet provided from United Pipe and Steel Corporation to quantify the additional cost for the pipe size difference; and has determined the cost to be in the amount of $6,510.80. The Executive Director approved all additional costs in the total amount of $8,735.80. The original approval included re-routing plumbing services at One Quail Place for Buildings No. 30, 19, 22 and 40, estimated not to exceed $308,511.00. Instead, the additional re-routing of plumbing services for Buildings No. 19, 22 and 40 will be put out to bid and will be brought to the Authority Board for consideration at a future meeting. The proposed additional cost has been determined to be reasonable and in accordance with the Project scope of work and conditions. Therefore, staff recommends that the Authority Board ratify the Executive Director's approval of Change Order No. 1 to Contract No. HA35590A with VINCOR Construction, Inc., for re-routing plumbing at One Quail Place building No. 30 in the total amount not to exceed of $8,735.80. Fiscal Analysis The fiscal impact is the Change Order No. 1 cost of the re-routing of plumbing at One Quail Place in the total not -to -exceed amount of $8,735.80 which will be paid from the FY 2016/2017 Housing Authority's capital replacement budget. Submitted by: De•artment He-d: - a Gonzalesy..S�nior Management Analyst Approv Lauri Aylaian, Executive Director Moore, Director of Housing 414". da6o3Y HOUSG AUTH ON "—in --UP VERIFIED BY: O-CA"--I rl►r-t Original on file with Citv Clerk's OfficF V INC OR CONSTRUCTION INC. 2707 Saturn St. Brea, CA 92821 TEL 714-528-2900 PAX 7/4-528-2901 E-,11.4IL: john�a rincorinc.com September 14, 2016 City of Palm Desert 73-510 Fred Waring Drive Palm Desert, CA 92260 Attn: Jessica Gonzales Re: 8 Unit Plumbing Repairs - COR #1 Unforeseen Main Line POC Scope of Work: General Conditions: 1. Investigate and locate existing lines serving (8) units at Building 30 using line locator. Identify and mark each line on site. Existing boiler that feeds Building 30 feeds building 29 and 31. 2. Excavate and trench to expose existing 2 '/z" main line point of connection located at Boiler Room. 3. "french and install approx.. (440') of new 2" supply and return copper line with insulation to feed building 30 & 31 from boiler room to building POC. 4. Trench and install approx.. (360') of new 1 '/z" supply and return copper line with insulation to feed building 29 from boiler room to building POC. 5. Provide (4) penetrations through building to feed existing building 30 units. Locate and tie in to existing line to feed 2nd floor units. 6. Existing I-1W & CW lines to be capped and abandoned. 7. Provide and install (3) new yard box located at the exterior point of connections for building 29, 30 and 31. 8. Backfill and compact trench as required with existing soil. Clari fications: Any additional work due to unforeseen conditions will be treated as a supplemental to the work order. Excludes wall, floor and ceiling repairs, any finishes and new fixtures. All work to be executed as per Request for Proposal (RIP), Plumbing Re -pipe Services for Building 30 at One Quail Place dated 7/19/16. Prevailing wages apply including DIR Requirements. TOTAL = S16,675 Breakdown: Investigation & Utility Locate - $975 Excavation, Backfill & Compaction - $6,750 (Approx. 320') - Plumbing 2 '/z" Copper 11W POC - S1,000 - Plumbing 2" Copper - $7,050 (Approx. 440') Plumbing 1 ''/ " Copper - S4,650 — (Approx. 360') - Isolation Valve & Box - $1,250 — (Exterior yard box and shut off valve to feed buildings (3) locations for new plumbing line — interior shut off valves included in base proposal) - Credit Demo to Expose HW (-S2, 000) Credit Demo to Expose CW — (-Si, 000) — Partial Credit for Concrete Demo Still need to expose CW line for POC. - C'redit Plumbing I " Main POC' HW (-S2, 000) Please note main proposal includes to saw cut and demo existing concrete slab at (8) small locations (4ea CW , 4ea I IW) of the interior units to expose existing 1" water line and to cap, excavate and backfill the exposed hole locations only. Reference base proposal DSOW 46 and #7. PALM DESERT HOUSING AUTHORITY CHANGE ORDER NO. 1 Contract Purpose Consultant's Name Address: PDHA One Quail Place Reroute Plumbing Bldg No. 30 VinCor Construction, Inc. 2707 Saturn Street Brea, CA 92821 Contract # / P.O. # Amendment/ Change Order No. HA-35590A 1 Contingency: I YES X I NO Account No. I Project No. I Vendor No. I You are hereby requested to comply with the following changes from the contract plans and specifications: DECREASE INCREASE In Contract Price In Contract Price DESCRIPTION OF CHANGES Increase the Base Contract total amount by $8,736.00 for inclusion of unforseen scope of work to include: 1. Investigate and locate existing hot and cold water lines 2. Provide and install three (3) isolation valves and box for Building No. 30, 29 and 31. 3. Increase in material cost (change in copper water supply line from 1" to 1 1/2" and 2 1/2" respectively). TOTALS: NET CHANGE IN CONTRACT PRICE: JUSTIFICATION: TOTAL BUDGET FOR PROJECT: + 77,128.00 Less: Expend. & Encumb. To Date: 70,116.00 Less: This Change Order Amount - 8,735.80 BALANCE OF BUDGET REMAINING FOR PROJECT: (1,723.80) n/a CONTINGENCY: Amount Approved by Council: Less: PriorAmendment(s): Less: This Amendment: Balance Remaining of Contingency: $975 $1,250 $6,510.80 8,735.80 8,735.80 The amount of the Contract will be increased by the Sum of: Eight Thousand Seven Hundred Thirty -Five Dollars and Eighty Cents ($8,735.80). Page 1 G \HOUSING\Jessica Gonzales\HOUSING AUTHORITI'\CONTRACTS\Vincor\HA35590A - VINCOR_O Q Place Bldg 30 Re-routing Plumbing Change Order No 1 doc Contract HA-35590A Change Order No. 1 Continued from Page 1 This Contract Change Order No. 1 covers changes to the subject contract as described herein. The consultant shall perform all work, furnish equipment and materials as necessary or required to complete the Change Order No. 1 items for a lump sum price agreed upon between the Contractor and the Palm Desert Housing Authority, otherwise referred to as Owner. Contract Time Extension -0- Days. Revised Contract Total $78,851.80 The undersigned Consultant approves the foregoing Change Order No. 1 as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order No. 1. The Consultant agrees to furnish all labor and materials and perform all other necessary work, inclusive of that directly or indirectly related to the approved time extension, required to complete the Contract Change Order No. 1 items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Contract Change Order shall be effective when approved by the Owner. Execution of this Contract Change Order No. 1 by the Consultant constitutes a binding accord and satisfaction that fully satisfies, waives, and releases the Owner from all claims, demands, costs, and liabilities, in contract, law or equity, arising out of or related to the subject of the Contract Change Order No. 1, whether known or unknown, including but not limited to direct and indirect costs and/or damages for delay, disruption, acceleration, and loss of productivity, as well as any and all consequential damages. This document will become a supplement to the Contract and all provisions will apply hereto, all items included above must have required signatures as per the purchase resolution. 1. REQUESTED BY: 2. ACCEPTED BY: DEPARTMENT HEAD CONTRACTOR 3. REVIEWED BY: 4. APPROVED BY: FINANCE DIRECTOR LAURI AYLAIAN, EXECUTIVE DIRECTOR Date Approved NOTE: No Extra Work is to be completed without prior written approval by both parties INTERIM EXECUTIVE DIRECTOR Date Approved G \HOUSING\Jessica Gonzales\HOUSING AUTHORITY\CONTRACTS\Vincor\HA35590A - VINCOR_O O Place Bldg 30 Re-routing Plumbing Change Order No 1 doc